Welcome to the California Public Utilities Commission (CPUC) website
for the environmental review of a proposed 500-kilovolt (kV) transmission
line from the Antelope Substation in northern Los Angeles County
to the Pardee Substation in the City of Santa Clarita. Southern
California Edison (SCE) submitted an application for a Certificate
of Public Convenience and Necessity (CPCN) for this project to the
CPUC on December 9, 2004. SCE has also submitted an application
for a Special Use Easement to the USDA Forest Service. The proposed
project is subject to review under both the California Environmental
Quality Act (CEQA) and National Environmental Policy Act (NEPA).
This site provides access to public documents and information relevant
to the CEQA and NEPA review processes.
Background
SCE has filed applications with the CPUC and the Forest Service
to construct a new, 25.6-mile 500-kV transmission line between SCE's
existing 220-kV Antelope and Pardee substations in Los Angeles County,
California. The proposed 500-kV transmission line would replace
an existing 66-kV line that traverses the majority of the proposed
route between the Antelope and Pardee substations, including approximately
13 miles within the Angeles National Forest (ANF). The proposed
500-kV transmission line route traverses an area of residential
development in the Santa Clarita Valley area to the north and east
of the existing Pardee Substation. The 500-kV transmission line
would be energized initially at 220 kV. The proposed project
would include electrical interconnections at the existing Antelope
and Pardee substations as well as an initial expansion of the Antelope
Substation and relocation of several existing 66-kV subtransmission
lines in the vicinity of the Antelope Substation (collectively,
referred to as the Antelope-Pardee 500-kV Transmission Line Project).
The proposed project also includes the acquisition and fencing of
approximately 31 acres of land necessary for the upgrade of the
Antelope Substation from 220 kV to 500 kV.
Maps of the proposed transmission route can be viewed at the links
below:
Map 1 Map
2 Map 3 Map
4
Aerial Photo of Santa Clarita
Area
Proponent's Environmental Assessment
(PEA)
As part of its application to the CPUC, SCE prepared and submitted
a Proponent's Environmental Assessment (PEA), which describes the
proposed project, existing environmental conditions in the project
area, and potential environmental impacts. The December 2004 PEA
may be viewed here.
Notice of Preparation and Project
Scoping
The CPUC on June 24, 2005, issued a Notice of
Preparation of an Environmental Impact Report (EIR) for the
Antelope-Pardee 500-kV Transmission Line Project, including a map
of the project area. In addition, the Forest Service published
a Notice of Intent to prepare an Environmental
Impact Statement (EIS) for the proposed project. The CPUC and the
Forest Service have agreed to prepare a joint EIR/EIS for the proposed
project to satisfy the requirements of CEQA and NEPA.
The CPUC and the Forest Service will hold two Public Scoping Meetings
to solicit input from the public on potential impacts of the proposed
project that should be addressed in the Draft EIR/EIS. The Scoping
Meetings will be held at the following locations:
EIR/EIS Public Scoping Meetings
|
June 29, 2005
6:30 p.m. to 8:30 p.m.
Desert Inn Hotel
44219 Sierra Highway
Lancaster, CA 93534
(661) 942-8401
July 14, 2005
6:30 p.m. to 8:30 p.m.
City of Santa Clarita Activities Center
20880 Centre Point Parkway
Santa Clarita, CA 91350
(661) 250-3703
|
Scoping comments for the EIR/EIS must be postmarked or received
by fax or e-mail no later than July 29, 2005.
Scoping comments should be sent to:
CPUC/ USDA Forest Service
c/o Aspen Environmental Group
30423 Canwood Street, Suite 215
Agoura Hills, CA 91301
Fax: (661) 215-5152
E-mail: antelope-pardee@aspeneg.com
Draft
Environmental Impact Report/Environmental Impact Statement
The CPUC and the Forest Service will prepare a Draft EIR/EIS for
the proposed project. When completed, the Draft EIR/EIS will be
released for public review and will be available on this website.
For Additional Information
The CPUC and the Forest Service, through their Environmental Review
Team, are conducting an environmental review of this project. To
request additional information or to be added to the mailing list,
please contact us by e-mail, fax, or phone, as follows:
|