Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of the
proposed Sunrise Powerlink Transmission Line Project. Applications
for this project were submitted to the CPUC on December 14,
2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). This site
provides access to public documents and information relevant to
the CEQA and National Environmental Policy Act (NEPA) review processes.
Background
SDG&E has filed an application with the CPUC to construct the
Sunrise Powerlink Project (SRPL). The CPUC is the CEQA lead agency
and the U.S. Bureau of Land Management (BLM) is the lead agency
under NEPA. This project was approved by the California Independent
System Operator on August 3, 2006. The Proponent's Environmental
Assessment was filed with the CPUC on August 4, 2006 and is
available on SDG&E's
project website.
The CPUC maintains other web pages for documents related to its
proceeding on the SRPL, where it makes available documents filed
by parties to that proceeding. The two web pages for Applications
A.06-0-8010
and A.05-12-014
list documents and rulings filed in the proceedings. The CPUC also
maintains a page of general
information on the SRPL project.
The SRPL Project, as proposed by SDG&E, includes a new, approximately
90-mile, 500 kV line from Imperial Valley Substation (in Imperial
County, near the City of El Centro) to a new Central East Substation
(in central San Diego County, south of the intersection of County
Highways S22 and S2). The 500 kV portion
would approximately follow the eastern boundary of BLM lands west
of El Centro and SR 78, and would pass through Anza-Borrego
Desert State Park.
The SRPL Project also proposes approximately 60 miles of 230 kV transmission
lines from the new Central East Substation to SDG&E's existing
Peñasquitos Substation (in the City of San Diego). SDG&E
proposes to construct two segments underground (one segment south
of Ramona and another in the community of Ranchos Peñasquitos,
San Diego). Figure 1 shows
an overview of the proposed project route.
Second Round of Scoping
on Alternatives
The CPUC and BLM held public meetings from February 5 through February 9,
2007 in order to hear input on alternatives to the Sunrise Powerlink
Project. February 24 was the end of the comment period, and
a second Scoping Report is now being prepared.
September/October 2006 Scoping
On August 31, 2006, the BLM published its Notice
of Intent to prepare an Environmental Impact Statement in the
Federal Register (Volume 71, No. 169, page 51848). On
September 15, 2006, the CPUC issued a Notice
of Preparation/Notice of Public Scoping Meetings for an Environmental
Impact Report/Environmental Impact Statement. In early October 2006,
the CPUC and BLM held a series of seven public scoping meetings
in Imperial and San Diego Counties to take public comment on the
scope and content of the environmental document. The scoping comment
period ended on October 20, 2006.
A Scoping Report (Part 1) was
prepared and was sent to all repositories on November 29,
2006; see the list of available documents below. The Scoping Report
includes a copy of every letter submitted, as well as transcripts
of the public scoping meetings and summaries of issues raised during
scoping.
A second Scoping Report is now being prepared, summarizing all
comments received (including oral comments made at the Public Meetings
on Alternatives). When completed in late March 2007, this report
will be posted on this website and copies will be placed in local
document repository sites.
Documents Available
The following documents are available
at 28 libraries and offices in the
project area.
SDG&E's
Application and Proponent's Environmental Assessment (August 4,
2006).
Notice of Intent
(August 31, 2006)
Notice of Preparation
(NOP) (September 15, 2006)
Figure 1.
Proposed Project Overview
Figure 2. Imperial Valley
Link
Figure 3. Anza-Borrego Link
Figure 4A. Central Link
Figure 4B. Proposed Central
East Substation
Figure 5A. Inland Valley
Link
Figure 5B. Detail of Ramona
Area
Figure 6A. Coastal Link
Figure 6B. Rancho Peñasquitos
Detail
Figure 7. SDG&E Alternatives
Fully Evaluated and Carried Forward in PEA
Figure 8. SDG&E Alternatives
Considered and Eliminated
Scoping Report, Part 1
(November 29, 2006)
Notice of Second
Round of Scoping Meetings on Alternatives to the Proposed Sunrise
Powerlink Project
Figure 1.
Sunrise Powerlink Project Overview
Figure 2. Imperial Valley
Link Alternatives
Figure 3. Anza-Borrego Link
Alternatives
Figure 4. Central Link Alternatives
Figure 5. Inland Valley Link
Alternatives
Figure 6. Coastal Link Alternatives
Retained
Figure 7. Coastal Link Alternatives
Eliminated
Figure 8. Southwest Powerlink
Alternatives
Figure 9. Non-Wires Alternatives
Figure 10. System Alternatives
Data Requests
The EIR/EIS Team will submit Data Requests to SDG&E when it
needs specific information to support EIR/EIS preparation. These
requests will be made available here at the time they are issued.
Data requests submitted to SDG&E to date are provided below.
Responses to these data requests can be found at SDG&E's
website.
Data Request No. 1 (September
27, 2006)
Data Request No. 2 (November 15,
2006)
Data Request No. 3 (November 21,
2006)
Data Request No. 4 (December 6,
2006)
Data Request No. 5 (January 8,
2007)
Data Request No. 6 (January 26,
2007)
Data Request No. 7 (February 1,
2007)
For Additional Information
To request additional information or to be added to the mailing
list, please contact us by email, fax, or phone, as follows:
The CPUC's Project Manager is:
Billie Blanchard, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-2068
Fax (415) 703-2200
Email: bcb@cpuc.ca.gov
|