Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of the
proposed construction of Lodi Gas Storage, L.L.C.'s Kirby Hills
Natural Gas Storage Facility. An application for this project was
submitted to the CPUC on July 25, 2005 (Application A.05-07-018).
This site provides access to public documents and information relevant
to the CEQA environmental review.
Project Documents Available
Background
Lodi Gas Storage, L.L.C. (LGS) is proposing to use a depleted natural
gas reservoir in the Kirby Hills gas field as a storage facility
for natural gas transported to the site by its customers. The total
storage capacity of the reservoir is approximately 7 billion cubic
feet (BCF) and the project will have a maximum injection and withdrawal
capability of 100 million cubic feet per day (MMcf/day) of natural
gas. Project operations would involve tapping into the PG&E
400 pipeline near mile 286.65, constructing facilities to convey
natural gas from the PG&E 400 pipeline approximately seven miles
to the Kirby Hills gas field, storing the gas in the existing natural
reservoir, withdrawing the stored gas on demand from Lodi Gas Storage
customers, and conveying the withdrawn gas to the PG&E 400 pipeline
for delivery to those customers.
The proposed project is comprised the following six primary components
(see Project Facilities Map):
- Metering station
- Gas pipeline
- Compressor station
- Flow line
- Injection/withdrawal wells
- Temporary gas injection system
In accordance with Public Utilities Code Section 1001, LGS is seeking
approval of a Certificate of Public Convenience and Necessity (CPCN)
from the CPUC to construct and operate the project.
Project Location
The project site is located in a rural agricultural area in the
Montezuma Hills of southeastern Solano County, California, immediately
north of the SacramentoSan Joaquin River Delta. The site is
approximately six miles west of Rio Vista and eight miles southeast
of Fairfield (see Regional
Location Map).
The proposed project contains two major component locations, connected
by an approximately six-mile east-west pipeline corridor (see Project
Location Map). The eastern project component is a natural gas
receiving/metering station site, located west of Bird's Landing
Road, one mile south of its intersection with State Route 12.
The western project component is the natural gas storage/withdrawal
site located in the Kirby Hills between Montezuma/Nurse Slough on
the west and Shiloh road on the east. The western portion of the
project area is also located within the Suisun Marsh Secondary Management
Area.
CPUC's Application Review
The CPUC is responsible for the review and approval of any natural
gas storage facility in California. In proposals such as this, the
CPUC has a two-part review process to evaluate economic and environmental
impacts. The CPUC conducts a legal proceeding before an administrative
law judge to examine the economic and public utility issues, including
impacts to utility ratepayers. At the same time, the CPUC conducts
an environmental review consistent with CEQA. The ultimate result
of the two reviews is a decision by the Commission whether to grant
a CPCN for the project.
Environmental Review
Review and approval of the application must comply with the CEQA,
which requires consideration of the potential environmental impacts
of the proposed project. The CPUC is now identifying the potential
environmental impacts of the proposed project.
To learn more about the legal proceedings for the Certificate of
Public Convenience and Necessity or to become a participant in that
part of CPUC's review, please contact the CPUC Process Office at
(415) 703-2021
Contact Information
Please send comments and questions about the environmental review
process to CPUC's project manager:
Junaid Rahman, Regulatory Analyst
California Public Utilities Commission
505 Van Ness Avenue, Room 4A
San Francisco, CA 94102-3298
E-mail: jnr@cpuc.ca.gov
Phone: (415) 355-5492
Fax (415) 703-2200
|