2.1 Project Overview
-
2.2 Existing Regional Electric System in the
Tri-Valley
Area
-
2.3 Project Purpose and Need
-
2.4 Description of the Project
-
2.5 Project Facilities Detail
-
2.6 Project Construction
-
2.7 Permit Requirements
-
2.8 Public Information Program
-
2.9 Intended Uses of a CPUC EIR
-
2.10 Project Schedule
-
-
3.1 Introduction
-
3.2 Decision Analysis Process
-
3.3 Development of Alternatives and Selection of
the
Preferred Project
-
3.4 No Project Alternative
-
3.5 Alternative 1
-
3.6 Alternative 2
-
3.7 Alternative 3
-
3.8 Alternative 4
-
-
4.1 CEQA Initial Study Checklist
-
4.2 Impact Assessment Summary Checklist
-
-
5.1 Introduction
-
5.2 Existing Conditions
-
5.3 Potential Impacts
-
5.4 Mitigation Measures
-
5.5 References
-
-
6.1 Introduction
-
6.2 Existing Conditions
-
6.3 Potential Impacts
-
6.4 Mitigation Measures
-
6.5 References
-
-
7.1 Introduction
-
7.2 Existing Conditions
-
7.3 Potential Impacts
-
7.4 Mitigation Measures
-
7.5 References
-
-
8.1 Introduction
-
8.2 Existing Conditions
-
8.3 Potential Impacts
-
8.4 Mitigation Measures
-
8.5 References
-
-
9.1 Introduction
-
9.2 Existing Conditions
-
9.3 Potential Impacts
-
9.4 Mitigation Measures
-
9.5 References
-
-
10.1 Introduction
-
10.2 Existing Conditions
-
10.3 Potential Impacts
-
10.4 Mitigation Measures
-
10.5 References
-
-
11.1 Introduction
-
11.2 Existing Conditions
-
11.3 Potential Impacts
-
11.4 Mitigation Measures
-
11.5 References
-
-
12.1 Introduction
-
12.2 Existing Conditions
-
12.3 Potential Impacts
-
12.4 Mitigation Measures
-
12.5 References
-
-
13.1 Introduction
-
13.2 Existing Conditions
-
13.3 Potential Impacts
-
13.4 Mitigation Measures
-
13.5 References
-
-
14.1 Introduction
-
14.2 Existing Conditions
-
14.3 Potential Impacts
-
14.4 Mitigation Measures
-
14.5 References
-
-
15.1 Introduction
-
15.2 Existing Conditions
-
15.3 Potential Impacts
-
15.4 Mitigation Measures
-
15.5 References
-
-
16.1 Introduction
-
16.2 Existing Conditions
-
16.3 Potential Impacts
-
16.4 Mitigation Measures
-
16.5 References
-
-
17.1 Introduction
-
17.2 Corona
-
17.3 Induced Currents
-
17.4 Computer Interference
-
17.5 Mitigation Measures
-
17.6 References
-
-
18.1 Introduction
-
18.2 Growth Inducing
Impacts
-
18.3 Cumulative Impacts
-
-
19.1 Introduction
-
19.2 Mitigation
Monitoring
-
19.3 Mitigation
Enforcement
-
- Appendices
- A. PG&E
Guide for Planning Area Distribution Facilities
- B. Anticipated
Residential and Commercial Development
(Units per Year)
- C. Public
Information Program
- D. Tri-Valley
Local Integrated Resource Plan Summary
- E. Example
Native American Burial Protection Plan
- G. PEA Report
Preparation
- H. Glossary
-
- List of
Figures
Not Available Online
-
- List of
Tables
Not Available Online