STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

San Diego Gas & Electric Company's Sunrise Powerlink Project

(Applications A.05-12-014 and A.06-08-010)

Welcome to the California Public Utilities Commission (CPUC) website for the California Environmental Quality Act (CEQA) review of the proposed Sunrise Powerlink Transmission Line Project. Applications for this project were submitted to the CPUC on December 14, 2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). This site provides access to public documents and information relevant to the CEQA and National Environmental Policy Act (NEPA) review processes.

Background

SDG&E has filed an application with the CPUC to construct the Sunrise Powerlink Project (SRPL). The CPUC is the CEQA lead agency and the U.S. Bureau of Land Management (BLM) is the lead agency under NEPA. The CPUC and BLM are preparing an Environmental Impact Report (EIR, under CEQA) and an Environmental Impact Statement (EIS, under NEPA), which will be published as a single joint document, an EIR/EIS.

This project was approved by the California Independent System Operator on August 3, 2006. The Proponent's Environmental Assessment was filed with the CPUC on August 4, 2006 and is available on SDG&E's project website.

The CPUC maintains other web pages for documents related to its proceeding on the SRPL, where it makes available documents filed by parties to that proceeding. The web page for Application A.06-08-010 incorporates the earlier filing, and lists documents and rulings filed in the proceedings. The CPUC also maintains a page of general information on the SRPL project.

The SRPL Project, as proposed by SDG&E, includes a new, approximately 90-mile, 500 kV line from Imperial Valley Substation (in Imperial County, near the City of El Centro) to a new Central East Substation (in central San Diego County, south of the intersection of County Highways S22 and S2). The 500 kV portion would approximately follow the eastern boundary of BLM lands west of El Centro and SR 78, and would pass through Anza-Borrego Desert State Park.

The SRPL Project also proposes approximately 60 miles of 230 kV transmission lines from the new Central East Substation to SDG&E's existing Peñasquitos Substation (in the City of San Diego). SDG&E proposes to construct two segments underground (one segment south of Ramona and another in the community of Ranchos Peñasquitos, San Diego). Figure 1 shows an overview of the proposed project route.

Draft EIR/EIS

The Draft EIR/EIS was released to the public on January 3, 2008. It is available here and is also available for review at numerous area libraries and government offices.

Copies of the Executive Summary of the Draft EIR/EIS along with a DVD of the complete document may be requested. The CPUC and BLM also have a limited number of copies of the complete six-volume Draft EIR/EIS document available to the public. Requests for documents should be made to (866) 711-3106 (phone or fax) or via e-mail to sunrise@aspeneg.com.

Resumen en Español. Un resumen del borrador Informe de Impacto Ambiental/Declaración de Impacto Ambiental en español está disponible aquí.

Submitting Comments on the Draft EIR/EIS. Written comments on the Draft EIR/EIS must be postmarked or received by fax or e-mail no later than April 11, 2008. Please be sure to include your name, address, and telephone number. Written comments on the Draft EIR/EIS should be sent to:

CPUC/BLM
c/o Aspen Environmental Group
235 Montgomery Street, Suite 935
San Francisco, CA 94104
Fax: (866) 711-3106
Email: sunrise@aspeneg.com

Informational Workshops. The CPUC and BLM held 9 informational workshops during the week of January 28, 2008. These informal workshops provided an opportunity to speak with the specialists who wrote the Draft EIR/EIS and ask questions. While written comments could be submitted during these workshops, there were no facilities to record oral comments.

Public Participation Hearings. The Public Participation Hearings will be held on the dates listed in the table below to receive oral and written comments from interested parties. CPUC Administrative Law Judge Steven Weissman will conduct the Public Participation Hearings, and receive comments on the Draft EIR/EIS and any other issues of concern related to the SDG&E CPCN application. These oral comments will be recorded and entered into the public record. Transcripts of these hearings are available at the links below:

San Diego, 2/25/08
Pine Valley, 2/25/08
Borrego Springs, 2/26/08
Ramona, 2/26/08
Julian, 2/27/08

EIR/EIS Alternatives

Throughout 2007, the CPUC and BLM gathered information on alternatives to the proposed Sunrise Powerlink Project through an extensive public involvement process. Information and documents from that process are available here.

Documents Available

In addition to the EIR/EIS, other documents that were published during the CEQA and NEPA processes are available here.

Data Requests

The EIR/EIS Team submits Data Requests to SDG&E and other entities when it needs specific information to support EIR/EIS preparation. These requests are available here at the time they are issued.

Requests for Technical Information Related to the Draft EIR/EIS

During the 90-day public comment period on the Draft EIR/EIS, various parties submitted requests for technical information related to that document. The information provided has available here.

For Additional Information

To request additional information or to be added to the mailing list, please contact us by email, fax, or phone, as follows:

Project email: sunrise@aspeneg.com
Project fax and voicemail: (866) 711-3106

The CPUC's Project Manager is:

Billie Blanchard, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-2068
Fax (415) 703-2200
Email: bcb@cpuc.ca.gov
   
This page contains tables and is best viewed with Firefox or Internet Explorer. Please report any problems to the Energy Division web coordinator.
   
 
Project Home Page - CPUC Environmental Information - CPUC Home