Back to Power Line Replacement Projects Main Page
Welcome to the California Public Utilities Commission (CPUC) Mitigation
Monitoring, Compliance and Reporting Program website for the San Diego Gas &
Electric (SDG&E) Master Special Use Permit (MSUP) and Permit to Construct (PTC)
Power Line Replacement Projects located in and around the Cleveland National
Forest (CNF) in San Diego County, California.
Pursuant to the CPUC approval of the Project, SDG&E is required to implement
the Applicant Proposed Measures (APMs) and mitigation measures identified in the
Final Environmental Impact Report (EIR)/Environmental Impact Statement (EIS) and
the Mitigation Monitoring, Reporting, and Compliance Program (MMRCP). The CPUC,
as a lead agency under CEQA, is responsible for ensuring that the APMs and
mitigation measures, as well as plans reviewed and approved by other agencies,
are implemented throughout the construction phase of the Project. Below are
project documents related to mitigation monitoring that are available for public
review.
Quick Links
Mitigation Monitoring, Compliance and Reporting Program
Notice to Proceed
Environmental
Monitoring Reports
Minor Project Refinements
Request
The program’s goal is to ensure compliance with CPUC’s adopted
mitigation. The CPUC, in conjunction with SDG&E, drafted a Mitigation Monitoring
Compliance and Reporting Program (MMCRP) to ensure compliance with mitigation
measures approved in the Final EIR/EIS. Click on link below to view a complete
copy of the MMCRP.
MMCRP
A NTP is issued contingent upon SDG&E’s compliance with pre-construction
requirements as specified by the approved mitigation measures and responsible
agency permitting requirements. A link to the approved pre-construction
documentation is provided below.
Pre-Construction Documentation
Data Requests
A CPUC Environmental Monitor (EM) is monitoring construction activities
to ensure that they are conducted in accordance with the approved mitigation
measures and permit conditions. Reports documenting construction status and
compliance activities will be provided when available.
Weekly Report #
|
Reporting Period
|
Environmental
Issues/Concerns
|
001
|
September 23-October 2, 2016
|
No
issues/concerns reported.
|
002
|
October 3-October 16, 2016 |
Approved parking areas.
|
003 |
October 17-October 30, 2016 |
No issues/concerns reported. |
004 |
October 31-November 13, 2016 |
No issues/concerns reported. |
005 |
November 14-November 27, 2016 |
No issues/concerns reported. |
006 |
November 28-December 11, 2016 |
Work limits. |
007 |
December 12-December 25, 2016 |
No issues/concerns reported. |
008 |
December 26, 2016 - January 8, 2017 |
No issues/concerns reported. |
009 |
January 9 - January 22, 2017 |
Dewatering system. |
010 |
January 23 - February 5, 2017 |
Waste disposal, Fire equipment. |
011 |
February 6 - February 19, 2017 |
Work limits. |
012 |
February 20 - March 5, 2017 |
Work limits. |
013 |
March 6 - March 19, 2017 |
No issues/concerns reported |
014 |
March 20 - April 2, 2017 |
No issues/concerns reported |
015 |
April 3 - April 16, 2017 |
No issues/concerns reported |
016 |
April 17 - April 30, 2017 |
No issues/concerns reported |
017 |
May 1-May 14, 2017 |
Work Limits |
018 |
May 15-May 28, 2017 |
No issues/concerns reported |
019 |
May 29-June 11, 2017 |
No issues/concerns reported |
020 |
June 12-June 25, 2017 |
No issues/concerns reported |
021 |
June 26-July 9, 2017 |
Work Limits |
022 |
July 10-July 23, 2017 |
No issues/concerns reported |
023 |
July 24-August 6, 2017 |
No issues/concerns reported |
024 |
August 7-August 20, 2017 |
Nest Buffer Encroachment |
025 |
August 21-September 3, 2017 |
No issues/concerns reported |
026 |
September 4-September 17 |
Work Limits |
027 |
September 18-October 2, 2017 |
No issues/concerns reported |
028 |
October 2-October 15, 2017 |
Work Limits |
029 |
October 16-October 29, 2017 |
No issues/concerns reported |
030 |
October 30-November 12, 2017 |
Work Limits |
031 |
November 13-November 26, 2017 |
Work Limits |
032 |
November 27-December 10, 2017 |
No issues/concerns reported |
033 |
December 11-December 24, 2017 |
Work Limits |
034 |
December 25, 2017 – January 7, 2018 |
Work Limits |
035
|
January 8 – January 21, 2018 |
Work Limits |
036 |
January 22 – February 4, 2018 |
No issues/concerns reported |
037 |
February 5 – February 18, 2018 |
Work limits |
