Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of the
proposed Sunrise Powerlink Transmission Line Project. Applications
for this project were submitted to the CPUC on December 14,
2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). This site
provides access to public documents and information relevant to
the CEQA and National Environmental Policy Act (NEPA) review processes.
Background
SDG&E has filed an application with the CPUC to construct the
Sunrise Powerlink Project (SRPL). The CPUC is the CEQA lead agency
and the U.S. Bureau of Land Management (BLM) is the lead agency
under NEPA. This project was approved by the California Independent
System Operator on August 3, 2006. The Proponent's Environmental
Assessment was filed with the CPUC on August 4, 2006 and is
available on SDG&E's
project website.
The CPUC maintains other webpages for documents related to its
proceeding on the SRPL, where it makes available documents filed
by parties to that proceeding. The two webpages for Applications
A.06-0-8010
and A.05-12-014
list documents and rulings filed in the proceedings. The CPUC also
maintains a page of general
information on the SRPL project.
The SRPL Project, as proposed by SDG&E, includes a new, approximately
90-mile 500 kV line from Imperial Valley Substation (in Imperial
County, near the City of El Centro) to a new Central East Substation
(in central San Diego County, south of the intersection of County
Highways S-22 and S-2). The 500 kV portion
would approximately follow the eastern boundary of BLM lands west
of El Centro and SR 78, and would pass through Anza-Borrego
Desert State Park.
The SRPL Project also proposes approximately 60 miles of 230 kV transmission
lines from the new Central East Substation to SDG&E's existing
Peñasquitos Substation (in the City of San Diego). SDG&E
proposes to construct two segments underground (one segment south
of Ramona and another in the community of Ranchos Peñasquitos,
San Diego). Figure 1 shows
an overview of the proposed project route.
Data Requests
The EIR/EIS Team will submit Data Requests to SDG&E when it
needs specific information to support EIR/EIS preparation. These
requests will be made available here at the time they are issued.
Data requests submitted to SDG&E to date are provided below.
Responses to these data requests can be found at SDG&E's
website.
Data Request No. 1 (September 27,
2006)
Data Request No. 2 (November 15,
2006)
Data Request No. 3 (November 21,
2006)
Public Scoping
Part 1 of Scoping. On August 31, 2006, the BLM published
its Notice of Intent to prepare an
Environmental Impact Statement in the Federal Register (Volume 71,
No. 169, page 51848). On September 15, 2006, the CPUC
issued a Notice of Preparation/Notice
of Public Scoping Meetings for an Environmental Impact Report/Environmental
Impact Statement. In early October 2006, the CPUC and BLM held a
series of seven public scoping meetings in Imperial and San Diego
Counties to take public comment on the scope and content of the
environmental document. The scoping comment period ended on October 20,
2006.
A Scoping Report has been prepared
and was sent to all repositories on November 29, 2006; see
the list of available documents below. The Scoping Report includes
a copy of every letter submitted, as well as transcripts of the
public scoping meetings and summaries of issues raised during scoping.
Part 2 of Scoping. Additional public meetings will be held
in early 2007 to obtain public comment on alternatives. Notices
of those meetings and the timeframes during which comments on alternatives
will be accepted will be posted here and mailed to all those on
the NEPA/CEQA mailing list. A second part of the Scoping Report
will be prepared to summarize all comments received (including oral
comments made at the Scoping Meetings).
Documents Available
The following documents are available
at 26 libraries and offices in the
project area.
SDG&E's
Application and Proponent's Environmental Assessment (August 4,
2006).
Notice of Intent
(August 31, 2006)
Notice of Preparation
(NOP) (September 15, 2006)
NOP Figure 1.
Proposed Project Overview
NOP Figure 2. Imperial Valley
Link
NOP Figure 3. Anza-Borrego
Link
NOP Figure 4A. Central Link
NOP Figure 4B. Proposed
Central East Substation
NOP Figure 5A. Inland Valley
Link
NOP Figure 5B. Detail of
Ramona Area
NOP Figure 6A. Coastal Link
NOP Figure 6B. Rancho Peñasquitos
Detail
NOP Figure 7. SDG&E Alternatives
Fully Evaluated and Carried Forward in PEA
NOP Figure 8. SDG&E Alternatives
Considered and Eliminated
Scoping Report, Part 1
(November 29, 2006)
For Additional Information
To request additional information or to be added to the mailing
list, please contact us by email, fax, or phone, as follows:
The CPUC's Project Manager is:
Billie Blanchard, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-2068
Fax (415) 703-2200
Email: bcb@cpuc.ca.gov
|