Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of the
proposed Sunrise Powerlink Transmission Line Project. Applications
for this project were submitted to the CPUC on December 14,
2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). The Proponent's
Environmental Assessment was filed with the CPUC on August 4,
2006 and is available on SDG&E's
project website. This project was approved by the California
Independent System Operator on August 3, 2006. This site provides
access to public documents and information relevant to the CEQA
and National Environmental Policy Act (NEPA) review processes. The
CPUC voted on December 18, 2008 to approve the Final Environmentally
Superior Southern Route (see Decision D.08-12-058)
and a Notice of Determination was
submitted to the State Clearinghouse. The BLM issued a Record
of Decision approving the same route on January 20, 2009.
Construction Progress and Mitigation
Monitoring
Construction is scheduled to begin in March 2010, with the majority
of construction expected to start in June 2010 once the CPUC issues
Notices to Proceed for each segment. Issuance of Notices to Proceed
will be contingent upon SDG&E compliance with pre-construction
requirements as specified by the approved mitigation measures. SDG&E
is constructing the Sunrise Powerlink Project in 25 segments, as
follows:
Segment |
Description |
Type |
Status |
Segment 1 |
Imperial Valley Substation |
Substation Upgrades |
Not started |
Segment 2 |
Imperial Valley Substation to Pyramid Mining
(MP0 to MP19.2) |
500 kV Overhead |
Not started |
Segment 3 |
Pyramid Mining to Mountain Springs Grade (MP19.2
to MP23.2) |
500 kV Overhead |
Not started |
Segment 4 |
Mountain Springs Grade to Jade (MP23.2 to
MP30.3) |
500 kV Overhead |
Not started |
Segment 5 |
Jade to I-8 (McCain Valley) (MP30.3 to MP39.7)
|
500 kV Overhead |
Not started |
Segment 6 |
I-8 (McCain Valley) to USFS (MP39.7 to MP52.5)
|
500 kV Overhead |
Not started |
Segment 7 |
USFS East (MP52.5 to MP61.3) |
500 kV Overhead |
Not started |
Segment 8 |
USFS East to Cameron Substation (MP61.3 to
MP65.4) |
500 kV Overhead |
Not started |
Segment 9 |
MP65.4 to MP70.9 |
500 kV Overhead |
Not started |
Segment 10 |
MP70.9 to MP74.8 |
500 kV Overhead |
Not started |
Segment 11 |
MP74.8 to MP77.6 |
500 kV Overhead |
Not started |
Segment 12 |
MP77.6 to MP90.0 |
500 kV Overhead |
Not started |
Segment 13 |
Suncrest Substation (Modified Route D Substation) |
New 500/230 kV Substation |
Not started |
Segment 14 |
Suncrest Substation to Alpine Boulevard (MP90.0
to MP92.8) |
230 kV Overhead |
Not started |
Segment 15 |
Alpine Boulevard Underground (MP92.8 to MP99.0)
|
230 kV Underground |
Not started |
Segment 16 |
Peutz Valley to El Monte Valley (MP99.0 to
MP105.5) |
230 kV Overhead |
Not started |
Segment 17 |
El Monte Valley to Highway 67 (MP105.5 to
MP112.7) |
230 kV Overhead |
Not started |
Segment 18 |
Highway 67 to Sycamore Canyon Substation (MP112.7
to MP118.1) |
230 kV Overhead |
Not started |
Segment 19 |
Sycamore Canyon Substation |
Substation Upgrades
| Not started
|
Segment 20 |
Sycamore to Elliot 69 kV Reconductor |
69 kV Reconductoring |
Not started |
Segment 21 |
Sycamore to Scripps 69 kV Reconductor |
69 kV Reconductoring |
Not started |
Segment 22 |
Sycamore to Pomerado 69 kV Reconductor |
69 kV Reconductoring |
Not started |
Segment 23 |
South Bay Substation Upgrades |
Substation Upgrades |
Not started |
Segment 24 |
Encina Substation Upgrades |
Substation Upgrades |
Not started |
Segment 25 |
San Luis Rey Substation Upgrades |
Substation Upgrades |
Not started |
The CPUC in conjunction with SDG&E, BLM, USFS and other Responsible
Agencies, drafted a Mitigation Monitoring Compliance and Reporting
Program (MMCRP) to ensure compliance with mitigation measures approved
in the Final EIR/EIS, as well as with the terms and conditions associated
with the BLM Right of Way. Although changes may be made to the document
as construction progresses, a current final version of the MMCRP
document and attachments, including a map
of the approved route with segments, is found here.
