STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

Level 3 Communications Infrastructure Project

(A.99-06-028)

Proponent's Environmental Assessment 

Table of Contents

Section 1.0

1.1   Project Background     
1.2  Purpose and Scope of the PEA
1.3  Level 3 Environmental Commitments
1.4  Major Conclusions

Section 2.0

2.1  Purpose of the project 

2.2  Project Need    

Section 3.0 Project Description

3.1  Introduction 

3.2  Project Location

3.3 Construction and Operation Overview

3.4  Required Permits and Approvals

3.5  Level 3 Environmental Commitments

Section 4.0 Environmental Setting

Section 5.0 Environmental Impact Assessment Summary

5.1  Impact Assessment Methodology

5.2  Cumulative Impact Assessment Methodology

Section 6.0 Detailed Discussion of Significant Impacts

Section 7.0 Alternatives to the Proposed Action 

7.1  Evaluation of Site Alternatives 

7.2  Evaluation of the No Project Alternatives

Section 8.0 Growth-Inducing Impact of the Proposed Action

Section 9.0 Affected Property Owners

Section 10.0 Sources

Tables

Table 1    Long-Haul Network Elements

Table 2    Attributes of Each Project Facility Relevant to Impact Assessment

Table 3    Summary of Potential Impacts of the No Project Alternative

Figures

Figure 1    Level 3 Communications, LLC California Statewide Network
Figure 2    Level 3 Communications, LLC California Network Elements
Figure 3    Artist's Rendition of Four-Hut ILA Facility and Generator Shelter
Figure 4    Artist's Rendition of the Transport of a Pre-Fabrication ILA Hut

Appendices

Appendix A    CEQA Initial Study Checklist for Proposed Facilities 
Appendix B    Level 3 Environmental Commitments from CPUC Negative Declaration IX
Appendix C   Fiber Optic Cable Construction Methods
Appendix D    Project Construction Specifications 
Appendix E    Measures to be Implemented to Avoid and Minimize Water Quality Impacts         During Construction
Appendix F    Property Owners Affected by Proposed Facilities
Appendix G    Description of ILA Sites Within Existing Utility Right-Of-Way

1.0    Summary

1.1  Project background

Level (3) Communications, LLC (“Level (3)”), a U.S.  telecommunications company, is building the first international fiber optic network optimized for internet technology.  The company is currently connecting various city pairs in the United States by constructing a national Long-Haul Network mainly in utility ROW for the transmission of voice and data services.  Approximately 2,000 miles of this network will be located in California (Figure 1). 

In Decision No.  98-03-066 issued March 26,1998 (“Decision”), the California Public Utilities Commission ("CPUC" or "Commission") granted Level (3) a Certificate of Public Convenience and Necessity ("CPCN") to provide services to the public as a facilities-based competitive local exchange carrier.  The Commission’s Decision allows Level (3) to construct underground innerduct and cable installation and support facilities (e.g., emergency power supply) within existing utility ROW, subject to certain conditions and the “Environmental Mitigation Measures” specified in the Commission’s Negative Declaration IX (Appendix D of the subject decision).   The Commission concluded that implementation of these measures would ensure that impacts associated with the project would be less than significant.  According to the measures specified under “All Environmental Factors,” a Petition to Modify (or “Application for Modification of”) the CPCN must be filed to obtain approval for off-ROW work.   As part of this Application for Modification, Level (3) must perform a site-specific assessment of the potential impacts associated with off-ROW design, construction, and operation activities. These off-ROW elements of the California Network are herein referred to as “project elements.”

To address the Commission’s requirements for off-ROW work, Level (3) prepared and submitted its Proponent’s Environmental Assessment (“PEA”) on May 21, 1999 as part of its filing of an Application for Modification of its CPCN.  This assessment was responsive to the specifications of Rule 17.1 of the Commission’s Rules of Practice and Procedures (the Special Procedure for Implementation of the California Environmental Quality Act of 1970) and the Commission’s Information and Criteria List. 

The May 21st submittal included CEQA checklists for 31 vacant (and largely undeveloped) land sites where construction of ILAs, 3Rs, and D-Nodes were proposed, as well as 3 Workarounds.  On June 15th Level (3) submitted an addendum to the PEA which included checklists for two additional vacant land sites.  The CPUC provided review comments on these submittals on June 18th and June 28th, prompting Level (3) to reevaluate its off-ROW system needs.  As a result, Level (3) substantially reduced both the number of (off-ROW) project elements and the potential for environmental impacts associated with those selected for inclusion in the California Network.  This transition from what were largely undeveloped sites to ROW sites and off-ROW developed or disturbed sites imposed a substantial cost burden on Level (3), but was determined to be the environmentally superior system design as mandated by CEQA.  The revised PEA, which included CEQA checklists for 25 off-ROW project elements (22 facilities and 3 Workarounds), was submitted to CPUC on October 1. 

CPUC conducted a preliminary review of Level (3)’s October 1 submittal and, on October 14th, provided 12 “threshold comments” to which responses were needed before the October 1 submittal could be fully evaluated.  On November 11, as part of Level (3)’s response to these threshold comments, 5 additional CEQA checklists (4 facilities and 1 Workaround) were submitted to CPUC, and CPUC was notified that 5 of the October 1 off-ROW project elements had been dropped.  Since the November 11th submittal, one additional facility (Escondido ILA) has been relocated to ROW, and the CEQA checklist for the October 1 site has been dropped.  This change reduced the suite of off-ROW project elements for which CEQA checklists were required to 24 (20 facilities and 4 Workarounds).   These 24 project elements were the subject of Level (3)’s January 4th Draft Final PEA.

Subsequent to the Jan 4th submittal, Level (3) dropped the Irvine D-Node site from the California Network. .  Therefore, this Final PEA addresses 23 project elements, which fall into the following categories:

  • Facilities within existing structures on developed sites (9 project elements);
  • Facilities on the existing foundations of demolished or removed structures on developed sites (5 project elements);
  • Facilities on vacant developed sites (2 project elements);
  • Facilities on disturbed undeveloped sites (3 project elements); and
  • Workarounds (4 project elements)

1.2    PURPOSE AND SCOPE OF THE PEA

Pursuant to the Environmental Mitigation Measures of CPUC’s Negative Declaration IX, and specifically the measures included under “All Environmental Factors,” Level (3) has prepared this PEA to accompany the Application for Modification of its CPCN.  As specified in CPUC Rule 17.1, the PEA is designed to enable the Commission to quickly focus on project impacts which may be of concern.   The PEA may also be used as an aid in preparing the Commission’s Initial Study.  The information provided is intended to support the Commission's responsibilities as lead agency under the California Environmental Quality Act of 1970 ("CEQA," PRC § 21000 et seq.  and the CEQA Guidelines, CCR Title 14 § 15000 et seq.), to assist other reviews or evaluations by CEQA responsible or trustee agencies, and to facilitate agency actions in accordance with the Permit Streamlining Act (CGC § 65920 et seq.).

