Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of the
proposed Sunrise Powerlink Transmission Line Project. Applications
for this project were submitted to the CPUC on December 14,
2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). This site
provides access to public documents and information relevant to
the CEQA and National Environmental Policy Act (NEPA) review processes.
Background
SDG&E has filed an application with the CPUC to construct the
Sunrise Powerlink Project (SRPL). The CPUC is the CEQA lead agency
and the U.S. Bureau of Land Management (BLM) is the lead agency
under NEPA. This project was approved by the California Independent
System Operator on August 3, 2006. The Proponent's Environmental
Assessment was filed with the CPUC on August 4, 2006 and is
available on SDG&E's
project website.
The CPUC maintains other web pages for documents related to its
proceeding on the SRPL, where it makes available documents filed
by parties to that proceeding. The web page for Application A.06-08-010
incorporates the earlier filing, and lists documents and rulings
filed in the proceedings. The CPUC also maintains a page of general
information on the SRPL project.
The SRPL Project, as proposed by SDG&E, includes a new, approximately
90-mile, 500 kV line from Imperial Valley Substation (in Imperial
County, near the City of El Centro) to a new Central East Substation
(in central San Diego County, south of the intersection of County
Highways S22 and S2). The 500 kV portion would
approximately follow the eastern boundary of BLM lands west of El
Centro and SR 78, and would pass through Anza-Borrego Desert
State Park.
The SRPL Project also proposes approximately 60 miles of 230 kV
transmission lines from the new Central East Substation to SDG&E's
existing Peñasquitos Substation (in the City of San
Diego). SDG&E proposes to construct two segments underground
(one segment south of Ramona and another in the community of Ranchos
Peñasquitos, San Diego). Figure 1
shows an overview of the proposed project route.
EIR/EIS Scoping
On August 31, 2006, the BLM published its Notice
of Intent to prepare an Environmental Impact Statement in the
Federal Register (Volume 71, No. 169, page 51848). On
September 15, 2006, the CPUC issued a Notice
of Preparation/Notice of Public Scoping Meetings for an Environmental
Impact Report/Environmental Impact Statement. In early October 2006,
the CPUC and BLM held a series of seven public scoping meetings
in Imperial and San Diego Counties to take public comment on the
scope and content of the environmental document. The scoping comment
period ended on October 20, 2006.
A Scoping Report (Part 1) was prepared
and was sent to all repositories on November 29, 2006; see the list
of available documents below. The Scoping Report includes a copy
of every letter submitted, as well as transcripts of the public
scoping meetings and summaries of issues raised during scoping.
Decisions on EIR/EIS Alternatives
January 2007 Notice of Second Round of Scoping Meetings on Alternatives
to the Proposed Sunrise Powerlink Project. The CPUC and BLM
held a second scoping period during January and February 2007 in
order to hear input on alternatives to the Sunrise Powerlink Project.
The comment period ended on February 24, 2007. A second
Scoping Report was prepared that documents all comments received
during the second scoping period, including copies of all comment
letters and transcripts of oral comments made at the February 5-9,
2007 Public Meetings on Alternatives. The Scoping Report (Part 2)
is included in the document list below and copies have been placed
in local document repository sites.
March 2007 Notice on Alternatives Conclusions. The CPUC/BLM
Notice Regarding Conclusions on EIR/EIS Alternatives to the Proposed
Sunrise Powerlink Project was mailed to everyone on the project
mailing list during the week of March 19, 2007. The Notice
and the seven maps referenced in it may be viewed at the links presented
below under "Documents Available."
May 2007 Notice on Modified Route D Alternative. The conclusions
presented in the March Notice referenced above were based on the
feedback received from the public and agencies, along with research
conducted by the EIR/EIS team. Following the publication of that
Notice, additional input was received from the Cleveland National
Forest (Forest), including Forest's request that an alternative
be fully analyzed in the EIR/EIS that would not require an amendment
to the Forest's 2005 Land Management Plan. As a result, portions
of the Route D Alternative that were previously considered
and eliminated have been combined with new route segments, and will
be analyzed in the EIR/EIS. The CPUC/BLM
Notice Regarding an Additional EIR/EIS Alternative to the Proposed
Sunrise Powerlink Project was mailed in mid-May to announce
this change.
The May Notice announced a third 30-day public comment period that
ended in mid-June 2007. The comment letters
that were received during May and June 2007 are available for review.
From mid-June through September 2007, the EIR/EIS Team reviewed
comments on the Modified Route D Alternative and evaluated
suggested route changes. Public comments were accepted into early
October 2007, in order to allow concerns about this alternative
to be reviewed by the EIR/EIS team. The comment
letters that were received between mid-June and October 2007
are available for review.
Documents Available
Except as noted with an asterisk (*),
the following documents are available at 28
libraries and offices in the project area.