A CPUC Environmental Monitor will be monitoring construction activities
to ensure that they are conducted in accordance with the approved
mitigation measures and permit conditions. Once construction begins,
this site will hold all weekly reports documenting this monitoring
activity. Reports on construction status and activities are posted
here. Other monitoring compliance reports,
permit applications, and documents are available in their final
form here.
Final EIR/EIS
The Final EIR/EIS was released to the public on October 13,
2008. The Final EIR/EIS is available here
and is also available at numerous area libraries
and government offices. Copies of the Executive Summary of the
Final EIR/EIS along with a DVD of the complete document may be requested.
The CPUC and BLM also have a limited number of copies of the complete
four-volume Final EIR/EIS document available to the public. Requests
for documents should be made to (866) 711-3106 (phone or fax) or
via email to sunrise@aspeneg.com.
The Notice of Availability provides
further information on the approval processes for the CPUC and the
BLM. Pursuant to NEPA requirements, the Final EIR/EIS and Proposed
Land Use Plan Amendment will be available for review for 30 calendar
days from the date the Environmental Protection Agency (EPA) publishes
the Notice of Availability (NOA) in the Federal Register, which
is expected to occur on October 17, 2008. The review period
would end on November 15, 2008.
Copies of the Executive Summary of the Final EIR/EIS along with
a DVD of the complete document may be requested. The CPUC and BLM
also have a limited number of copies of the complete four-volume
Final EIR/EIS document available to the public. Requests for documents
should be made to (866) 711-3106 (phone or fax) or via email to
sunrise@aspeneg.com.
Draft EIR/EIS
The CPUC and BLM published the Draft EIR/EIS in January 2008. Please
note that the Final EIR/EIS (described above) includes the entire
text of the Draft EIR/EIS, modified where necessary in response
to comments on the Draft EIR/EIS. The original text of the Draft
EIR/EIS document is available here.
EIR/EIS Alternatives
Throughout 2007, the CPUC and BLM gathered information on alternatives
to the proposed Sunrise Powerlink Project through an extensive public
involvement process. Information and documents from that process
are available here.
Documents Available
In addition to the EIR/EIS, other documents that were published
during the CEQA and NEPA processes are available here.
Documents and letters that were compiled following publication of
the Final EIR/EIS, such as SDG&E Biological Assessment, USFWS
Biological Opinion, BLM Section 106 Programmatic Agreement, and
appeals to the BLM Interior Board of Land Appeals, are also included.
In response to concerns from the Lakeside community, a fact sheet
that summarizes past public notification and consideration of alternative
routes in the community of Lakeside is available here
(posted February 24, 2009). A similar fact sheet on public
notification was prepared for the Town of Alpine in January 2010
and is available here.
Data Requests
The EIR/EIS Team submits Data Requests to SDG&E and other entities
when it needs specific information to support EIR/EIS preparation.
These requests are available here at
the time they are issued.
Requests for Technical Information
Related to the Draft EIR/EIS
During the 90-day public comment period on the Draft EIR/EIS, various
parties submitted requests for technical information related to
that document. The information provided has available here.
For Additional Information
To request additional information or to be added to the mailing
list, please contact us by email, fax, or phone, as follows:
The CPUC's Project Manager is:
Billie Blanchard, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-2068
Fax (415) 703-2200
Email: bcb@cpuc.ca.gov
|