This PEA has been developed to be consistent with, and responsive to, Section V Environmental Information Requirements, of the CPUC’s Information and Criteria List (adopted pursuant to Chapter 1200 of the Statutes of 1977, Government Code Sections 65940 through 65942), which applies to all projects subject to CEQA for which Commission approval is required by law. 

To meet these requirements, the PEA presents Level (3)’s detailed environmental assessment of proposed (off-ROW) project elements.  The assessment:

·        Identifies probable direct or reasonably foreseeable indirect physical changes in the environment that would result from construction or operation of these project elements;

·        Analyzes the potential impacts of these physical changes to each of 16 potentially affected environmental issue areas; and

·        Recommends measures to ensure that potential impacts are kept at less-than-significant levels.

Summary information is also provided on Level (3)’s proposed on-ROW ILA sites (Appendix G).  More detailed treatment of these on-ROW ILA sites is provided in the individual Facility Construction Workbooks.

1.3  LEVEL (3) ENVIRONMENTAL COMMITMENTS

Level (3) is committed to avoiding or reducing to less-than-significant levels any potentially significant environmental impacts resulting from off-ROW work activities.  Level (3) has conducted a rigorous evaluation of the potential for off-ROW impacts.  Level (3)’s decision to re-configure the California Network with emphasis on placement of project elements within utility ROW, on developed parcels, and on disturbed sites represents a strong commitment by the company to maintaining the quality of California’s environment and being fully responsive to CEQA. 

This PEA identifies those actions that Level (3) will undertake to ensure that any potential environmental impacts are less than significant.  These actions include integration into project planning, design, and technical specifications all “Environmental Mitigation Measures” stipulated in Appendix D of the Commission’s Negative Declaration IX (see Appendix B of this PEA) as well as other appropriate measures.  In so doing, these mitigation measures become Level (3) Site-Specific Environmental Commitments and potentially significant impacts addressed by them are now considered to be less than significant. 

1.4  Major Conclusions

Due substantially to an alternatives evaluation process that favored selection of developed and disturbed sites with minimal environmental attributes, Level (3)’s detailed impact assessment found that the potential environmental impacts for all (off-ROW) project elements are less than significant for all impact assessment issues.  Technical analyses that support this conclusion are reported in the site-specific CEQA checklists in Appendix A.  The need for mitigation measures, per se, has been avoided by integrating into the planning and design of the California network Site-Specific Environmental Commitments that ensure that any and all potential impacts do not exceed less-than-significant levels.  This approach was especially beneficial with respect to cultural resources, biological resources, and land use issues. 

As a result of the rigorous alternatives evaluation criteria designed to avoid impacts along with Level (3)’s Environmental Commitments, no impacts or areas of concern result from the proposed actions.  Level (3) concludes that there are no issues remaining that would change the conclusions of this impact assessment.

2.0 PROJECT PURPOSE AND NEED

Level (3) is authorized to build a state-of-the-art underground fiber optic system that relies on internet technology and protocols and sets new standards for the telecommunications industry to serve the burgeoning communication needs of California.  The California Network (Figure 1) is part of the 15,000-mile national network that will change the way people across the U.S., and ultimately the world, communicate. 

2.1     Purpose of the project

The purpose of the California Network project is to offer businesses and communities in California competitive choices in the provisioning of innovative and efficient telecommunications services and equipment.  Such choices offer significant benefits to end users in our State, including lower prices, faster and more reliable data transmission, and increased diversification.  Level (3) will offer a variety of services to enhance user’s Internet access, phone calls, faxes, and other telecommunication needs.

The design of this network integrates the latest technology with sufficient capacity, bandwidth, and speed to meet rapidly expanding consumer demand with minimal environmental impacts.  The Level (3) network is the first to provide Gigabit Ethernet as a standard option for directly connecting customer server and network equipment.  Interconnection of the California network with Level (3)’s international network will build upon a combination of facilities-based and resold switches, interexchange points of presence, central offices, and gateways.  The Level (3) international network is the first such network optimized end-to-end for IP technology.

2.2  PROJECT NEED

The project will provide the benefits of competition to the consumers of the State of California, which is one of two areas in the U.S. that have been given priority in Level (3)’s schedule for network implementation.  Construction of the world’s most sophisticated and technologically advanced telecommunications network will keep California at the forefront of internet technology and availability, and ensure services second to none well into the future.  By implementing state-of-the-art technology, Level (3) can provide competitive service with minimal environmental impacts.  Level (3) firmly believes this project will have a positive impact on the communities served by the network by providing a range of cost-effective telecommunications services, new infrastructure, and local jobs.

The need for the 23 off-ROW project elements is addressed in more detail in Section 3.0 Project Description.

3.0  PROJECT DESCRIPTION

This section provides a broad overview and regional perspective of the California Network and its elements.  The 23 off-ROW project elements that are subject to CEQA analysis are described in detail in the Appendix A checklists.  On-ROW network elements are briefly described in Appendix G, and described in greater detail in the Facility Construction Workbooks.

3.1      INTRODUCTION

Level (3) is developing the first international fiber optic voice and data transmission network optimized for internet technology.  Level (3)’s network will make possible a major and highly beneficial shift in communications.  Information is typically transferred worldwide over the Internet via high-bandwidth fiber optic cables.  Information that moves over the Internet is broken into pieces called "packets.” These packets are coded with address information for delivery and reassembled into their original form upon reaching their proper destination.  Two important communication tools make this process work.  One divides and reassembles the packets while the other ensures packets reach their correct destination.  Together, these tools allow for a single, unbroken connection between sender and receiver, and make data transmission much quicker and more efficient than transmission through traditional circuit-switched networks designed almost a century ago.  The Level (3) network embraces the “packet-switched” design using an Internet-based technology.  Unlike other planned major fiber optic networks, Level (3)’s system will combine both local and long distance connections, linking customers end-to-end across the United States.

As part of this ambitious effort, the company is building a 15,000-mile Long-Haul Network across North America.  The vast majority of this network will be located within utility ROW.  Level (3) has targeted proposed routes in California and in the Boston-to-Washington D.C.  corridor as first priorities in its nationwide network because of their ability to link major U.S. population centers.  In California, Level (3) is building two main routes covering approximately 2,000 miles.  Level (3)’s California Network project includes the design and construction of a city-to-city fiber optic network with multiple fiber ducts. The California Network will serve the entire state and will link California with the rest of the U.S.  and the world (Figure 1).

Level (3) was granted a CPCN in Decision 98-03-066 by the CPUC to provide switched and dedicated, resale, and facilities-based, inter-exchange and local exchange telecommunications services in California.  The original CPCN Decision did not address construction of project elements outside utility ROW.  Such construction is required in some locations for Long-Haul cable placement or support facility development.  Collectively, these off-ROW activities constitute a “project” as defined by CEQA.  The checklists in Appendix A provide a detailed description and impact assessment of each project element. 