038 |
February 19 – March 4, 2018 |
No issues/concerns reported |
039 |
March 5 – March 18, 2018 |
No issues/concerns reported |
040 |
March 19 – April 1, 2018 |
No issues/concerns reported |
041 |
April 2 – April 15, 2018 |
No issues/concerns reported |
042 |
April 16 – April 30, 2018 |
Fire Equipment |
043 |
April 30 – May 13, 2018 |
No issues/concerns reported |
044 |
May 14 – May 27, 2018 |
No issues/concerns reported |
045 |
May 28 – June 10, 2018 |
No issues/concerns reported |
046 |
June 11 – June 24, 2018 |
No issues/concerns reported |
047 |
June 25 – July 8, 2018 |
No issues/concerns reported |
048 |
July 9-July 22, 2018 |
Cultural resources monitoring |
049 |
July 23-August 5, 2018 |
Work Limits, Cultural resources monitoring |
050 |
August 6-August 19, 2018 |
Fire Equipment |
051 |
August 20-September 2, 2018
|
Work Limits, Fire Equipment |
052 |
September 3-September 16, 2018
|
Work Limits |
053 |
September 17-September 30, 2018
|
Trash Management |
054 |
October 1-October 14, 2018
|
Biological Monitoring |
055 |
October 15-October 28, 2018
|
Work Hours |
056 |
October 29-November 11, 2018 |
Work Hours |
057 |
November 12-November 25, 2018 |
No issues/concerns reported |
058 |
November 26-December 9, 2018 |
Work Limits |
059 |
December 10-December 23, 2018 |
Work Limits |
060 |
December 23-January 13, 2019 |
Work Hours |
061 |
January 14-January 27, 2019 |
Work Limits |
062 |
January 28-Feburary 10, 2019 |
Work Limits |
063 |
February 11-February 24, 2019 |
Work Limits |
064 |
February 25-March 10, 2019 |
Work Limits |
065 |
March 11-March 24, 2019 |
Work Limits, Work Hours |
066 |
March 25-April 7, 2019 |
No issues/concerns reported |
067 |
April 8-April 21, 2019 |
Work Hours |
068 |
April 22-May 5, 2019 |
Work Hours |
069 |
May 6-May 19, 2019 |
No issues/concerns reported |
070 |
May 20-June 2, 2018 |
No issues/concerns reported |
071 |
June 3-June 16, 2019 |
Covering work areas |
072 |
June 17, 2019-June 30, 2019 |
No issues/concerns reported |
073 |
July 1-July 14, 2019 |
Cultural Monitoring |
074 |
July 15-July 28, 2019 |
No issues/concerns reported |
075 |
July 29-August 11, 2019 |
Work Limits, Work Hours, Work Activity on USFS during PAL EV |
076 |
August 12-August 25, 2019 |
No issues/concerns reported |
077 |
August 26-September 8, 2019 |
No issues/concerns reported |
078 |
September 9-September 22, 2019 |
Work limits, Work Hours, Authorization from USFS for work during PAL EV, SWPPP |
079 |
September 23-October 6, 2019 |
Work hours |
080 |
October 7-October 20, 2019 |
Work Limits |
081 |
October 21-November 3, 2019 |
No issues/concerns reported |
082 |
November 4-November 17, 2019 |
Work Limits, Excavation Covering, Work Hours |
083 |
November 18-December 1, 2019 |
SWPPP, Work Limits |
084 |
December 2-December 15, 2019 |
Excavation Covering, Work Limits, Fire Tools, Work Hours, SWPPP |
085 |
December 16-December 29, 2019 |
Work Limits, SWPPP |
086 |
December 30, 2019-January 12, 2020 |
SWPPP, Work Limits, Fire Tools |
087 |
January 13-January 26, 2020 |
Work Limits, Cultural Monitoring |
088 |
January 27-February 9, 2020 |
Work Limits, Excavation Covering |
089 |
February 10-February 23, 2020 |
Work Limits, Work Hours |
090 |
February 24-March 8, 2020 |
Work Hours, Work Limits, Trash Management |
091 |
March 9-March 22, 2020 |
Work Hours, Work Limits |
The Commission decision approving the permit to construct authorizes
Energy Division staff to approve requests by SDG&E for minor project
refinements. The decision states that the Energy Division may approve requests
by San Diego Gas & Electric Company for minor project refinements that may be
necessary due to final engineering of the Power Line Replacement Projects so
long as such minor project refinements are located within the geographic
boundary of the study area of the Environmental Impact Report and do not,
without mitigation, result in a new significant impact or a substantial increase
in the severity of a previously identified significant impact based on the
criteria used in the environmental document; conflict with any mitigation
measure or applicable law or policy; or trigger an additional permit
requirement. San Diego Gas & Electric Company shall seek any other project
refinements by a petition to modify this decision.
SDG&E's Minor Project
Refinement Requests will be made available below when submitted to the CPUC.
