STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

Pacific Gas & Electric Company's Proposed Windsor Substation Project

(Application A.10-04-024, filed April 21, 2010)


Files ilnked on this page are in Portable Document Format (PDF). To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your PC. Note: For best results in displaying the largest files (see sizes shown in parentheses below for files larger than 5 MB), right-click the file's link, click "Save Target As" to download the file to a folder on your hard drive, then browse to that folder and double-click the downloaded file to open it in Acrobat.

Welcome to the California Public Utilities Commission (CPUC) website for Pacific Gas and Electric's (PG&E's) proposed Windsor Substation Project. An application for this project was submitted to the CPUC on April 21, 2010 (A.10-04-024). The project was reviewed by CPUC in accordance with the California Environmental Quality Act (CEQA) and a Mitigated Negative Declaration (MND) was prepared.

This site provides access to public documents and information relevant to the permitting, CEQA review, and construction of the Windsor Substation Project.

PROJECT STATUS

The Final MND was adopted by the CPUC on April 3, 2014 in Decision D.14-03-031. In accordance with CEQA, a Mitigation Monitoring, Compliance, and Reporting Plan (MMCRP) was prepared to ensure compliance with the mitigation measures approved in the MND. The MMCRP is available here (6.4MB). PG&E plans to start construction of the Windsor Substation Project in Summer 2016.

Pre-construction Compliance

Notices to Proceed (NTPs) will be issued by CPUC by subsection of the project as requested by PG&E. As NTPs are issued for the Windsor Substation Project they will be posted on this web site. Issuance of NTPs will be contingent upon PG&E's compliance with pre-construction requirements as specified by the approved mitigation measures and responsible agency permitting requirements.

Other responsible agency permits required for construction, and their amendments, are listed in the MMCRP (see above). Major compliance plans requiring CPUC and/or permit agency review and approval included the following:

  • Sensitive Biological Habitat Survey Reports
  • Bird Nesting Survey Reports
  • Special-status Bat Survey Reports
  • Restoration Plans
  • Storm Water Pollution Prevention Plans (SWPPPs)
  • Construction Site Monitoring Program (CSMP)
  • Spill Prevention Control and Countermeasure Plans (SPCCs)
  • Hazardous Substance Control and Emergency Response Plan
  • Worker Environmental Awareness Program Plans

Construction Monitoring and Minor Project Change Review

CPUC Environmental Monitors will monitor construction activities to ensure that construction is being conducted in accordance with the approved mitigation measures and permit conditions. Monitoring reports documenting construction and monitoring activities will be posted on this website.

As final engineering is completed or as construction necessitates, Minor Project Changes (MPCs) could be submitted for the Project. Each of these requests will be reviewed by CPUC to ensure that no new impacts or increase in impact severity would result from the requested change. All MPCs will be posted on this website.

BACKGROUND

Project Description

The originally proposed Windsor Substation Project site was located on Mitchell Lane in the southern part of the Town of Windsor, Sonoma County, California. Subsequent to its original Application, PG&E amended its Application and submitted a Supplemental PEA for substation sited at a different location. The new site is in the northern part of the Town, on Old Redwood Highway at Herb Road, between Highway 101 and the Northwestern Pacific Railroad (NWPRR) right of way.

Electrical power would enter the substation by tapping the existing Fulton No. 1 60 kV power line that parallels the west side of the NWPRR right of way. Electrical power would leave the substation as 12 kV via distribution feeder lines, which would interconnect with the distribution network. Construction involves the installation of the following components:

  • Construction of a 3-bank 115/12 kilovolt substation on 2.6 acres of a 4.11-acre parcel on Old Redwood Highway at Herb Road in the Town of Windsor, California. The substation would consist of the following at full buildout:

    • Three 115 kV bus structures
    • Six 115 kV circuit breakers
    • Three 115/12 kV power transformers
    • Eighteen 115 kV disconnecting switches
    • Three 12 kV metal-clad switchgear enclosures
    • Twelve 12 kV distribution circuits
    • Three 30 MVA power transformers
    • Connection of the new substation to on the Fulton No. 1 60 kV power line by way of a new tubular steel pole [TSP] replacing an existing wood pole
    • Two 42-foot-high dead-end structures within the substation supporting the 60 kV power line entering and exiting the substation

  • Pole replacement and line work along Old Redwood Highway, Starr Road, Gumview Road, Wilcox Road, Starr Circle, Railroad Avenue and Joni Court.

  • Underground distribution lines connecting the substation to existing and future infrastructure.

  • Rebuilding approximately 1.5 miles of the existing Fulton No. 1 60 kV power line, requiring replacement 39 wooden poles (with 38 wood poles and 1 steel pole) and installation of 2 new wood riser poles.

  • Reconductoring approximately 1.8 miles of existing distribution line with 12 kV double-circuit conductor along Old Redwood Highway, requiring replacement of 44 wooden poles with taller wood poles and installation of 3 additional wood riser poles.

Proponent's Environmental Assessment (PEA)

PG&E filed a PEA with the Application in April 2010. A Supplemental PEA was submitted in May 2011. The PEA provides a starting point for the independent environmental review process conducted by the CPUC. In addition, PG&E's Notice of an Application for a Permit to Construct can be found here.

Environmental Review Process

PG&E's Application and PEA were deemed complete for review by the CPUC on May 20, 2010. However, the PEA was replaced by the Supplemental PEA, submitted in 2011. The CPUC evaluated the substation site and related project elements identified in the Supplemental PEA.

The CPUC determined that an Initial Study/Mitigated Negative Declaration (IS/MND) appeared to be the appropriate CEQA document to prepare for this project. After it was prepared, the Draft IS/MND was published and the public and agencies had an opportunity to comment on the document. Based on the Draft IS/MND, CPUC determined that an EIR was not required.

Draft Initial Study/Mitigated Negative Declaration

On July 15, 2013, the CPUC released a Notice of Intent to Adopt a Mitigated Negative Declaration for the Windsor Substation Project showing that the Proposed Project, as mitigated, would not have any significant effects on the environment. The Draft Mitigated Negative Declaration and Supporting Initial Study (IS/MND) can be viewed here.

The Draft IS/MND underwent a public review period from July 15, 2013 through August 14, 2013.

Final Initial Study/Mitigated Negative Declaration

After the close of the comment period, CPUC prepared a Final Mitigated Negative Declaration for the Windsor Substation Project. The Final IS/MND can be viewed here. The study showed that the Proposed Project, as mitigated, would not have any significant effects on the environment. The Final MND provides details on the Proposed Project, evaluates and describes its potential environmental impacts, identifies those impacts that could be significant, and presents mitigation measures to avoid or minimize these impacts.

Public Information Meeting

The CPUC Energy Division held a public information meeting on August 16, 2010, to describe the then-proposed project, describe the CEQA process, and receive public comments on the proposal. Written comments were submitted at this meeting. Subsequent to the meeting, PG&E identified its alternate site and submitted a supplemental PEA.

For Additional Information

To request additional information, ask a question, or be added to the project mailing list, please contact:

U.S. Mail
or Courier:
Eric Chiang
California Public Utilities Commission
c/o Aspen Environmental Group
235 Montgomery Street, Suite 935
San Francisco, CA 94104-3002
Email: windsorsubstation@aspeneg.com
   

This page contains tables and is best viewed with Firefox or Internet Explorer. Please report any problems to the Energy Division web coordinator.

   
 
Project Home Page - CPUC Environmental Information - CPUC Home