|
Welcome to the California Public Utilities Commission (CPUC) website for San Diego Gas & Electric's (SDG&E) Vine Substation Project. This website provides information on the status of the CPUC's environmental review, permitting, and construction monitoring of the project, as Lead Agency, under the California Environmental Quality Act (CEQA). SDG&E submitted an application (A.14-05-021) for a Permit to Construct Electrical Facilities with Voltages between 50 kV and 200 kV, and Proponent's Environmental Assessment (PEA), to the CPUC on May 27, 2014. A Supplemental PEA was filed February 25, 2015, which revised the proposed alignment of the 12-kV distribution line. A Final Initial Study/Mitigated Negative Declaration (IS/MND) was prepared by CPUC for the Project in accordance with CEQA. This website provides access to public documents and information relevant to the CEQA review, permitting, and construction of the Vine Substation Project. PROJECT STATUS The Final IS/MND was adopted and the Project was approved by the CPUC on May 13, 2016 in Decision D.16-05-008. In accordance with CEQA, a Mitigation Monitoring, Compliance, and Reporting Plan (MMCRP) was prepared to ensure compliance with the mitigation measures approved in the Final IS/MND and is available here (35.6MB). SDG&E plans to start construction of the Vine Substation Project in June 2016. Pre-Construction Compliance A Notice to Proceed (NTP) was issued by CPUC for the entirety of the project on June 8, 2016 and is available here. Issuance of the NTP was contingent upon SDG&E's compliance with pre-construction requirements as specified by the approved mitigation measures and responsible agency permitting requirements. Other responsible agency permits required for construction are listed in the Final IS/MND, Section B.1.14 (see below). Major compliance plans and surveys required prior to construction include the following:
Construction Monitoring & Minor Project Change Review CPUC Environmental Monitors will monitor construction activities to ensure that construction is being conducted in accordance with the approved mitigation measures and permit conditions. Monitoring reports documenting construction and monitoring activities are available here. As final engineering is completed or as construction necessitates, Minor Project Changes (MPCs) could be submitted for the Project. Each of these requests will be reviewed by CPUC to ensure that no new impacts or increase in impact severity would result from the requested change. All MPCs will be posted on this site. BACKGROUND The Vine Substation Project is proposed to be located within the southwestern portion of the City of San Diego, California, near San Diego International Airport. A summary of SDG&E's proposed Project is provided below:
Application (A.14-05-021)
Proponent's
Environmental Assessment Proponent's
Environmental Assessment Supplement Environmental Review Process SDG&E’s Application was deemed complete by the CPUC on May 4, 2015. The CPUC determined that a Mitigated Negative Declaration (MND) will be the appropriate document to be prepared for this project. Final Mitigated Negative Declaration On September 21, 2015, the CPUC released a Notice of Intent to Adopt an MND for the Vine Substation Project, showing that the Proposed Project, as mitigated, would not have any significant effects on the environment. The Draft MND and supporting Initial Study (IS/MND) underwent a public review period from September 21, 2015, to October 20, 2015. Following the close of the review period (October 20, 2015), SDG&E informed the CPUC of a potential conflict with a planned sewer pipeline project. Therefore, SDG&E proposed an approximately 1,030-foot realignment option which would instead reroute the 12-kV line along India Street between West Redwood Street and West Palm Street, and then along West Palm Street to Columbia Street, thereby avoiding the segment of Columbia Street between West Redwood Street and West Palm Street. The IS/MND was revised to address this alignment option, as well as comments received on the original Draft IS/MND. The Revised IS/MND underwent a public review period from December 4, 2015, to January 4, 2016. On January 18, 2016,
the CPUC released a Final IS/MND for the Vine Substation Project, showing
that the Proposed Project, as mitigated, would not have any significant
effects on the environment. The Final IS/MND details the Proposed Project,
evaluates and describes its potential environmental impacts, identifies
those impacts that could be significant, and presents mitigation measures
to avoid or minimize these impacts. The Final IS/MND can be viewed here.
For Additional Information
|