Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of Pacific
Gas and Electric's (PG&E) proposed Embarcadero-Potrero 230 kV
Transmission Project (Proposed Project or Embarcadero-Potrero 230
kV). An application for this project was submitted to the CPUC on
December 11, 2012 (A.12-12-004),
which starts the CPUC proceeding to decide whether a Certification
of Public Convenience and Necessity (CPCN) should be issued. The
CPUC is currently reviewing the application. This site provides
access to public documents and information relevant to the CEQA
review process.
Background
PG&E filed an application with the CPUC to build the proposed
Embarcadero-Potrero 230 kV Transmission Project. The Proposed Project
would include construction, operation, and maintenance of a 230
kV transmission line entirely within the City and County of San
Francisco from Embarcadero Substation near the corner of Fremont
and Folsom Streets, to Potrero Switchyard on Illinois Street between
22nd and 23rd Streets.
The new 230 kilovolt (kV) transmission line would be approximately
3.5 miles in total length, including approximately 2.5 miles to
be installed offshore underneath the seafloor of the San Francisco
Bay (the Bay), 0.4 mile to be installed in horizontal directional
drills (HDD) from two onshore transition points to the Bay, and
approximately 0.6 miles to be installed underground in paved areas.
The new transmission line would be placed in City streets, including
Spear Street and Folsom Street in San Francisco's Rincon Hill neighborhood
and 23rd Street east of Illinois Street. Construction of a new 230
kV switchyard would occur near the existing Potrero Switchyard,
but no new substation work is proposed to occur at the existing
Embarcadero Substation beyond the proposed termination of the new
cable into the 230 kV bus.
PG&E's project objectives include improving the reliability
of the existing transmission system in San Francisco to provide
a high likelihood of continued electric service to downtown San
Francisco in the event of overlapping outages on both of two existing
230 kV transmission lines that presently feed Embarcadero Substation.
Proponent's Environmental Assessment
(PEA)
PG&E filed a PEA with the Application
on December 11, 2012. This document provides a starting point for
the environmental review process conducted by the CPUC. PG&E's
Application and PEA were deemed complete for review by the CPUC
on January 10, 2013.
Environmental Review Process
The CPUC Energy Division reviewed PG&E's Application and PEA
and prepared an Initial Study/Mitigated Negative Declaration (IS/MND)
as the appropriate CEQA document for this project.
Draft Mitigated Negative Declaration
and Supporting Initial Study
The CPUC released a Notice of Intent to Adopt a Mitigated Negative
Declaration for the proposed Embarcadero-Potrero 230 kV Transmission
Project showing that the Proposed Project, as mitigated, would not
have any significant effects on the environment. The Draft Mitigated
Negative Declaration and Supporting Initial Study (IS/MND) was made
available for public review and comment from August 13, 2013
to September 16, 2013.
The Draft IS/MND can be viewed here.
Final Mitigated Negative Declaration
and Supporting Initial Study
On October 29, 2013, the CPUC released a Final Mitigated Negative
Declaration showing that the proposed Embarcadero-Potrero 230 kV
Transmission Project, as mitigated, would not have any significant
effects on the environment. The Final IS/MND details the Proposed
Project, evaluates and describes its potential environmental impacts,
identifies those impacts that could be significant, and presents
mitigation measures to avoid or minimize these impacts.
The Final IS/MND can be viewed here.
CPUC Actions After Final Initial
Study/Mitigated Negative Declaration (IS/MND) Publication
There is no comment period following release of the Final IS/MND.
The CPUC will determine the adequacy of the Final IS/MND, and, if
adequate, the CPUC may adopt the document as being compliant with
CEQA and issue a Proposed Decision on the Application. Any Proposed
Decision will be announced and published concurrent with a scheduled
Commission meeting. After the Commission makes the decision on the
Application, a Notice of Determination will be mailed to the State
Clearinghouse within 5 days of the Decision. The 30-day statute
of limitations for court challenges begins after the Notice of Determination
is filed.
Mitigation Monitoring
Mitigation Monitoring, Compliance, and Reporting Plan. Following
CPUC approval, a Mitigation Monitoring, Compliance, and Reporting
Plan (MMCRP) will be prepared to ensure compliance with applicant
proposed measures (APMs) and mitigation measures approved in the
Final IS/MND. This MMCRP will be developed to provide guidelines
and standardize procedures for environmental compliance during project
implementation. The procedures will be developed in coordination
with PG&E and CPUC and will describe the reporting relationships,
the roles and responsibilities of the project's environmental compliance
team members, compliance reporting procedures, and the communication
protocol.
For Additional Information
The CPUC, through its Environmental Review Team, is conducting
an environmental review of the project. To request additional information,
please contact the CPUC, as follows:
Billie Blanchard
California Public Utilities Commission
c/o Aspen Environmental Group
235 Montgomery Street, Suite 935
San Francisco, CA 94104
Email: embarcaderopotrero@aspeneg.com
|