The types of off-ROW support facilities addressed in this PEA that are required to make the network operational are:

·        In-Line Amplification Units (ILAs) – The technology used in Level (3)’s fiber optic network requires amplification of the light signal being transmitted through the fiber approximately every 60-miles along the Long-Haul network.  The proposed ILA units occupy approximately 3,000 square feet, with a total of approximately 5,000 square feet of total development at the site;

·        Regeneration Units (3Rs) - A regeneration station is an integral part of the operation of a fiber network.  Regeneration is the process of re-shaping, re-timing, and re-modulating the optical signal.  The resulting signal is filtered of noise and directed to the end destination along the fiber.  The optical signal is converted to an electrical signal and then back to an optical signal through the 3R processing.  Current technology limits the distance an optical signal can travel to about 300 miles without going through a regeneration process.  The 3R station, which requires about 6,000 square feet of space, would be assembled at the site and would contain equipment to regenerate the signals carried on the fiber optic network;

·        Distribution Nodes (D-Nodes)The Long-Haul fiber optic network is connected to local telecommunication systems through distribution nodes.  A D-node facility size is about 20,000 square feet, subject to local building and zoning codes.  The larger size of a node (compared to an ILA or 3R) allows the installation of additional hardware needed to connect the fiber optic network to local telecommunication systems.  A particular D-Node will perform the ILA or 3R function, depending on its location along the network; and

·        Terminals - A terminal, which typically marks the point where two segments of the running line come together, is designed to direct traffic (signals) to major distribution centers and elsewhere on the Level (3) network.  These facilities are also designed to allow other telecommunication customers to co-locate within the facility.   Depending on its location along the network, a terminal will also perform ILA, 3R, or D-Node functions. 

The project elements described herein are necessary and sufficient to operate the system and meet existing and expected demand.  Any further construction or expansion of the network and associated support facilities is speculative because of the rapidly changing technology in this industry and is not proposed herein.  The ultimate configuration of the project elements may vary because of site configuration, engineering constraints, or the presence of drainage constraints, natural resource concerns, wetlands, or cultural or historical resources.  Because of their modular construction, huts can be added to ILA sites as service load increases and additional fiber optic cables are installed in unused ducts. 

For the project herein proposed, each ILA, 3R, D-node, and Terminal will have signal amplification and emergency generator capabilities needed to service a maximum of four fiber optic cables.  Each 3R will have regeneration capabilities required to service up to four cables, as will those D-Nodes, and terminals that must also serve a 3R function based on their location along the California network.  Four fiber optic cables are sufficient to meet the identified needs of Level (3) and its lessees. 

While Level (3)'s Long-Haul Project will include laying 12 fiber ducts that could potentially carry fiber optic lines in the future, it is unknown at this time whether this capacity will ever be put into use.   Level (3) has made a business decision to include additional fiber optic cable capacity in this manner so that future “installation” of such cables will not require ground disturbance along the conduit right-of-way with the attendant environmental impacts.  Level (3) may utilize this capacity in the future or may lease the capacity to other carriers, thereby minimizing future ground disturbance by the industry as a whole.  Additionally, the incremental cost of laying empty conduit now, as compared to having to go back at some time in the future and lay more conduit, is relatively small.  At this time, however, Level (3) has no definite plans to use any capacity beyond the four ducts herein addressed, and the possibility of such use is highly speculative.  Rapid technological development has already significantly increased the information capacity of a single line and may render the additional capacity unnecessary.  Moreover, it is anticipated that technological advances in fiber optic technology will minimize both the need for and size of ancillary equipment such as ILA, 3R, D-Node, and Terminal facilities, such that it would be speculative to plan for such facilities at this time.  Finally, the number and capacity of fiber optic cable systems being installed by other carriers makes the future market for additional fiber optic cables uncertain and speculative.  According to CEQA Guidelines, the possible future expansion of a project, which is speculative, need not be considered in determining the significance of the environmental effects caused by a project. 

3.2 Project Location

As herein defined, a “location” is the general area or vicinity in which a network element is situated.  Locations of all 40 elements supporting the California Network are provided in Figure 2 and Table 1. 

Of the 40 network elements shown in Figure 2 and Table 1, 23 are located outside of ROW and not within existing telecommunications facilities.  These 23 project elements include 19 support facilities and four Workarounds.   Each is addressed in detail in the site-specific CEQA checklists (see Appendix A).  Thirteen (13) additional ILAs will be located on existing utility ROW.   Each is briefly described in Appendix G and more fully addressed in the site-specific Facility Construction Workbooks.  The four Gateways will be co-located in existing telecommunications facilities and are outside the scope of this PEA.

The “Map ID” numbers in Table 1 correspond to the identification numbers on Figure 2.   The 23 project elements are assigned MAP ID numbers 1-23, the 13 on-ROW ILA sites are assigned MAP ID numbers 24-36, and the 4 Gateways are assigned MAP ID numbers 37-40.  The right-hand column in Table 1 (“PEA Status”) identifies the 23 project elements as “Included,” the 13 on-ROW ILA sites as “Line Book,” and the four Gateways as “Not Applicable.” In Appendix A, the tab number for each project element corresponds the MAP ID number in Table 2 and identification number on Figure 1.

The five types of network support facilities (i.e., ILAs, 3Rs, D-Nodes, Terminals, and Gateways) are positioned along the network to perform functions necessary to provide integrated telecommunications services throughout the State of California, and to link California users with users across the nation and much of the world.  Workarounds are located adjacent to the running line ROW in areas where engineering or environmental concerns required the running line to diverge from the ROW.

After travelling approximately 60 miles along the Long-Haul network, signals require amplification, a function performed by an ILA station.  However, as the amplified signal travels along the fiber, it also becomes increasingly distorted because of splicing and imperfections in the fiber.  After the fifth ILA in a series, the signal can no longer just be amplified to maintain system standards.  It must be re-generated, re-shaped, and re-timed at approximately 300-mile intervals, a function of a 3R station.  A typical 3R facility also provides the signal amplification function of an ILA station.  D-Nodes are required to distribute signal to customers.  A D-Node and Terminal may also perform the ILA or 3R function depending on its relative location along the network.  Similarly, Terminals may also incorporate D-Node capabilities as their position along the network may require.  Thus, while an ILA per se may not exist at every 60-mile interval along the Long-Haul running line and a 3R per se may not exist at every 300-mile interval, their functions are accomplished at these intervals by other support facilities.

Table 2 provides a summary of characteristics of each of the 19 (non-Workaround) support facilities that are key to assessment of impacts from the proposed action(s).  Information particularly important to assessing construction-related impacts include the presence and usability of on-site buildings, the size of the area of grading, and size of the primary structure.  The most important factor for assessing operational impacts is the capacity of the emergency generator.  A detailed analysis of the impacts of each of these 19 support facilities and the four Workarounds with regard to each of the 16 impact assessment areas is provided in the Appendix A checklists.

