Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of Southern
California Edison's (SCE's) proposed Banducci Substation Project
(Proposed Project). An Application for this project was submitted
to the CPUC on November 15, 2012. The CPUC currently is reviewing
the Application. This website provides access to public documents
and information relevant to the CEQA review process for the Proposed
Project.
Application A.12-11-011
CPUC INFORMATIONAL
MEETING
|
An Informational
Meeting concerning the project will be held December 11,
2014, from 5:30 p.m. to 8:00 p.m. at the Tehachapi
Police Department, Community Room, 220 West C Street, Tehachapi.
|
Comments must be
received in writing by 5:00 p.m. on December 15, 2014.
|
Background
The proposed Banducci Substation Project includes the following
components:
- Construction of a new Banducci 66/12 kilovolt (kV) Substation.
Banducci Substation would be an unstaffed, automated, 56.0 megavolt-ampere
(MVA), low-profile substation with a potential capacity of 112
MVA at final buildout. The proposed 66/12 kV distribution substation
would be located on an approximately 6.3 acre parcel in the unincorporated
Cummings Valley area of Kern County.
- Construction of two new 66 kV subtransmission line segments
that would loop the existing Correction-Cummings‒Kern River
1 66 kV Subtransmission Line: one that would enter and one that
would exit the proposed Banducci Substation creating the new Banducci‒Kern
River 1 66 kV Subtransmission Line and the new Banducci-Correction-Cummings
66 kV Subtransmission Line.
- Construction of three new underground 12 kV distribution getaways.
- Installation of telecommunications facilities to connect the
proposed Banducci Substation to SCE's existing telecommunications
system.
The Banducci Substation site is located at the southeast corner of
Pelliser Road and unimproved Dale Road in unincorporated Cummings
Valley, Kern County. The subtransmission line upgrades would occur
on new and replacement poles along Pelisse Road in close proximity
to the substation. Telecommunications upgrades would include installation
of fiber optic cable within existing SCE rights-of-way, overhead on
existing and replacement poles and underground in new conduit. A total
of approximately 32 miles of fiber optic cable would be installed
between the proposed Banducci Substation and the existing Cummings
and Monolith Substations, both near the City of Tehachapi, Kern County.
Construction would last approximately 12 months. SCE states that the
Proposed Project is needed to serve increased electrical demand and
to address reliability and operational flexibility issues in the Electrical
Needs Area. In accordance with the CPUC's General Order 131 D, approval
of this project must comply with CEQA.
Proponent's Environmental Assessment
(PEA)
SCE filed its original PEA with the Application on November 15,
2012. The PEA provided a starting point for the environmental review
process that is to be conducted by the CPUC. After reviewing the
2012 PEA, CPUC directed SCE to supplement and submit additional
information. A number of requests and responses ensued, culminating
in SCE submitting an amended PEA dated June 6, 2014.
Original Proponent's Environmental Assessment
2012 (superseded)
Amended Proponent's Environmental Assessment
2014
Original (2012) PEA Review
SCE's Application and original PEA were reviewed by the CPUC. The
Energy Division sent a letter to SCE on December 17, 2012,
indicating that the submitted PEA for the Banducci Substation required
supplementation and resubmission.
PEA Completeness Letter
#1
SCE subsequently submitted supplemental information to the CPUC
on February 5, 2013.
Supplemental PEA Information
#1
The Energy Division sent a letter to SCE on February 25, 2013,
indicating that the PEA for the Banducci Substation requires further
supplementation and resubmission.
PEA Completeness Letter
#2
In response, SCE submitted additional supplemental information
to the CPUC on April 19, 2013.
Supplemental PEA Information
#2
After reviewing the supplemental information, the Energy Division
sent a letter to SCE on May 8, 2013, indicating that the PEA
for the Banducci Substation again requires further supplementation
and resubmission.
PEA Completeness Letter
#3
In response, SCE submitted additional supplemental information
to the CPUC on June 3, 2013:
Response to Question #1,
Right-of-Way Description and Land Rights Definitions
Response
to Question #2, Soil Types GIS Data (.zip file; right-click
to download)
Response
to Question #3, Vegetation GIS Data (.zip file; right-click
to download)
Response to Question
#4, Cultural Resources Survey Description (PDF)
Revised
Mapping Suite of Data Package (.mpk file; right-click to
download)
After reviewing all supplemental information, the Energy Division
sent a letter to SCE on July 2, 2013, indicating that SCE has
submitted all necessary information at this time. However, in order
to deem the PEA complete, the CPUC requestsed that SCE re-file the
PEA in its entirety in the format consistent with the CPUC's PEA
Checklist for Transmission Line Projects (2008).
PEA Completeness Letter
#4
Amended (2014) PEA Review
The requested Amended PEA was submitted in June 2014.
Amended PEA 2014
After a completeness review of the amended PEA, the CPUC deemed
SCE's Application and PEA complete on July 15, 2014.
PEA Completeness Letter
#5
Draft Initial Study/Mitigated
Negative Declaration
On November 14, 2014, the CPUC released a Notice of Intent to Adopt
a Mitigated Negative Declaration (MND) for the Banducci Substation
Project, showing that the Proposed Project, as mitigated, would
not have any significant effects on the environment.
Draft Initial Study/Mitigated Negative
Declaration (IS/MND)
The Proposed IS/MND is undergoing a public review period from November 14,
2014, through December 15, 2014. Comments must be received
in writing by 5:00 p.m. on December 15, 2014,
at the project email or mailing address (see "For Additional
Information" below).
Public Informational Meeting
In order to help affected communities understand the Proposed Project
and the Proposed IS/MND and to explain how the public can participate
in the CPUC's decision-making process, the CPUC will hold an informational
meeting on:
Date: |
December 11, 2014 |
Time: |
5:30 p.m. to 8:00 p.m. |
Place: |
Tehachapi Police Department
Community Room
220 West C Street
Tehachapi, CA 93561
|
This informal meeting will be an opportunity to ask questions about
the content of the Draft IS/MND. While written comments may be submitted
during the meeting, there will be no facilities to record oral comments.
For Additional Information
The CPUC, through its Environmental Review Team, is conducting
an environmental review of the project. To request additional information,
please contact the CPUC, as follows:
Jensen Uchida, CPUC Project Manager
c/o Aspen Environmental Group
235 Montgomery Street, Suite 935
San Francisco CA 94104
Email: banduccisubstation@aspeneg.com
|