Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of Pacific
Gas and Electric's (PG&E) proposed Seventh Standard Substation
Project. An application for this project was submitted to the CPUC
on March 2, 2009 (A.09-03-004).
The CPUC voted on October 29, 2009 to approve the proposed project
(see Decision D.09-10-049) and
a Notice of Determination
was submitted to the State Clearinghouse. Construction of the Project
began the week of March 8-12, 2010, and was completed
in November 2010. This site provides access to public documents
and information relevant to the CEQA review process.
Background
The proposed Seventh Standard Substation Project is located in
northwest Bakersfield, Kern County, California. The proposed 4.9-acre
substation is located south of Seventh Standard Road and west of
the Calloway Canal, approximately 2.5 miles west of State Route 99.
It would be on land that is currently an almond orchard.
The new electric substation would be an automated, low-profile
facility. Electrical power would enter the substation by tapping
the Rio BravoKern Oil 115 kV power line that parallels the
south side of Seventh Standard Road. Electrical power would leave
the substation as 21 kV via distribution feeder lines, which would
interconnect with the distribution network. Construction involves
the installation of the following components:
- A new, three-bank 115/21 kV distribution substation;
- A single tubular steel pole (TSP) to be located midway between
the substation and Seventh Standard Road, and two other TSPs (drop-down
structures) to be located nearer to and east of the substation;
- Two dead-end structures on the east side of the substation;
- Up to nine distribution circuits (at full build-out) exiting
the substation in underground conduit and transitioning to the
overhead position or remaining underground; and
- A paved access road from Seventh Standard Road to the substation.
Proponent's Environmental Assessment
(PEA)
PG&E filed a PEA with the Application
in March 2009. This document provided a starting point for the environmental
review process conducted by the CPUC. In addition, PG&E's Notice
of an Application for a Permit to Construct can be found here.
Environmental Review Process
PG&E's Application and PEA were deemed complete by the CPUC
on April 1, 2009.
The CPUC has determined that an Initial Study/Mitigated Negative
Declaration (IS/MND) will be the appropriate CEQA document to be
prepared for this project. The Draft IS/MND was published on August 11,
2009 and the Final IS/MND was published on October 16, 2009.
The CPUC voted on October 29, 2009 to approve the proposed project
(see Decision D.09-10-049) and
a Notice of Determination
was submitted to the State Clearinghouse.
Construction of the project began the week of March 8, 2010,
after a Notice to Proceed with Construction was granted by CPUC.
A CPUC Environmental Monitor will be monitoring construction activities
to ensure that they are conducted in accordance with the approved
mitigation measures and permit conditions. Reports documenting construction
and compliance activities are available here.
Construction was completed in November 2010.
Final Initial Study/Mitigated
Negative Declaration
On October 16, 2009, the CPUC released a Final Mitigated Negative
Declaration for the Seventh Standard Substation Project, showing
that the Proposed Project, as mitigated, would not have any significant
effects on the environment. The Final MND details the Proposed Project,
evaluates and describes its potential environmental impacts, identifies
those impacts that could be significant, and presents mitigation
measures to avoid or minimize these impacts. The Final IS/MND can
be viewed here.
Draft Initial Study/Mitigated
Negative Declaration
On August 11, 2009, the CPUC released a Notice
of Intent to Adopt a Mitigated Negative Declaration (MND) for
the Seventh Standard Substation Project, showing that the Proposed
Project, as mitigated, would not have any significant effects on
the environment. The Draft Initial Study/Mitigated Negative Declaration
(IS/MND) can be viewed here.
The Proposed IS/MND underwent a public review period from August 11,
2009, through September 11, 2009. Comments should have been
received in writing by 5:00 p.m. on September 11, 2009, at
the email, fax, or project mailing address (see "For Additional
Information" below).
Public Informational Meeting
In order to help affected communities understand the Proposed Project
and the Proposed IS/MND and to explain how the public can participate
in the CPUC’s decision-making processes, the CPUC held an informational
workshop in Bakersfield on August 25, 2009. This informal workshop
was an opportunity to ask questions about the content of the Draft
IS/MND. While written comments may have been submitted during these
workshops, there were no facilities to record oral comments.
For Additional Information
The CPUC, through its Environmental Review Team, conducted an environmental
review of the project. To request additional information, please
contact the CPUC, as follows:
Mary Jo Borak
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-1333
Fax (415) 703-2200
Email: BOR@cpuc.ca.gov
|