Welcome to the California Public Utilities Commission (CPUC) website for SCE's Valley
South 115 kV Subtransmission Project (Valley South). This website will provide information on the status of the CPUC's environmental review
of the project under the California Environmental Quality Act (CEQA). SCE submitted an application for a Permit to Construct Electrical Facilities
with Voltages between 50 kV and 200 kV to the CPUC on December 15, 2014. Concurrently, SCE also filed its Proponent's Environmental Assessment (PEA)
for the project on this date.
This website provides access to public documents and information relevant to the CEQA review of the Valley South project. The application and
Proponent's Environmental Assessment, included below, are currently under review by the CPUC.
Application
Proponent's Environmental Assessment
Background
The Valley South project is proposed to be located in southwestern Riverside County.
The documents noted above provide more detail regarding the proposed location
and key components of the project. A summary of the proposed project is provided below:
- Modification of SCE's existing Valley 500/115 kV Substation would include equipping an existing 115 kV line position and providing protection
equipment as required.
- Construction of a new 115 kV subtransmission line originating at SCE's existing Valley 500/115 kV Substation and connecting at a Tubular
Steel Pole (TSP), which is located at the southeast corner of Leon Road and Benton Road. The TSP is the common point of the three-terminal
existing Valley-Auld-Triton 115 kV Subtransmission Line. The new construction and associated reconfiguration would result in the formation
of the Valley-Auld No. 2 and Valley-Triton 115 kV Subtransmission Lines. The new 115 kV subtransmission line would be approximately 12 miles
in length and is referred to as Segment 1 of the Proposed Project.
- Replacement of a segment of overhead conductor of the existing Valley-Auld-Triton 115 kV Subtransmission Line beginning at the TSP located at
the southeast corner of Benton Road and Leon Road continuing
south to the Terminal TSP located on the south side of Nicolas Road, approximately 250 feet west of Los Chorus Ranch Road in the City of Temecula.
This reconductor segment is approximately 3.4 miles in length and is referred to as Segment 2 for the Proposed Project.
- Relocation of existing distribution and telecommunication lines would be required to support the installation of Segments 1 and 2 for
the new 115 kV subtransmission line.
- Installation of telecommunication equipment at Triton and Valley Substations would support Segments 1 and 2 for the new 115 kV
subtransmission line.
For Additional Information
The CPUC, through its Environmental Review Team, will be conducting an environmental review of the project. To request additional
information or to be added to the mailing list, please contact us by phone or email, as follows:
Project Voicemail: (888) 400-3930
Project Email: Valley-South-Project@aspeneg.com
The CPUC's Project Manager is:
Eric Chiang, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
|
|