Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of the
proposed Sunrise Powerlink Transmission Line Project. Applications
for this project were submitted to the CPUC on December 14,
2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). This site
provides access to public documents and information relevant to
the CEQA and National Environmental Policy Act (NEPA) review processes.
The CPUC voted on December 18, 2008 to approve the Final Environmentally
Superior Southern Route (see Decision D.08-12-058)
and a Notice of Determination was
submitted to the State Clearinghouse. The BLM issued a Record
of Decision approving the same route on January 20, 2009.
Background
SDG&E has filed an application with the CPUC to construct the
Sunrise Powerlink Project (SRPL). The CPUC is the CEQA lead agency
and the U.S. Bureau of Land Management (BLM) is the lead agency
under NEPA. The CPUC and BLM are preparing an Environmental Impact
Report (EIR, under CEQA) and an Environmental Impact Statement (EIS,
under NEPA), which will be published as a single joint document,
an EIR/EIS.
This project was approved by the California Independent System
Operator on August 3, 2006. The Proponent's Environmental Assessment
was filed with the CPUC on August 4, 2006 and is available
on SDG&E's
project website.
The CPUC maintains other web pages for documents related to its
proceeding on the SRPL, where it makes available documents filed
by parties to that proceeding. The web page for Application A.06-08-010
incorporates the earlier filing, and lists documents and rulings
filed in the proceedings. The CPUC also maintains a page of general
information on the SRPL project.
The SRPL Project, as proposed by SDG&E, includes a new, approximately
90-mile, 500 kV line from Imperial Valley Substation (in Imperial
County, near the City of El Centro) to a new Central East Substation
(in central San Diego County, south of the intersection of County
Highways S22 and S2). The 500 kV portion would
approximately follow the eastern boundary of BLM lands west of El
Centro and SR 78, and would pass through Anza-Borrego Desert
State Park.
The SRPL Project also proposes approximately 60 miles of 230 kV
transmission lines from the new Central East Substation to SDG&E's
existing Peñasquitos Substation (in the City of San
Diego). SDG&E proposes to construct two segments underground
(one segment south of Ramona and another in the community of Ranchos
Peñasquitos, San Diego). Figure 1
shows an overview of the proposed project route.
Final EIR/EIS
The Final EIR/EIS was released to the public on October 13,
2008. The Final EIR/EIS is available here
and is also available at numerous area libraries
and government offices. Copies of the Executive Summary of the
Final EIR/EIS along with a DVD of the complete document may be requested.
The CPUC and BLM also have a limited number of copies of the complete
four-volume Final EIR/EIS document available to the public. Requests
for documents should be made to (866) 711-3106 (phone or fax) or
via email to sunrise@aspeneg.com.
The Notice of Availability provides
further information on the approval processes for the CPUC and the
BLM. Pursuant to NEPA requirements, the Final EIR/EIS and Proposed
Land Use Plan Amendment will be available for review for 30 calendar
days from the date the Environmental Protection Agency (EPA) publishes
the Notice of Availability (NOA) in the Federal Register, which
is expected to occur on October 17, 2008. The review period
would end on November 15, 2008.
Copies of the Executive Summary of the Final EIR/EIS along with
a DVD of the complete document may be requested. The CPUC and BLM
also have a limited number of copies of the complete four-volume
Final EIR/EIS document available to the public. Requests for documents
should be made to (866) 711-3106 (phone or fax) or via email to
sunrise@aspeneg.com.
Draft EIR/EIS
The CPUC and BLM published the Draft EIR/EIS in January 2008. Please
note that the Final EIR/EIS (described above) includes the entire
text of the Draft EIR/EIS, modified where necessary in response
to comments on the Draft EIR/EIS. The original text of the Draft
EIR/EIS document is available here.
EIR/EIS Alternatives
Throughout 2007, the CPUC and BLM gathered information on alternatives
to the proposed Sunrise Powerlink Project through an extensive public
involvement process. Information and documents from that process
are available here.
Documents Available
In addition to the EIR/EIS, other documents that were published
during the CEQA and NEPA processes are available here.
Documents and letters that were compiled following publication of
the Final EIR/EIS, such as SDG&E Biological Assessment, USFWS
Biological Opinion, BLM Section 106 Programmatic Agreement, and
appeals to the BLM Interior Board of Land Appeals, are also included.
In response to concerns from the Lakeside community, a fact sheet
that summarizes past public notification and consideration of alternative
routes in the community of Lakeside is available here
(posted February 24, 2009).
Data Requests
The EIR/EIS Team submits Data Requests to SDG&E and other entities
when it needs specific information to support EIR/EIS preparation.
These requests are available here at
the time they are issued.
Requests for Technical Information
Related to the Draft EIR/EIS
During the 90-day public comment period on the Draft EIR/EIS, various
parties submitted requests for technical information related to
that document. The information provided has available here.
For Additional Information
To request additional information or to be added to the mailing
list, please contact us by email, fax, or phone, as follows:
The CPUC's Project Manager is:
Billie Blanchard, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-2068
Fax (415) 703-2200
Email: bcb@cpuc.ca.gov
|