Welcome to the California Public Utilities Commission (CPUC) website
for the environmental review of the proposed El Casco System Project
(Proposed Project). The Proposed Project would include construction
of the El Casco Substation; upgrades to the Zanja and Banning Substations;
transmission line upgrades and installation from the new El Casco
Substation, located within the Norton Younglove Reserve, east to
the Banning Substation in the City of Banning; and telecommunications
improvements.
The objective of Southern California Edison Company's (SCE's) Proposed Project is to build the electrical
facilities necessary to serve forecasted demand in Calimesa, Beaumont,
and the surrounding areas of unincorporated northern Riverside County,
and to maintain safe and reliable service to customers in the area.
The Proposed Project is subject to review under the California
Environmental Quality Act (CEQA). This site provides access to public
documents and information relevant to the CEQA environmental review
process.
Recirculated (Revised) Final Environmental Impact Report
The CPUC, as Lead agency under the California Environmental Quality Act (CEQA) has prepared the Recirculated Final Environmental Impact Report (EIR) for consideration of SCE's Proposed El Casco System Project. The Recirculated Final EIR has been prepared in compliance with CEQA, and includes responses to comments received during the Recirculated Draft EIR comment period (July 9, 2008 through August 22, 2008), updates to the original Final EIR resulting from new information presented in the Recirculated Draft EIR, and any text changes resulting from the comments submitted and a feasibility review of mitigation measures.
The Recirculated Final EIR was released for public review on October 17, 2008 and is available for review at several area libraries and on this Project website. The Recirculated Draft EIR, the original Draft EIR, and the original Final EIR are also available in their entirety on the Project website (see below). Copies of these documents are available on CD-ROM and may be requested by phone or fax at (877) 576-8342, or by e-mail at elcasco@aspeneg.com.
Recirculated (Revised) Draft Environmental Impact Report
The CPUC, as Lead agency under CEQA, has prepared a Recirculated Draft Environmental Impact Report (Draft EIR) for consideration of Southern California Edison Company's (SCE) Proposed El Casco System Project (Proposed Project).
The Recirculated Draft EIR for the Proposed Project has been prepared to inform the public of changes to the document resulting from new information provided by SCE regarding the ambient noise levels adjacent to the existing single-circuit 115kV subtransmission line. This information was received subsequent to the CPUC publishing the Final EIR on April 11, 2008.
The Recirculated Draft EIR contains an updated noise analysis (Section D.9) reflecting the new information received from SCE; an updated cumulative noise effects analysis (also in Section D.9), an updated Comparison of Alternatives analysis (Section E) the includes a revised discussion of the Environmentally Superior Alternative; and an updated Executive Summary summarizing the changes to the above mentioned sections. Only those sections that have changed from the original Draft EIR published in December 2007 (discussed below) are included in the recirculated EIR, per CEQA Guidelines §15088.5(c).
The Recirculated Draft EIR was released for public review for 45 days on July 9, 2008. The Recirculated Draft EIR public review period ended on August 22, 2008.
Original Environmental Impact Reports
The CPUC prepared a Draft
Environmental Impact Report (Draft EIR) in December 2007. The Draft EIR details the Proposed Project, evaluates and describes the potential environmental impacts associated with the construction and operation of the Proposed
Project, identifies those impacts that could be significant, and presents
mitigation measures, which, if adopted by the CPUC or other responsible
agencies, could avoid or minimize these impacts. The Draft EIR also
evaluates alternatives to the Proposed Project, including the No
Project Alternative, as required by CEQA. The Draft EIR was released
for public review for 45 days on December 12, 2007. The Draft EIR public review period ended on January 25, 2008.
The CPUC published the Final Environmental Impact Report (Final EIR) on April 11, 2008. The Final EIR was prepared in complaince with the California Environmental Quality Act (CEQA), and included responses to comments received during the original Draft EIR comment period from December 12, 2007 through January 25, 2008 and any text changes resulting from the comments submitted.