Comment letters received on
the Modified Route D Alternative from mid-June to October 2007
Comment letters received in
response to the May 16, 2007 Notice on the Modified Route D
Alternative*
CPUC/BLM Notice Regarding
an Additional EIR/EIS Alternative to the Proposed Sunrise Powerlink
Project (May 16, 2007)
Scoping Report, Part 2
(April 2, 2007)
Notice Regarding
Conclusions on EIR/EIS Alternatives to the Proposed Sunrise Powerlink
Project (March 16, 2007)
Figure
1. Imperial Valley Link Alternatives
Figure 2.
Anza-Borrego Link Alternatives
Figure 3. Central
Link Alternatives
Figure 4.
Inland Valley Link Alternatives
Figure
5. Coastal Link Alternatives Retained
Figure
6. Coastal Link Alternatives Eliminated
Figure
7. Southwest Powerlink Alternatives
Notice of Second
Round of Scoping Meetings on Alternatives to the Proposed Sunrise
Powerlink Project (January 22, 2007)
Figure 1.
Sunrise Powerlink Project Overview
Figure 2. Imperial Valley
Link Alternatives
Figure 3. Anza-Borrego Link
Alternatives
Figure 4. Central Link Alternatives
Figure 5. Inland Valley Link
Alternatives
Figure 6. Coastal Link Alternatives
Retained
Figure 7. Coastal Link Alternatives
Eliminated
Figure 8. Southwest Powerlink
Alternatives
Figure 9. Non-Wires Alternatives
Figure 10. System Alternatives
Scoping Report, Part 1
(November 29, 2006)
Notice of Preparation
(NOP) (September 15, 2006)
Figure 1.
Proposed Project Overview
Figure 2. Imperial Valley
Link
Figure 3. Anza-Borrego Link
Figure 4A. Central Link
Figure 4B. Proposed Central
East Substation
Figure 5A. Inland Valley
Link
Figure 5B. Detail of Ramona
Area
Figure 6A. Coastal Link
Figure 6B. Rancho Peñasquitos
Detail
Figure 7. SDG&E Alternatives
Fully Evaluated and Carried Forward in PEA
Figure 8. SDG&E Alternatives
Considered and Eliminated
Notice of Intent
(August 31, 2006)
SDG&E's
Application and Proponent's Environmental Assessment (August 4,
2006).
Data Requests to SDG&E
The EIR/EIS Team will submit Data Requests to SDG&E when it
needs specific information to support EIR/EIS preparation. These
requests will be made available here at the time they are issued.
Data requests submitted to SDG&E to date are provided below.
Responses to these data requests can be found at SDG&E's
website.
Data Request No. 1 (September
27, 2006)
Data Request No. 2 (November 15,
2006)
Data Request No. 3 (November 21,
2006)
Data Request No. 4 (December 6,
2006)
Data Request No. 5 (January 8,
2007)
Data Request No. 6 (January 26,
2007)
Data Request No. 7 (February 1,
2007)
Data Request No. 8 (February 16,
2007)
Data Request No. 9 (March 27, 2007)
Data Request No. 10 (April 23,
2007)
Data Request No. 11 (May 7, 2007)
Data Request No. 12 - original
(May 15, 2007)
Data Request No. 12 - modified
(June 27, 2007)
Data Request No. 13 (May 21, 2007)
Data Request No. 14 (June 1, 2007)
Data Request No. 15 - original
(June 27, 2007)
Data Request No. 15 - modified
(July 27), 2007)
Data Request No. 16 (July 6, 2007)
Data Request No. 17 (July 27,
2007)
Data Request No. 18 (August 13,
2007)
Data Request No. 19 (August 20,
2007)
Data Request No. 20 (October 20,
2007)
Data Request No. 21 (October 20,
2007)
Data
Requests to Other Entities
U.S. Department of Defense, Division of the Navy
Data Request No. 1 (July
18, 2007)
The Nevada Hydro Company, Inc
Data Request No. 1 (January
4, 2007)
Data Request No. 2 (August
28, 2007)
Data Request No. 3 (October
1, 2007)
California ISO
Data Request No. 1 (March
8, 2007)
Data Request No. 2 (August
28, 2007)
Imperial Irrigation District
Data Request No. 1 (January
4, 2007)
Data Request No. 2 (January
29, 2007)
Data Request No. 3 (April 10,
2007)
Southern California Edison Company
Data Request No. 1 (January
26, 2007)
Data Request No. 2 (August
20, 2007)
Stirling Energy Systems, Inc.
Data Request No. 1
(March 8, 2007)
Data Request No. 2 (July
27, 2007)
For Additional Information
To request additional information or to be added to the mailing
list, please contact us by email, fax, or phone, as follows:
The CPUC's Project Manager is:
Billie Blanchard, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-2068
Fax (415) 703-2200
Email: bcb@cpuc.ca.gov
|