3.3  CONSTRUCTION AND OPERATION OVERVIEW

Section 8, Description of Facility, of each Appendix A checklist provides a summary description of the construction and operation activities associated with the project element.  Impacts at Workarounds are restricted to the construction-phase since operations-phase activities are negligible (i.e., Workarounds are functionally identical to the running line).  For the other 19 project elements, impacts associated with both facility construction and operation must be assessed. 

Construction Activities

Development of ILA, 3R, D-Node, and Terminal facilities may include some or all of the following, depending on the functions and characteristics of the particular site:

·        Pre-construction surveys as required to mark environmentally sensitive resources for avoidance;

·        Site brush clearance and grubbing;

·        Building demolition and debris removal;

·        Minimal grading;

·        Pouring of a foundation slab and driveway improvements;

·        Delivery of prefabricated building components;

·        Assembly of prefabricated structures or buildings;

·        Connection of the facility to the Long-Haul network (cable installation and hookup,  see Workaround construction, below).

·        Connection of utilities (electrical power, telephone, sewer and potable water);

·        Installation of fencing; and

·        Site finishing (e.g., landscape vegetation, architectural treatments).

Figures 3 is an artist’s representation of a 4-hut ILA installation with generator shelter (sufficient to service four fiber optic cable fibers), while Figure 4 is an artist’s representation of delivery of a single ILA hut to the construction site. 

Off-site staging and parking will not be required at any of these facilities during either construction or operation phases.

Construction at Workarounds will involve the following:

·        Pre-construction surveys to mark environmentally sensitive resources for avoidance;

·        Site brush clearance and grubbing;

·        Disturbing a section of earth, approximately 1 foot wide by 5 feet deep, by means of plowing, trenching, or boring (maximum width of ground disturbance by vehicles is 20 feet);

·        Inserting PVC innerducts within the trench while simultaneously backfilling the trench after the innerduct is installed; and

·        Burying handhole structures to connect innerduct sections.    

Table 3 of each checklist in Appendix A provides detailed quantitative and descriptive information on the construction and operation activities at each site, including the following:

·        Equipment (e.g., graders, excavators, and water trucks) that will be used at the construction site.  Included are the size (in gross horsepower (hp)) and number of units of each type of equipment, and the numbers of hours per day and days that each piece of equipment will operate;

·        Numbers of trips and one-way commuting distance (miles) that members of the construction crew will travel to the construction site;

·        Number of trips per day, total number of trips, and number of one-way miles traveled by material delivery vehicles (e.g., cement and gravel trucks); and

·        The amount of material (soil) that will be disturbed during cable placement operations at the proposed site.

Methods and specifications for construction of several categories of project elements are described in detail in Appendices C and D.   These construction techniques and standards have been designed to avoid or minimize damage to the environment.  Level (3) has introduced state-of-the-art and “environmentally friendly” equipment for construction.  Technologically advanced equipment like the “spider” plow, equipment with large, low-pressure tires, and directional boring will be used whenever possible to minimize impacts to sensitive natural or cultural resources and to avoid encroachment on public roads.  Appendix E describes the measures Level (3) will implement to avoid and minimize water quality impacts during construction.

Responsiveness of Level (3)’s construction practices to environmental concerns is ensured by adoption of the issue-specific Environmental Mitigation Measures identified in the Negative Declaration IX and other relevant and appropriate measures in project planning and design.  For example, procedures and practices to control fugitive dust during site grading and cable placement will be followed as specified by local or air quality maintenance permits.  Noise will be controlled through observance of allowable work periods, generator shelter insulation and placement, and construction equipment mufflers.  Use of equipment that meets BACT will help reduce the potential for air quality impacts.  These measures, which have been incorporated into Level (3)’s standard operating procedures, are termed “Environmental Commitments” in the checklists.

The construction duration for an ILA site is 30 to 45 working days, depending on the characteristics of the particular site and associated logistic considerations.  The construction duration for a 3R facility is approximately 24 weeks, while that for a D-Node or Terminal is approximately 28 weeks.  Workaround construction will vary from several days to several weeks, depending on the length of the Workaround.  Construction activities within an air basin will be sequenced, as necessary, to avoid significant air quality impacts, based on comparison of estimates of district-total emissions to conservative thresholds (see Section III of the Appendix A checklists).

Level (3) does not currently know when approval for construction of off-ROW project elements will be granted and station construction can be initiated; therefore, the precise construction schedule has not been established.  However, Level (3)’s commitment to sequence construction where necessary to achieve environmental compliance is unambiguous.  Construction schedules will be detailed in Level (3)’s Quarterly Reports to CPUC as well as in the segment Line Books. 

The company's timetable for the Long-Haul network calls for the completion of both the Easterly and Westerly Sacramento to Los Angeles routes before the end of year 2000.

Operation Activities

The ILA, 3R, and D-node sites that perform ILA functions (i.e., ILA D-Nodes) will not be permanently staffed.  Operational impacts will be associated with the approximately weekly site visits for data logging and maintenance and the weekly automated testing of the emergency generators (which does not require a site visit).  The 3R D-nodes (i.e., those D-Nodes that also perform the 3R function) and Terminals will be permanently staffed (3 individuals each).  Operational impacts at these sites will be associated with daily commutes and use of the facility , and automatic emergency generator testing.

Table 3 of each Appendix A checklist provides detailed quantitative and descriptive information on the operation activities at each site, including the following:

·        Size/gross horsepower of the standby generator and its duration of activity; and

·        Number and distances of vehicular trips to the site associated with site operation, maintenance, and data logging.

Except for the occasional inspection visit, there are no operation activities associated with the Workarounds. 

3.4        Required Permits and Approvals

Consistent with the Environmental Mitigation Measures identified in Negative Declaration IX, all necessary local, state, or federal permits, and approvals will be obtained for each ILA, 3R, D-node, Terminal, and Workaround.   These permits and approvals are discussed in detail in each Appendix A checklist under Item 10 (Other Agencies Whose Approval Is Required) of the “Environmental Checklist” section and under the relevant impact assessment areas of the “Environmental Impacts” section.

3.5        Level (3) Environmental Commitments

Level (3) is committed to avoiding or reducing to less-than-significant levels any potentially significant environmental impacts resulting from off-ROW work activities.  This goal will be met through implementation of Level (3)’s Environmental Commitments (based on the Mitigation Measures in the Negative Declaration IX and other appropriate environmental concerns), Level (3)’s corporate policies on environmental protection and safety, and any additional requirements that CPUC may impose based on its Initial Study.  These commitments and corporate policies are addressed below.  Level (3) continues to file its Quarterly Reports as required by the CPCN, and will integrate the project elements into this reporting process once the CPCN is modified.