Public Meetings and Hearings
As of October 17, 2008, the CPUC has held one Pre-Hearing Conference and four public meetings to provide information on the Project and to take public comments.
During the scoping (July 16, 2007 through August 14, 2007), the CPUC held one Pre-Hearing Conference and two public scoping meetings in two locations in northern Riverside County on August 1, 2007, as follows:
Pre-Hearing Conference:
Location |
Banning City Hall Council Chambers |
Date |
August 1, 2007 |
Time |
1:00 to 2:30 pm |
Address
Phone
No. |
99 East Ramsey Street
Banning, CA 92220-0998
(951) 922-3102 |
Public Scoping Meetings:
Location |
Banning City Hall Council Chambers |
Beaumont Civic Center Council Chamber |
Date |
August 1, 2007 |
August 1, 2007 |
Time |
2:30 - 4:30 p.m. |
6:30 - 8:30 p.m. |
Address |
99 E. Ramsey Street
Banning, CA 92220 |
550 East Sixth Street
Beaumont, CA 92223 |
During the Draft EIR public review period, the CPUC held public workshops and public participation meeting in the City of Banning on January 9, 2008 as follows:
Location |
City of Banning Council Chambers |
Day, Date |
Wednesday, January 9th, 2008 |
Time |
1:30 to 2:30 pm Workshop
3 to 4 pm Public Participation Meeting
|
5:30 to 6:30 pm Workshop
7 to 8 pm Public Participation Meeting |
Address
Phone No.
|
99 East Ramsey Street
Banning, CA 92220-0998
(951) 922-3102 |
Scoping Report
In September 2007, a comprehensive
Scoping Report was issued that summarizes the issues and concerns
received from the public and various agencies during the scoping period (July 16, 2007 throught August 14, 2007), and presents copies
of all written comments received. Approximately 15 letters and emails
were received during the NOP scoping period from public agencies
and private citizens.
The Appendices to the Scoping Report are available here:
Notice of Preparation
In accordance with CEQA, a Notice of Preparation
(NOP) of an Environmental Impact Report (EIR) for the El Casco System
Project was issued on July 16, 2007 (also see the list of Available
Documents below). The NOP summarized the Proposed Project and
advised the public and interested parties of the scoping process
for the environmental impact review. The dates, locations,
and times of the CPUC's pre-hearing conference and scoping meetings
were identified in the NOP.
Repository Sites.
All project-related documents are available for review at the following project
information repository locations:
Repository Sites |
Repository Site |
Location |
Phone Number |
Hours of Operation |
Yucaipa Branch Library |
12040 5th St. Yucaipa CA 92399 |
(909)790-3146 |
Sun Closed.
Mon -Thurs 10 am -8 pm
Fri 10 am - 6 pm
Sat 9 am- 5 pm |
Banning
Public Library |
21 W.Nicolet St. Banning, CA 92220 |
(951)849-3192 |
Sun Closed.
Mon - Thurs
9 am - 7 pm
Fri 9 am - 5 pm |
Calimesa Branch
Library |
974 Calimesa Blvd.
Calimesa, CA 92320 |
(909)795-9807 |
Sun, Mon Closed.
Tues ,Thurs, Fri
10 am -6 pm
Wed 12 pm - 8 pm
Sat 9 am - 5 pm |
Beaumont Library |
125 E 8th Street Beaumont, CA 92223 |
(951)845-1357 |
Sun Closed.
Mon, Wed, Fri
10 am - 6 pm
Tues,Thurs 10 am - 8 pm
Sat 10 am - 6 pm |
University of Redlands Armacost Library |
1200 East Colton Avenue Redlands, CA 92373-0999 |
(909)748-8081 |
Mon -Thurs 8 am - midnight
Fri 8 am - 9 pm
Sat 10 am - 9 pm
(Call to verify hours) |
CEQA Process and CPUC General Proceeding
CEQA requires the CPUC to take into account the environmental impacts
that could result from the Proposed Project, and requires the preparation
of an EIR if the Project has the potential to result in significant
impacts to the environment. CEQA also requires that the EIR development
process include public notice of the Proposed Project and address
relevant environmental concerns that the public may have regarding
the Proposed Project.
