STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

Pacific Gas and Electric's
Proposed Embarcadero-Potrero 230 kV Transmission Project

(Application A.12-12-004, filed December 11, 2012)

Welcome to the California Public Utilities Commission (CPUC) website for the California Environmental Quality Act (CEQA) review of Pacific Gas and Electric's (PG&E) proposed Embarcadero-Potrero 230 kV Transmission Project (Proposed Project or Embarcadero-Potrero 230 kV). An application for this project was submitted to the CPUC on December 11, 2012 (A.12-12-004), which starts the CPUC proceeding to decide whether a Certification of Public Convenience and Necessity (CPCN) should be issued. The CPUC is currently reviewing the application. This site provides access to public documents and information relevant to the CEQA review process.

Background

PG&E filed an application with the CPUC to build the proposed Embarcadero-Potrero 230 kV Transmission Project. The Proposed Project would include construction, operation, and maintenance of a 230 kV transmission line entirely within the City and County of San Francisco from Embarcadero Substation near the corner of Fremont and Folsom Streets, to Potrero Switchyard on Illinois Street between 22nd and 23rd Streets.

The new 230 kilovolt (kV) transmission line would be approximately 3.5 miles in total length, including approximately 2.5 miles to be installed offshore underneath the seafloor of the San Francisco Bay (the Bay), 0.4 mile to be installed in horizontal directional drills (HDD) from two onshore transition points to the Bay, and approximately 0.6 miles to be installed underground in paved areas. The new transmission line would be placed in City streets, including Spear Street and Folsom Street in San Francisco's Rincon Hill neighborhood and 23rd Street east of Illinois Street. Construction of a new 230 kV switchyard would occur near the existing Potrero Switchyard, but no new substation work is proposed to occur at the existing Embarcadero Substation beyond the proposed termination of the new cable into the 230 kV bus.

PG&E's project objectives include improving the reliability of the existing transmission system in San Francisco to provide a high likelihood of continued electric service to downtown San Francisco in the event of overlapping outages on both of two existing 230 kV transmission lines that presently feed Embarcadero Substation.

Proponent's Environmental Assessment (PEA)

PG&E filed a PEA with the Application on December 11, 2012. This document provides a starting point for the environmental review process conducted by the CPUC. PG&E's Application and PEA were deemed complete for review by the CPUC on January 10, 2013.

Environmental Review Process

The CPUC Energy Division reviewed PG&E's Application and PEA and prepared an Initial Study/Mitigated Negative Declaration (IS/MND) as the appropriate CEQA document for this project.

Draft Mitigated Negative Declaration and Supporting Initial Study

The CPUC released a Notice of Intent to Adopt a Mitigated Negative Declaration for the proposed Embarcadero-Potrero 230 kV Transmission Project showing that the Proposed Project, as mitigated, would not have any significant effects on the environment. The Draft Mitigated Negative Declaration and Supporting Initial Study (IS/MND) was made available for public review and comment on August 13, 2013.

The Draft IS/MND can be viewed here.

The Draft IS/MND is available for public review and comment until 5:00 p.m. on September 16, 2013.

Public Informational Meeting: In order to help affected communities understand the Proposed Project and the IS/MND and to explain how the public can participate in the CPUC's decision-making processes, the CPUC Energy Division staff will hold an informational workshop on Tuesday, August 20, 2013. This informal workshop is an opportunity to ask questions about the content of the Draft IS/MND. While written comments may be submitted during the workshop, there will be no facilities to record oral comments.

Workshop Date and Time: August 20, 2013 from 3:00 p.m. to 5:00 p.m. at Port of San Francisco, Bayside 1 Conference Room.

Workshop Location: Pier 1, Washington Street at The Embarcadero; San Francisco, California

Following a 30-day public comment period of the Draft IS/MND, the CPUC will respond to comments and prepare a Final IS/MND. After release of the Final IS/MND, the CPUC will determine the adequacy of the Final IS/MND, and, if adequate, the CPUC may adopt the document as being compliant with CEQA and issue a Proposed Decision on the Application. Any Proposed Decision will be announced and published concurrent with a scheduled Commission meeting. After the Commission makes the decision on the Application, a Notice of Determination will be mailed to the State Clearinghouse within 5 days of the Decision. The 30-day statute of limitations for court challenges begins after the Notice of Determination is filed.

For Additional Information and Public Comments

The CPUC, through its Environmental Review Team, is conducting an environmental review of the project. To request additional information and to comment on the Draft IS/MND, please contact the CPUC, as follows:

Billie Blanchard
California Public Utilities Commission
c/o Aspen Environmental Group
235 Montgomery Street, Suite 935
San Francisco, CA 94104
Email: embarcaderopotrero@aspeneg.com
   

This page contains tables and is best viewed with Firefox or Internet Explorer. Please report any problems to the Energy Division web coordinator

   
 
Project Home Page - CPUC Environmental Information - CPUC Home