Environmental Mitigation Measures

Level (3) has incorporated all of the mitigation measures specified in Negative Declaration IX, as well as additional appropriate measures, into the planning, design, construction, and operation of the project elements addressed in this PEA.  Therefore, all actions previously identified as mitigation measures for ROW network construction and operation are now part of Level (3)’s Environmental Commitments for off-ROW activities.  These Environmental Commitments include:

·        Measures to avoid or minimize potential impacts to various resources;

·        Commitment to obtain all approvals and permits required for construction and operation of the project;

·        Coordination and/or consultation with local and resource management agencies;

·        Notifications to adjacent property owners;

·        Coordination with other utility projects in the area; and

·        Documentation and reporting of compliance measures.

Level (3)’s decision to reconfigure the network with emphasis on placement of project elements within ROW, on developed parcels, and on disturbed sites is a strong commitment to maintaining the quality of California’s environment and being responsive to CEQA.

Site-specific details of how Level (3) will implement its Environmental Commitments are provided in the Appendix A CEQA Checklists for each element.  The site-specific actions proposed in these checklists are necessarily preliminary (based on field reviews of sites and rely upon applicable regulations and input from local agency contacts) and subject to final agreement by authorizing agencies and permit conditions which may be imposed at the local level. 

Level (3) Corporate Policies and Approach to Environmental Quality

Above and beyond Level (3)’s Environmental Commitments, this project incorporates Level (3)'s corporate policies and procedures on environmental quality as standard measures in project design, construction, and operation. 

Level (3) has issued an "Environmental/Cultural Resources Philosophy" statement that defines what Level (3) expects from its employees and contractors.  The statement promotes employee and contractor awareness of the company's goal to comply with the conditions of its CPCN and permits and thus protect the long-term quality of the environment wherever it constructs.  Native American, archaeologists, endangered species specialists, and environmental inspectors currently provide oversight during Long-Haul construction, and are expected to do the same for off-ROW reviews.

Level (3)’s multidisciplinary team of in-house environmental specialists communicates the company’s commitment to compliance with the conditions of its CPCN and various permits, and ensures that all contractors are aware of the adverse impact that non-compliance could have on both the environment and the construction schedule.

Level (3)’s commitment to protecting the quality of the environment includes, but is not limited to:

·        Utilizing a highly reputable contractor with experience with California's environmental policies, laws, and regulations, as its construction contractor.  The construction contractor then hired a national engineering firm with a strong presence in California to manage the acquisition of the needed permits by subcontractors;

·        Training the construction managers and crews and providing guidance to construction managers and crews via permit workbooks;

·        Employing a site selection process that emphasized environmental protection over cost, and was successful in siting all facilities on developed and/or disturbed properties;

·        Implementing state-of-the-art and costly “environmentally-friendly” construction methods to avoid or minimize impacts to sensitive or regulated areas.  Such methods include, but are not limited to:

·        Boring under streams and sensitive resource areas instead of plowing through them;

·        Employing "spider" plows that leave a smaller "footprint" in sensitive areas; and

·        Putting larger tires on vehicles to reduce soil disturbance and compaction;

·        Requiring construction contractors and subcontractors to define and implement very aggressive safety and environmental protection programs;

·        Employing experienced environmental inspectors for each construction segment who take the lead for their respective segment-specific environmental teams in ensuring compliance with the CPCN Decision and permit conditions; and

·        Actively seeking opportunities to participate in "joint-build" opportunities in order to reduce costs and minimize environmental impacts.

4.0  ENVIRONMENTAL SETTING

Item 9, Surrounding Land Uses and Environmental Setting, of the “Environmental Checklist” section of each Appendix A checklist includes a discussion of the setting of the particular (on-ROW) project element.  These discussions are supported by Figure 5 that shows the surrounding land use and by a set of photos that visually display the site characteristics as well as those of the surrounding landscape.  Figure 6, the photo key map, identifies the vantage points from which each photo was taken.  Figure 7, the conceptual plot plan, schematically shows actual or proposed development appurtenances in the immediate vicinity of each non-Workaround element, while Figure 8 (Figure 7 for the Workarounds) depicts the locations of public and sensitive receptors relevant to air and noise analysis.  As appropriate and relevant, the checklists also include figures depicting the presence of wetlands and floodplains within the vicinity of the project element.

In addition to the Item 9 setting description, many issue-specific sections under the “Environmental Impacts” section of these checklists include a “setting” discussion that describes those aspects of the local environment of particular concern to that specific issue area.

Table 2 provides a summary of the salient features for each non-Workaround project element.  Information provided in Table 2 includes:

·  Proposed location;

·  Zoning designation;

·  Parcel size;

·  Project element space requirement;

·  Size of existing building (if present) and demolition status;

·  Type and status of existing fencing;

·  Size of new buildings (main facility and generator structure) ;

·  Generator and fuel tank capacities;

·  Area of grading or otherwise disturbed surfaces;

·  Facility staffing requirement; and

·        Estimate of solid waste volume to be generated during construction.

In addition, The Appendix A checklist for each of the 23 off-ROW project elements includes detailed maps showing the locations and boundaries of each site. 

The 13 on-ROW ILA sites are briefly described in Appendix G that includes generic designs for the 3000- and 5000-square foot ILA facilities.  Construction Workbooks are being developed to provide all CPUC-required information for these off-ROW ILAs to the construction crews.  The Construction Action Lists (CALs) in the segment Line Books are also being updated to: (1) denote the locations of proposed on- and off-ROW facilities as construction exclusion areas; (2) specify the permitting, monitoring, and mitigation requirements; and, (3) identify the need for CPUC approval prior to construction (e.g., the CAL inserts will be “gray” until approval is granted).

5.0 Environmental Impact Assessment Summary

A detailed assessment of impacts for each project element was conducted by addressing each of the 86 questions contained in the CEQA Checklist.  The results are presented in the 23 element-specific Appendix A checklists.   This assessment incorporated Level (3)’s Environmental Commitments, which include the mitigation measures required by the Level (3) CPCN Decision (Appendix B) and other appropriate actions.  The detailed assessment process was used to identify potential environmental impacts for which implementation of these Environmental Commitments will be required.  In this way, the Environmental Commitments became integral components of Level (3)’s project design and planning.  

Assessment of potential impact requires that thresholds of significance be defined.  The thresholds defined in the 1998 CEQA Revisions and Checklist were employed in this PEA.  Each of the 86 detailed questions in the CEQA Checklist provides a description of how significance is to be judged.

5.1   IMPACT ASSESSMENT METHODOLOGY

Assessment of project-related impacts proceeded as a four-step process, as follows:

1.            Preparation of field questionnaires;

2.            Implementation of site visits;

3.            Discipline-specific impact analyses; and

4.            Cumulative impact assessment.

Each of these four steps in the assessment process are discussed in the following paragraphs.