The initial public scoping and comment period for the Proposed
Project was 30 days per CEQA requirements, from July 16, 2007,
until August 14, 2007. During this period, public comments
were accepted and two public scoping meetings and a pre-hearing
conference were held, prior to selection of alternatives and the
preparation of the analysis documented in the EIR. The intent of
the scoping process was to obtain input from affected agencies and
members of the public on the scope and content of the EIR.
The Draft EIR includes an objective analysis of the potential environmental
impacts of the Proposed Project. In addition, the Draft EIR provides
a detailed discussion of alternatives, including a comparison of
each alternative to the Proposed Project. Per CEQA requirements,
the Draft EIR was distributed for a 45-day public review period.
A notice of completion (NOC) of the Draft EIR was filed with the
State Clearinghouse by the CPUC. The CPUC considered all comments
on the Draft EIR, prepared responses to comments, and revised
the document (as necessary) prior to issuance of the Final EIR on April 11, 2008. The
Final EIR included responses to comments received on the Draft
EIR during the original public review period.
The California Public Utilities Commission (CPUC) has since prepared a Reciruclated Draft EIR for considerated of the Proposed El Casco System Project. The Recirculated Draft EIR has been prepared to inform the public of changes to the document resulting from new information provided by SCE regarding the ambient noise levels adjacent to the existing single-circuit 115 kV subtransmission line. SCE provided this information subsequent to the CPUC publishing the Final EIR on April 11, 2008. The Recirculated Draft EIR was released for public review for a 45 days on July 9, 2008. The Reciruclated Draft EIR public review period ending August 22, 2007. A NOC was filed with the State Clearinghouse by the CPUC.
On October 17, 2008, the CPUC released the Recirculated Final EIR for the Proposed El Casco System Project. The Recirculated Final EIR has been prepared in compliance with the California Environmental Quality, and includes responses to comments received during the Recirculated Draft E"IR comment period (July 9, 2008 through August 22, 2008), updates to the original Final EIR resulting from new information presented in the Recirculated Draft EIR, and any text changes resulting from comments submitted and a feasibility review of mitigation measures.
Other Available
Documents
- Notice of Preparation of an Environmental
Impact Report for the El Casco System Project Proposed by Southern
California Edison Company prepared by the CPUC (July 16,
2007)
- Fact Sheet - El Casco System Project
prepared by CPUC (June 2007)
- Southern California Edison's Proponent's
Environmental Assessment (PEA) (March 14, 2007)
Note: The link above provides access to 59 manageably sized files
comprising the PEA. The complete PEA is also available for download
from the Southern
California Edison website as a single very large file (155 MB).
This file size means a very long download time, not advisable
for anyone with a dialup connection.
Project Description
The El Casco System Project includes the proposed El Casco Substation
site, upgrades to the Zanja and Banning Substations and the SCE's
Mill Creek Communications Site, upgrades to
a total of 15.4 miles of existing
115 kV subtransmission line and associated structures, and the installation
of fiber optic cables within existing conduits in public streets and
on existing SCE structures between the Cities of Redlands and Banning.
All portions of the Proposed Project are located within Riverside
and San Bernardino Counties, California. The main project components
are described below and indicated on the General
Location Map.
Construction of the El Casco Substation. The new 14-acre
El Casco 220/115/12 kV Substation would be located on a 28-acre
plot within the Norton Younglove Reserve in Riverside County. This
component would include associated 220 kV and 115 kV interconnections
and new 12 kV distribution line connections (getaways). The substation
would be designed with a low profile (structures no taller than
40 feet). Landscaping around the substation would incorporate primarily
native vegetation and would be designed to screen views of the substation
site. Once constructed, the substation would be an unattended, automated
220/115/12 kV substation.
