| Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of Pacific 
              Gas and Electric's (PG&E) Embarcadero-Potrero 230 kilovolt (kV) 
              Transmission Project. An application for this project was submitted 
              to the CPUC on December 11, 2012 (A.12-12-004), 
              which started the CPUC proceeding to decide whether a Certification 
              of Public Convenience and Necessity (CPCN) should be issued. The 
              CPUC reviewed the application and in a decision on January 16, 
              2014 (D.14-01-07) 
              approved the project and issued a CPCN. This website provides access 
              to public documents and information relevant to the CEQA review 
              process. 
             Quick links to project-related documents are provided here: 
              
              Proponent's Environmental Assessment (PEA) Draft Initial Study/Mitigated Negative 
                Declaration (Draft IS/MND) Final Initial Study/Mitigated Negative 
                Declaration (Final IS/MND) Mitigation Monitoring, Compliance, and 
                Reporting Program (MMCRP) Background 
             The Embarcadero-Potrero 230 kV Transmission Project includes construction, 
              operation, and maintenance of a 230 kV transmission line entirely 
              within the City and County of San Francisco from Embarcadero Substation 
              near the corner of Fremont and Folsom Streets to Potrero Switchyard 
              on Illinois Street between 22nd and 23rd Streets.
 The new 230 kV transmission line will be approximately 3.5 miles 
              in length, including approximately 2.5 miles installed offshore 
              in the seafloor of San Francisco Bay, 0.4 mile installed in horizontal 
              directional drills (HDD) from two onshore transition points to the 
              Bay, and approximately 0.6 miles underground in conventional trenching. 
              The new transmission line will be placed in City streets, including 
              Spear Street and Folsom Street in San Francisco's Rincon Hill neighborhood 
              and 23rd Street east of Illinois Street. Construction of a new 230 
              kV switchyard will occur near the existing Potrero Switchyard, but 
              no new substation work will occur at the existing Embarcadero Substation 
              beyond the proposed termination of the new cable into the 230 kV 
              bus.
 
 PG&E's project objectives include improving the reliability 
              of the existing transmission system in San Francisco to provide 
              a high likelihood of continued electric service to downtown San 
              Francisco in the event of overlapping outages on both of two existing 
              230 kV transmission lines that presently feed Embarcadero Substation.
 Proponent's Environmental Assessment 
              (PEA)  PG&E filed a PEA with the Application 
              on December 11, 2012. This document provided a starting point for 
              the environmental review process conducted by the CPUC. PG&E's 
              Application and PEA were deemed complete for review by the CPUC 
              on January 10, 2013. Environmental Review Process 
               The CPUC Energy Division reviewed PG&E's Application and PEA 
              and prepared an Initial Study/Mitigated Negative Declaration (IS/MND) 
              as the appropriate CEQA document for this project.  Draft Mitigated Negative Declaration 
              and Supporting Initial Study The CPUC released a Notice of Intent to Adopt a Mitigated Negative 
              Declaration for the proposed Embarcadero-Potrero 230 kV Transmission 
              Project showing that the Proposed Project, as mitigated, would not 
              have any significant effects on the environment. The Draft Mitigated 
              Negative Declaration and Supporting Initial Study (IS/MND) was made 
              available for public review and comment from August 13, 2013 
              to September 16, 2013. The Draft IS/MND can be viewed here. Final Mitigated Negative Declaration 
              and Supporting Initial Study On October 29, 2013, the CPUC released a Final Mitigated Negative 
              Declaration showing that the proposed Embarcadero-Potrero 230 kV 
              Transmission Project, as mitigated, would not have any significant 
              effects on the environment. The Final IS/MND details the Proposed 
              Project, evaluates and describes its potential environmental impacts, 
              identifies those impacts that could be significant, and presents 
              mitigation measures to avoid or minimize these impacts. The Final IS/MND can be viewed here. CPUC Actions After Final Initial 
              Study/Mitigated Negative Declaration (IS/MND) Publication
 The CPUC issued a Proposed Decision on the Application on December 2, 
              2013. The Commission made its decision on the Application on January 16, 
              2014, determining the adequacy of the Final IS/MND, adopting the 
              document as being compliant with CEQA, and issuing a CPCN. A Notice 
              of Determination was mailed to the State Clearinghouse. Mitigation Monitoring Mitigation Monitoring, Compliance, and Reporting Plan. Following 
              CPUC approval, a Mitigation Monitoring, Compliance, and Reporting 
              Plan (MMCRP) was prepared to ensure compliance with applicant proposed 
              measures (APMs) and mitigation measures approved in the Final IS/MND. 
              The MMCRP provides guidelines and standardize procedures for environmental 
              compliance during project implementation. The procedures were developed 
              in coordination with PG&E and CPUC and describe the reporting 
              relationships, the roles and responsibilities of the project's environmental 
              compliance team members, compliance reporting procedures, and the 
              communication protocol. The MMCRP can be viewed here. For Additional Information To request additional information, please contact the CPUC, as 
              follows: Billie Blanchard 
              California Public Utilities Commission 
              c/o Aspen Environmental Group 
              235 Montgomery Street, Suite 935 
              San Francisco, CA 94104 
              Email: embarcaderopotrero@aspeneg.com |