Minor Project
Refinement #
|
Description
|
MPR Request
|
MPR Approval
|
001
|
Modifications to Merrigan, Japatul Spur and Anderson Staging Yards
|
10/5/16, as revised 10/18/16
|
10/21/16
|
002
|
Modifications to
TL625B and TL629E
|
12/21/16
|
2/10/17
|
003
|
Addition of Water Source for Construction—Wilson Pond Facility
|
01/18/17
|
04/04/17
|
004
|
Use of two new staging and fly yards-TL 682
|
03/20/17
|
05/16/17
|
005
|
Modifications to Circuit (C) 78
|
05/09/17
|
08/15/17
|
006
|
Drainage Structure Installation at Pole Z272867 (TL 625B)
|
06/20/17
|
07/06/17
|
007
|
Use of Love Valley Staging and Fly Yard
|
08/01/17
|
09/25/17
|
008
|
Use of Mendenhall Fly Yard
|
08/14/17
|
09/01/17
|
009
|
Refinements for Phase I and Phase II of TL682
|
10/10/17
|
11/21/17
|
010
|
Request to shift one pole and add an additional workspace
|
10/16/17
|
10/27/17
|
011
|
Modifications to TL6957 (formerly TL625D)
|
1/9/18
|
3/12/18
|
012
|
Addition of the Creekside Ranch Staging and Fly Yard
|
1/22/18
|
2/6/18
|
013
|
Request to shift one pole and add an additional workspace
|
2/7/18
|
2/9/18
|
014
|
Request to begin construction on Phase III of TL682. This request is combined with NTP #13
|
2/15/18
|
4/5/18
|
015
|
Refinements for TL682
|
2/22/18
|
3/14/18
|
016
|
Refinements for TL629E
|
3/29/18
|
4/3/18
|
017
|
Refinements for C157 and addition of Frye Staging and Fly Yard
|
04/12/18
|
6/26/18
|
018
|
Refinements for C449
|
5/29/18
|
8/30/18
|
019
|
Refinements for TL629C and addition of Buckman Springs Fly Yard
|
7/2/18
|
8/30/18
|
020
|
Refinements for C157
|
7/31/18
|
8/29/18
|
021
|
Interset Pole on TL 682
|
8/23/18
|
9/24/18
|
022
|
Refinements for TL 6958
|
10/16/18
|
11/30/18
|
023
|
Expansion of Buckman Springs Fly Yard and request for use of Old Buckman Springs and Rodriguez Staging Yards
|
11/15/18
|
12/4/18
|
024
|
New Construction Only Access Road for C 449 and TL 629C
|
11/26/18
|
12/20/18
|
025
|
Bartlett Staging Yard
|
12/11/18
|
1/22/19
|
026
|
Refinements for TL 629A
|
2/22/19
|
4/19/19
|
027
|
Expansion of Cameron Staging Yard
|
03/01/19, as revised 03/08/19
|
03/12/19
|
028
|
Underground workspaces at three existing pole locations on C 449
|
03/07/19
|
03/12/19
|
029
|
Refinements for C79A
|
03/28/19
|
05/29/19
|
030
|
Modification of navigation access road to Pole P45476
|
03/29/19
|
04/05/19
|
031
|
Refinements to TL 625C
|
4/26/19
|
6/18/19
|
032
|
Refinements to C440 Phase I Overhead
|
5/6/19
|
7/11/19
|
033
|
C 440 Conversion of Staging Yard 2 and 2A to Staging and Fly Yards
|
5/14/19, as revised 6/3/19
|
6/4/19
|
034
|
River Drive Staging Yard
|
05/17/19
|
05/29/19
|
035
|
TL 629A Refinements
|
6/6/19
|
6/18/19
|
036
|
C 79 Paso Picacho Staging Yard
|
6/28/19
|
7/17/19
|
037
|
TL 629A Merrigan Yard Expansion
|
6/28/19
|
7/3/19
|
038
|
TL 629A Refinements
|
7/26/19
|
8/14/19
|
039
|
TL 625C Refinements
|
9/05/19
|
9/19/19
|
040
|
Addition of underground alignment for C 440
|
9/12/19
|
10/10/19
|
041
|
TL 6923 Refinements
|
10/2/19, revised 10/30/19
|
11/22/19
|
042
|
Addition of temporary access/entry/turnaround areas, temporary pole work areas, and footpaths at Poles Z774861, Z774862, Z774863, and Z774864 for TL 269A
|
10/29/19, revised 11/08/19
|
12/9/19
|
043
|
Shift replacement pole Z272393 and add temporary pole work area
|
12/27/19
|
1/9/19
|
044
|
Refinements to TL 626 Conversion South
|
2/10/20
|
Pending
|
045
|
Temporary shoo-fly along TL629A
|
2/21/20
|
3/9/20
|
046
|
Additional anchors and access road modifications along C 440 Phase I
|
3/6/20
|
3/26/20
|
For Additional Information
To request additional information, please contact us by email, phone, or
fax, as follows:
Project email:
CNF_MSUP@dudek.com Project voicemail: (866) 467-4727
The CPUC's project manager is:
Lisa Orsaba, CPUC Project Manager California
Public Utilities Commission 505 Van Ness Avenue San Francisco CA 94102
Tel. (415) 703-1966 Fax (415) 703-2200
The Forest Service Project Manager is:
Brad Aughinbaugh United States Forest Service
Cleveland National Forest 10845 Rancho Bernardo Road, Ste. 200 San Diego,
CA 92127 Tel: 858-674-2912 Fax: (858) 524-0130
Please
report any problems to the Energy
Division web coordinator.
|
|
|