Upgrades to the Zanja and Banning Substations. The 115 kV
switchracks within the Zanja and Banning Substations, located in
the Cities of Yucaipa and Banning, respectively, would be rebuilt
to accommodate the new 115 kV subtransmission line, thereby allowing
for at least two subtransmission lines to serve each substation
at all times. This would reduce the likelihood of temporary power
outages, which currently occur due to the fact that each substation
is served by only one 115 kV subtransmission line at a time. If
there is a problem with the primary (or "preferred") line,
a brief delay currently occurs before the secondary (or "emergency")
line can be connected. The upgrades to the Zanja and Banning Substations
would eliminate this delay by providing a connection for a second
115 kV subtransmission line for each substation that would be active
at all times. Replacement of the switchracks in both substations
would occur within the existing fenced-in areas.
Transmission Line Upgrades and Installation. These upgrades
would include replacement of existing single-circuit 115 kV subtransmission
lines with new, higher capacity lines; tying existing 115 kV and
220 kV lines into the new El Casco Substation (looping in); and
installation of new 12 kV distribution line getaways at the El Casco
Substation.
The proposed upgrades of the existing single-circuit subtransmission
lines would include the following:
- Approximately 13 miles of single-circuit 115 kV lines would
be replaced with 115 kV double-circuit lines between the new El
Casco Substation and the Banning Substation, traversing the Cities
of Banning, Beaumont, and unincorporated Riverside County. Single-circuit
115 kV structures would be replaced with 115 kV double-circuit
structures.
- Approximately 1.9 miles of single-circuit 115 kV subtransmission
line would be replaced with new, higher capacity single-circuit
115 kV subtransmission lines and new support structures within
existing SCE rights-of-way (ROWs) in the City of Beaumont and
unincorporated Riverside County.
- Approximately 0.5 miles of single-circuit 115 kV subtransmission
line would be replaced with new, higher capacity single-circuit
115 kV subtransmission lines on existing support structures in
the City of Beaumont.
The existing San BernardinoMaraschino 115 kV subtransmission
line would be looped into the new El Casco Substation 115 kV switchrack
on two new approximately 900-foot line segments between the existing
ROW and the 115 kV switchrack. The DeversSan Bernardino No. 2
220 kV transmission line would be looped into the new 220 kV switchrack
at the El Casco Substation on two new approximately 500-foot line
segments between the existing ROW and the 220 kV switchrack. Two
approximately 400-foot underground duct banks would be constructed
for the 12 kV distribution line getaways, traversing beneath San
Timoteo Creek and the railroad tracks. These distribution lines
would eventually be connected to future distribution lines in the
area.
Telecommunications Improvements. Proposed improvements to the telecommunications
systems as part of the Proposed Project include the construction
of a microwave system at the proposed El Casco Substation and SCE's
existing Mill Creek Communications Site in the San Bernardino National
Forest, as well as installation of fiber optic cables within public
streets and on existing SCE structures in the Cities of Banning,
Beaumont, Calimesa, Redlands, and Yucaipa, as well as unincorporated
parts of Riverside and San Bernardino Counties.
The following link provides a general Project map:Map 1-General Location (2.5MB)
Additional maps and figures for the Proposed Project and alternatives
are can be found in the Proponent's Environmental
Assessment, which is provided as a link.
Commission Decision
D.08-12-031 - Issued December 18, 2008
Attachment A - CPUC CEQA Findings of Fact
For Additional Information
The CPUC, through its Environmental Review Team and per CEQA requirements,
is conducting the environmental review process for the Proposed
Project. To request additional information or to comment on the
Draft EIR, please contact us by project email, fax, or phone, as
follows:
The CPUC's Project Manager is:
Juralynne Mosley, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-2210
Fax (415) 703-2200
Email: jbm@cpuc.ca.gov |