STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

Southern California Edison's Antelope-Pardee 500-kV Transmission Line Project

(Application No. A.04-12-007)
 

Welcome to the California Public Utilities Commission (CPUC) website for the environmental review of a proposed 500-kilovolt (kV) transmission line from the Antelope Substation in northern Los Angeles County to the Pardee Substation in the City of Santa Clarita. Southern California Edison (SCE) submitted an application for a Certificate of Public Convenience and Necessity (CPCN) for this project to the CPUC on December 9, 2004. SCE has also submitted an application for a Special Use Easement to the USDA Forest Service. The proposed project is subject to review under both the California Environmental Quality Act (CEQA) and National Environmental Policy Act (NEPA). This site provides access to public documents and information relevant to the CEQA and NEPA review processes.

Background

SCE has filed applications with the CPUC and the Forest Service to construct a new, 25.6-mile 500-kV transmission line between SCE's existing 220-kV Antelope and Pardee substations in Los Angeles County, California. The proposed 500-kV transmission line would replace an existing 66-kV line that traverses the majority of the proposed route between the Antelope and Pardee substations, including approximately 13 miles within the Angeles National Forest (ANF). The proposed 500-kV transmission line route traverses an area of residential development in the Santa Clarita Valley area to the north and east of the existing Pardee Substation. The 500-kV transmission line would be energized initially at 220 kV. The proposed project would include electrical interconnections at the existing Antelope and Pardee substations as well as an initial expansion of the Antelope Substation and relocation of several existing 66-kV subtransmission lines in the vicinity of the Antelope Substation (collectively, referred to as the Antelope-Pardee 500-kV Transmission Line Project). The proposed project also includes the acquisition and fencing of approximately 31 acres of land necessary for the upgrade of the Antelope Substation from 220 kV to 500 kV.

Maps of the proposed transmission route can be viewed at the links below:

Map 1    Map 2    Map 3    Map 4

Aerial Photo of Santa Clarita Area

Proponent's Environmental Assessment (PEA)

As part of its application to the CPUC, SCE prepared and submitted a Proponent's Environmental Assessment (PEA), which describes the proposed project, existing environmental conditions in the project area, and potential environmental impacts. The December 2004 PEA may be viewed here.

Notice of Preparation and Project Scoping

The CPUC on June 24, 2005, issued a Notice of Preparation of an Environmental Impact Report (EIR) for the Antelope-Pardee 500-kV Transmission Line Project, including a map of the project area. In addition, the Forest Service published a Notice of Intent to prepare an Environmental Impact Statement (EIS) for the proposed project. The CPUC and the Forest Service have agreed to prepare a joint EIR/EIS for the proposed project to satisfy the requirements of CEQA and NEPA.

The CPUC and the Forest Service will hold two Public Scoping Meetings to solicit input from the public on potential impacts of the proposed project that should be addressed in the Draft EIR/EIS. The Scoping Meetings will be held at the following locations:

EIR/EIS Public Scoping Meetings
June 29, 2005
6:30 p.m. to 8:30 p.m.

Desert Inn Hotel
44219 Sierra Highway
Lancaster, CA 93534
(661) 942-8401

July 14, 2005
6:30 p.m. to 8:30 p.m.

City of Santa Clarita Activities Center
20880 Centre Point Parkway
Santa Clarita, CA 91350
(661) 250-3703

Scoping comments for the EIR/EIS must be postmarked or received by fax or e-mail no later than July 29, 2005. Scoping comments should be sent to:

CPUC/ USDA Forest Service
c/o Aspen Environmental Group
30423 Canwood Street, Suite 215
Agoura Hills, CA 91301
Fax: (661) 215-5152
E-mail: antelope-pardee@aspeneg.com
 

Draft Environmental Impact Report/Environmental Impact Statement

The CPUC and the Forest Service will prepare a Draft EIR/EIS for the proposed project. When completed, the Draft EIR/EIS will be released for public review and will be available on this website.

For Additional Information

The CPUC and the Forest Service, through their Environmental Review Team, are conducting an environmental review of this project. To request additional information or to be added to the mailing list, please contact us by e-mail, fax, or phone, as follows:

Project E-mail: antelope-pardee@aspeneg.com
Project Fax and Voicemail: (661) 215-5152
   

This page contains tables and is best viewed with Netscape or Internet Explorer. Please report any problems to the Energy Division web coordinator.

   
 
Project Home Page - CPUC Environmental Information - CPUC Home