Preparation of Field Questionnaires

To ensure that all information needed for impact assessment was acquired in an expeditious manner, field questionnaires were developed.  Five such forms were developed, as follows: (1) General Agency Questionnaire, (2) General Field Questionnaire, (3) Cultural Questionnaire, (4) Biological Questionnaire, and (5) Hazards Questionnaire.

The general field and general agency questionnaires includes information required to address all land use-related areas as well as air quality, noise, water quality, and geology issues.

To ensure the thoroughness of these questionnaires and their responsiveness to CPUC needs, Level (3) conducted a detailed reevaluation of existing checklists subsequent to receipt of CPUC comments on the May 21st and June 18th submittals.  With Team members from all disciplines assembled, each existing checklist was compared to CPUC comments and amended, as appropriate, for completeness. 

Site Visits

Once the questionnaires were complete, a multidisciplinary team visited each site.  In general, each field team included a biologist, a land use planner, and a cultural resources specialist.  These individuals evaluated the site, filled out the questionnaires, and in cases where the need was identified, specified additional types of expertise for which a follow-on site visit would be appropriate.  For example, the cultural resources specialist made an initial evaluation of the historical significance of any structures on the site and, as appropriate, identified the need for an Historical Architect to visit the site and evaluate its historic significance.  The Team took numerous photographs, particularly of site attributes whose evaluation might require a site visit by team members with other expertise.  The photos and field questionnaires were then evaluated in detail for final determination regarding the need for additional site visits.  The land use planner also took the opportunity to visit local agency offices and acquire land use plans, parcel maps, and other pertinent background information.

Once the field work was over, the field checklists were completed and distributed to team members involved in the detailed evaluation of impacts.

Discipline-Specific Evaluation Methodologies

While the information from the site visits was essential to the impact evaluation, it was not all that was required.  While these field efforts were underway, Level (3) engineers were conducting preliminary design of the project elements and providing key information on design, construction, and operation parameters needed for impact assessment.  Once this information was developed, the basis for detailed, discipline-specific impact assessment was established.  In the following paragraphs, the methodologies utilized in each impact assessment area is summarized.

Land Use, Aesthetics, Agricultural Resources, Mineral Resources, Population and Housing, Public Services, Recreation, Transportation/Traffic, Utilities and Service Systems

Following the field visits, information in the field checklists, acquired documents, and follow-up telephone interviews with personnel from appropriate agencies was collected and analyzed to determine the overall environmental impacts of each project element and to address the specific questions in the CEQA checklist.  Some of the most important information included the assessor’s map and parcel number of the site, information on surrounding properties, and the general atmosphere of the surrounding area.  Photographs taken during the site visit were particularly helpful in addressing aesthetic issues.  Primary documents reviewed included city and county general plans and zoning ordinances.  Information available on websites, such as city and county population trends and distributions and names of designated scenic highways, also proved useful.  Considerable information and confirmation of information in documents was obtained through telephone conversations with agency and other personnel (e.g., planners and engineers).  Additional information, such as location and capacity of solid waste landfills from cities and counties, was independently gathered to fill gaps in the data base.

Each analyst determined the significance of project impacts using her/his judgement and experience with similar projects.  Unofficial opinions of city and county staff members were also weighed into the determination.  Quantitative estimates of project contributions and limiting values that could be used to assess impacts were only available for a few issues (e.g., solid waste generation and landfill capacities).  For example, the requirement to obtain a conditional use permit when the project conformed with land use and zoning (but the zoning ordinance did not specifically list the project or a similar type of project) was usually not considered by itself to be a significant impact on land use.  Conditions that may be attached to the use permit usually have to do with site plot plan layout, fencing, egress/ingress, and similar conditions.  These types of conditions do not result in significant impacts to the environment. 

Air Quality/Noise

The air quality and noise impact assessments were based on detailed identification and quantification of construction and operation activities and equipment.  These data are summarized in tabular form in each checklist.  The key information derived from the field visits included distances to public and sensitive receptors and environmental setting information relevant to identifying ambient noise levels.  To the maximum extent possible, air quality and noise assessments were integrated to assure consistency.  Construction and operation impacts were assessed separately because activities were substantially different and typically subject to different regulations. 

For construction and operation phases, the analytical sequence proceeded as follows:

·        Review and summarize federal, state, and air district regulations, local noise regulations and ordinances, and the noise element of the county or city general plan;

·        Identify and describe relevant source activities and parameters;

·        Assemble emission factors and compute emissions;

·        Describe noise levels produced by source activities;

·        Describe project features that are designed to keep air quality and noise impacts below a level of significance; and

·        Determine the resulting level of significance.

Proposed project design features that keep air quality and noise impacts below a level of significance at individual project elements include the following:

·        Fugitive dust control measures;

·        Construction and operation emissions and noise would comply with local, state, and federal emission standards;

·        Construction scheduling would be coordinated with other petitioners in locales where activities could potentially cause considerably cumulative impacts; and

·        If significant construction noise were expected, Level (3) would inform, at least two weeks in advance, surrounding property owners and occupants, particularly school districts, hospitals and residential neighborhoods, of the days when the most noise would occur.

Compliance with these actions would be documented in Level (3)’s quarterly report to the CPUC.

Biological Resources

Prior to conducting a site visit, the California Natural Diversity Database was searched for occurrence records of special status biological resources on the 7.5 minute USGS quadrangle map(s) where the site is located.  Potential habitat for each of these species was evaluated during a site visit and their potential to occur is described in Table 5 of each checklist.

During the site visit, a biologist walked over the property for one to two hours.  Notes and photographs were taken to document biological resources located on and adjacent to the site.  Special attention was given to species identified during the CNDDB search and protected or sensitive habitats.  In addition to evaluating species and habitats on the site, consideration was given to the impact of the project on wildlife movement corridors.  All biological features and photographic points were mapped onto a parcel map.

Cultural Resources

The protocols contained in Level (3)’s Long Haul Fiber Optics Project Cultural Resources Procedures (Parsons Brinckerhoff Network Services, 1999), requiring records searches and field survey, where appropriate, were followed for each facility site, as summarized below.  A technical report, providing more information on the results of the records search and field survey has been prepared for each of the facility sites.

For Cultural Resources questions, record searches were obtained from the appropriate information center of the California Historical Resources Inventory System.  These searches had two objectives: (1) to determine whether previous archaeological investigations have been conducted in the project area, and (2) to provide information on known historic sites or culturally sensitive areas on and in the vicinity of the proposed facility.  The Information Center staff checked maps on file and provided maps showing locations of cultural resources within one mile of the parcel, and provided site records.  The information centers sent a bibliography of survey reports and reports of other investigations for the one mile radius.  The Information Centers also checked the Inventory of Historic Resources from the Office of Historic Preservation, which includes State Historic Landmarks and properties, listed or eligible for the National Register of Historic Places, as well as properties evaluated, but not determined eligible.  Other sources checked by each information center are listed in each checklist.  

