|
On May 21, 2015, the Commission acted to dismiss without prejudice SCE's application for a Certificate of Public Convenience and
Necessity to construct the Coolwater-Lugo Transmission Project. Therefore, the application for this project is closed, and a Draft
EIR/EIS will not be published.
Welcome to the
California Public Utilities Commission (CPUC) website for the environmental
review of the Coolwater-Lugo Transmission Project (CLTP) in San Bernardino
County.Southern California Edison (SCE) submitted an application for
a Certificate of Public Convenience and Necessity (CPCN) for this project
to the CPUC on August 28, 2013. SCE also submitted a Draft Plan of Development
for the project to the US Department of Interior, Bureau of Land Management.
The project will be reviewed under both the California Environmental Quality
Act (CEQA) and National Environmental Policy Act (NEPA).This site provides
access to public documents and information relevant to the CEQA and NEPA
review processes, as well as information regarding construction of the
Project.Information pertaining to the environmental review process can
be reviewed by clicking on the boxes provided above.Below is a map displaying
the route of the proposed CLTP.
Proposed Project Overview
The proposed SCE CLTP is intended to provide additional south of Kramer
capacity to integrate current and future renewable generation projects.
The proposed CLTP, planned to be operational by 2018, would provide additional
transmission capacity to help alleviate the 220-kilovolt (kV) transmission
bottleneck between the existing Kramer and Lugo Substations, to facilitate
the interconnection of renewable generation projects, to accommodate future
load serving in the Town of Apple Valley, and to facilitate additional
system reliability. The proposed CLTP would consist of installing new
transmission lines, new substation facilities to support line termination,
and telecommunication facilities to support the use of a Special Protection
System.
The proposed transmission line would utilize a combination of single-circuit
and double-circuit structures consisting of 220-kV and 500-kV design standards
between the existing Coolwater Switchyard and the existing Lugo Substation,
in order to provide an additional path for power to flow from the Kramer
Substation ultimately to the Lugo Substation. Routing of the proposed
transmission line south from the Coolwater Switchyard through the Lucerne
Valley area to SCE's existing transmission right-of-way, would facilitate
future connection to SCE's proposed Jasper Substation, which is a separate
project that is being developed approximately 22 miles south of the Coolwater
Switchyard and 27 miles northeast of the Lugo Substation. In addition,
a new 500/220-kV transformer bank would be installed at the Lugo Substation
and a new Desert View Substation with ultimate design for 500/220/115/12
kV, would be sited and partially constructed approximately 16 miles northeast
of the Lugo Substation along the proposed transmission line route as part
of the CLTP.
|
|