STATE OF CALIFORNIA
|
|
Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of the proposed
construction of Southern California Edison's (SCE) Viejo System Project.
An application for this project was submitted to the CPUC on March 21,
2003 The purpose of the Viejo System Project is to improve reliability and
meet projected electrical load requirements in the rapidly urbanizing
south Orange County area. SCE proposes to construct a 220/66/12 kilovolt
(kV) substation (Viejo Substation) on a 12.5-acre site located in the
City of Lake Forest and a 3.1-mile 66 kV subtransmission line along the
corridor between the proposed Viejo Substation and the existing Chiquita
Substation located in the City of Mission Viejo. In addition, the project
would include the replacement of 20 double-circuit tubular steel poles
with 13 In accordance with Public Utilities Code Section 1001, SCE is seeking
approval of a Permit to Construct from the CPUC, identifying the selected
route based on environmental review of the proposed route and alternatives
and authorizing construction of the project.
The proposed route can be viewed at the two links following:
The PEA may be viewed online here. The CPUC intends to adopt a Mitigated Negative Declaration (MND) for
SCE's proposed Viejo System Project, and has prepared a Proposed MND and
supporting Initial Study (IS) describing the proposed project and its
potential environmental effects. Based on the IS, it has been determined
that the proposed project, as modified with mitigation, would not have
any significant effects on the environment, as defined by the California
Environmental Quality Act (CEQA). The complete MND/IS and related documents
prepared by SCE are available for public review for thirty (30) days,
from March 10 through April 9, at the repositories listed below,
during the hours shown. The MND/IS may also be viewed online here. The CPUC will hold, consecutively, a Prehearing Conference before the
Administrative Law Judge and a Public Participation Hearing, as shown
below: The CPUC, through its Environmental
Review Team, is managing the environmental
review of the project. The CPUC's Project Manager in the Energy Division's
CEQA unit is: Michael Rosauer, CPUC Project Manager To request additional information, please contact us via Project e-mail: viejosystem@aspeneg.com The State of California Department of Health Services and the Public
Health Institute have prepared a short fact sheet on electric and magnetic
field (EMF) safety issues as part of the California Electric and Magnetic
Fields Program. This Short
Factsheet on EMF answers some common questions about the safety of
powerlines and appliances. |
|||||||||||||