In addition, the Level (3) Team sent letters dated June 3, September 3, and October 22, 1999 to the Native American Heritage Commission (NAHC) requesting a search of the NAHC Sacred Lands file and identification of contact persons for follow-on contact/consultation for each of the facility sites (Mason, 1999a, 1999b; White, 1999).   The responses, dated July 9, September 17, and November 9, 1999, indicated that the NAHC searches revealed no available site-specific information on Sacred Lands (McNulty, 1999a, 1999b, 1999c).  The response letters cautioned that absence of information did not necessarily indicate the absence of cultural resources.  A list of Native American contacts that might serve as sources of additional information was also provided.   For each project element, Level (3) has sent letters to all NAHC-identified Native American contacts for the particular county, notifying them of the Level (3) project activities and requesting information they might have on sacred lands.  Any response indicating the possible presence of Sacred Lands will be followed up with a detailed, site-specific evaluation utilizing the expertise of the relevant Native American contacts. 

For Cultural Resources Question c), regarding paleontologic resources, a consulting paleontologist, Dr.  E.  Bruce Lander, obtained information on previously recorded fossil localities and the potential for specific formations underlying the project element parcels to yield fossils from the Invertebrate and Vertebrate Paleontology Sections of the Natural History Museum of Los Angeles County; the San Bernardino County Museum; the University of California, Riverside, Campus Museum; and the University of California, Berkeley, Museum of Paleontology.  He also consulted the California Division of Mines and Geology Geologic Map Series and the Society of Vertebrate Paleontology Bulletin, as well as other sources specific to individual parcels cited in the checklists.

Photographs of parcels were taken by environmental planning staff and were reviewed by the Consulting Archaeologist, Dr.  Roger D.  Mason, to determine if structures that appeared to be more than 50 years old were present and to determine whether open ground (not paved or covered by gravel) was present.  If structures that appeared to be more than 50 years old were present, they were evaluated for the California Register by architectural historians Richard Starzak, Gail Miller, and John Snyder.  The results of the evaluations are provided in the checklists as part of the response to cultural resources Question a).  Appropriate DPR 523 forms were filled out for evaluated structures.  If open ground was present, a field survey was performed by qualified archaeologists.  The results of the surveys are provided in the checklists as part of the response to cultural resources Question b).

The determination of the level of impact was based on whether significant resources were known to be present on the proposed parcel or whether there was only a potential to encounter such resources.  If a known significant cultural resource was identified on the parcel, the level of impact would normally be assessed as “Less Than Significant With Mitigation Incorporation.” However, if project design would result in avoidance or no significant effect on the known significant resource, the level of impact was assessed as “No Impact.” If there were prehistoric or historic sites or isolated artifacts recorded near the parcel, or if historic structures were known near the parcel, there would be a potential for encountering subsurface prehistoric or historic resources during construction.  In this case, the level of impact was assessed as “Less Than Significant” because Level (3) has made an environmental commitment to provide archaeological monitoring during construction in these situations.  For paleontology, the presence of fossils found elsewhere in formations identified as being under the parcel would suggest the potential for encountering similar fossils on the parcel.  All potential paleontologic impacts were assessed as “Less Than Significant” because Level (3) made an environmental commitment to provide paleontological monitoring during construction wherever necessary.

Geological Resources

The geological resources assessment focused on examination of specific geologic hazards to people and/or structures associated with each of the proposed sites.  The geologic hazards evaluated include: (1) Alquist-Priolo Earthquake Zones; (2) recently active faults; (3) potential ground failure; (4) landslide potential; (5) subsidence; (6) erosion; and (7) expansive soils.  This evaluation was based on current available literature, proposed facility structural design parameters and intended use, and Level (3)’s prior environmental commitments to this project. 

Hydrology and Water Quality

The factors considered to evaluate the significance of an impact included site habitation, proximity to specifically designated recharge areas, potential for flooding from storm events or from a dam failure, amount of topographic relief, and potential for inundation by tsunami or seiche. 

The primary references used to address each potential impact included County and City General Plans, floodplain maps from Vista Information Solutions, and inundation maps from the California Office of Emergency Services.  If a site was located within a groundwater recharge area or within the area subject to inundation by a 100-year flood, dam failure, tsunami, seiche, or mudflow, the impact was determined to be less than significant because the facilities will be placed within an existing building and will not be permanently occupied.  A “no impact” designation was assigned to those sites that were not located within a groundwater recharge area or within an area subject to inundation by a 100-year flood, dam failure, tsunami, seiche, or mudflow.

Hazards and Hazardous Materials

For questions relating to hazards and hazardous materials, a reconnaissance of the site was conducted and a record search was requested from Vista Information Solutions, Inc.  During the site reconnaissance, a field questionnaire was completed and photographs of the project sites were taken by environmental planning staff.  The field questionnaire and photographs were used to document factual information about the site and surrounding properties including conditions that might expose people or structures in the area to a significant risk of loss, injury, or death from safety hazards or hazardous materials.

The VISTA records search consisted of a “Site Assessment Plus Report” and a “NEPA Checklist” report.  The “Site Assessment Plus Report” covered 18 federal and state government databases containing environmental information about properties in the vicinity of the project site including properties that transport, use, or dispose of hazardous materials, emit hazardous emissions, and handle acutely hazardous materials.  The “NEPA Checklist” report covered 11 information sources that identified nearby properties containing historic landmarks, parks, wild and scenic rivers, wildlife preserves, areas of Native American significance, floodplains, wetlands, and endangered species. 

The field questionnaires, photographs and record searches were compiled and reviewed to determine if the project site or the proposed activities would create a hazard to the public or the environment, including safety hazards for people residing or working in the project area. 

5.2  CUMULATIVE IMPACT ASSESSMENT METHODOLOGY

In the context of CEQA, cumulative impacts are two or more environmental effects which, when considered together, are considerable or which compound or increase other environmental impacts.  Additionally, the scope of the cumulative impact analysis in this PEA includes the requirements of the Negative Declaration for the Level (3) network regarding construction within existing utility ROW.  Thus, Level (3) must coordinate with other carriers and consult with affected local agencies so that any cumulative impacts are minimized.  In addition, Level (3) has submitted reports to CPUC prior to the beginning of each quarter that summarize construction projects anticipated in the next three months.  The scope of the cumulative impact assessment in this PEA is limited to those attributable to current and reasonably foreseeable future projects located in the vicinity of the proposed project elements.

The results of the cumulative impact assessment are addressed in the checklist for each site.

6.0        Detailed Discussion of Significant Impacts

As a result of rigorous siting criteria designed to avoid potential impacts along with general and site-specific Environmental Commitments, the proposed project will not result in any significant impacts.

7.0  alternatives to the proposed action

7.1  EVALUATION OF SITE ALTERNATIVES

Level (3)’s alternatives evaluation process was implemented within the constraints imposed by the selected “ground zero” locations along the Long-Haul network, as described in Section 3.2.   At each location, the process focused on identifying the site or sites that minimized the potential for environmental impacts while satisfying network design requirements and constraints.  Typically, sites had to be within two miles of the “ground zero” location.  Lateral siting options were largely restricted by this distance constraint. 

When initially configured (i.e., the May 21st and June 18th submittals), the suite of proposed sites for California network support facilities consisted largely of undeveloped sites.  To minimize the potential for impacts, Level (3) subsequently reconfigured the network by establishing as its primary evaluation criterion that undeveloped sites would be considered only where suitable developed or disturbed parcels could not be found.  As a result, the suite of facility sites herein proposed includes no sites that are both undisturbed and undeveloped.  In general, the alternative developed or disturbed sites at a particular location that were subject to detailed evaluation all posed comparably low potential environmental impacts.

Within the domain of developed and disturbed sites that were identified by Level (3) land agents as meeting project requirements, the following criteria were used to evaluate alternatives and select the site with minimal environmental impacts:

Criterion 1: Highest alternatives ranking was given to sites on ROW.  These sites typically posed the lowest potential for impacts to the environment.  All were highly disturbed and required no off-ROW connector routes.  Several segments of the Long-Haul running line were relocated to take advantage of available ROW acreage.

Criterion 2: Off-ROW alternative sites were ranked in the following order of preference:

1.            Sites with buildings that could be retrofitted;

2.      Developed (i.e., graded and otherwise enhanced) sites without buildings;

3.             Sites with buildings that were of sufficient size but could not be retrofitted (building demolition/removal and use of existing foundations); and,

4.             Disturbed, undeveloped vacant land sites.

Sites with rankings 1-3 typically had access and parking facilities and were often fenced. 

Other generic considerations in the alternatives evaluation process included: (1) the presence of utility corridors to and from the ROW; (2) proximity to the running line; (3) industrial, commercial, or mixed-use zoning; and, (4) presence/absence of hazardous materials contamination on and adjacent to the site.

The alternatives evaluation process resulted in selection of 13 on-ROW sites for ILA construction and 19 off-ROW sites for construction of ILAs, 3Rs, D-Nodes, and Terminals.  These 19 off-ROW sites included 9 with useable buildings, 2 developed, vacant lots, 5 with  buildings that could not be retrofitted (requiring demolition or removal), and 3 disturbed, undeveloped properties (Table 1).  In a few cases, the owner of the alternative with highest ranking was unwilling to sell at a reasonable price, requiring selection of another alternative. 

Potential Workaround alignments were evaluated with the primary criterion being avoidance of areas of potential environmental concern.  This typically involved staying as close as possible to the ROW from which the Workaround diverged.  Where alignments lacking potential environmental issues did not exist, environmental concerns were avoided using innovative engineering techniques (i.e., directional boring).  

7.2  EVALUATION OF THE NO PROJECT ALTERNATIVE

The “no project” alternative assumes that no project elements will be constructed outside of utility corridors.  Because it was not possible to locate all project elements (including portions of the running line) within utility corridors, these elements of the Level (3) project would not be built under this scenario.  As a result, the proposed fiber optic system in California would be inoperable and would probably not be completed.  Because Level (3)’s proposed project will have no significant negative impacts on the environment, selection of the “no project” alternative would not benefit the environment, and the substantial environmental benefits of fiber optic cable communications as compared to more conventional means of communication (e.g., reducing travel by providing video conferencing and electronic transmission of information, and reducing the requirements for raw materials such as copper) would not be realized. 

Under the no project alternative, the ever-increasing demand for communication services would have to be addressed through means other than Level (3)’s fiber optic cable network.  Given Level (3)’s outstanding effort to design a system with minimal impacts, construction and operation of other fiber optic-based systems would be expected to have, at minimum, comparable and probably greater impacts.   Therefore, these fiber optic-based systems would also not be approved by CPUC.  Wireless communications systems might be built to fulfill demand, but these too would be expected to have greater long-term impacts compared to fiber optic cable systems.  Alternatively, the demand for communications would have to be handled by more conventional technologies with substantially greater operational impacts than the proposed project (e.g., resource use, aesthetics, air quality, and transportation).  In addition, signals transmitted along conventional wire-based electric lines are subject to interference, a problem not faced with fiber optic cable systems.  Table 3 summarizes the potential impacts of the no project alternative by impact category.

8.0  GROWTH-INDUCING IMPACT OF THE PROPOSED ACTION

The proposed project will not foster population growth, either directly or indirectly, in the surrounding environment.  However, as part of the overall transition to a technology-based society, the Level (3) network has the potential to contribute substantially to the economic growth of California.  If Level (3)’s network or a similar fiber optic-based telecommunications system is not developed, California would be at a serious competitive disadvantage with other states and countries for high-technology industry.  The situation could have disastrous consequences for the economy of California.

The Level (3) network will serve existing demand and provide for service expansion in response to continually increasing signal transmission.  Population growth in California is not dependent on the availability of fiber optic capacity.   While Level (3)’s network will address telecommunications needs associated with population growth, business and residential use of telecommunications services continue to increase independently of increases in population.  This reflects the overall societal transition to telecommunications-based commerce.  The substantial and on-going growth in telecommunications-based services creates the need for additional capacity and new technologies apart from those associated with increasing population.  Level (3)’s network will also increase the quality of telecommunications service and contribute to the competitive choices available to existing and future users.

9.0  AFFECTED PROPERTY OWNERS

Appendix F includes a tabular listing of affected property owners.  The entries in the Appendix F table are organized by City Pair segment and project element.  For each adjacent property, tract type, parcel number, property owner, and address are provided.

10.0  sources

Mason, R.D., Chambers Group.  Written communication to Gail McNulty, Native American Heritage Commission, June 3, 1999a.

Mason, R.D., Chambers Group.  Written communication to Gail McNulty, Native American Heritage Commission, September 3, 1999b.

McNulty, G.  Native American Heritage Commission.  Written communication to Roger Mason, Chambers Group, July 9, 1999a.

McNulty, G., Native American Heritage Commission.  Written communication to David White, Level (3) Long Haul Project, September 17, 1999b.

McNulty, G., Native American Heritage Commission.  Written communication to David White, Level (3) Long Haul Project Team, November 9, 1999c.

Parsons Brinckerhoff Network Services (PBNS).  Level (3) Long Haul Fiber Optics Project: Cultural Resources Procedures, July 1999.

White, D., Level (3) Network Communications.  Written communication to Gail McNulty, California Native American Heritage Commission, October 22, 1999

  
   This site contains tables and is best viewed with Netscape or Microsoft Explorer browsers. Please report any problems to the Energy Division web coordinator.

To view the pdf documents, please download Acrobat Reader 3.0 or above, if you do not have it installed on your PC.