STATE OF CALIFORNIA
|
Welcome to the California Public Utilities Commission (CPUC) website for the environmental review of proposed construction of the San Diego Gas & Electric (SDG&E) Mira Sorrento Distribution Substation Project (proposed project) located in the northwestern portion of the City of San Diego, California. SDG&E submitted an application for this project to the CPUC on October 14, 2011 (Application A.11-10-015 ). The proposed project is subject to review under the California Environmental Quality Act (CEQA). This site provides access to public documents and information relevant to the CEQA review process. BackgroundSDG&E filed an application for a Permit to Construct the Mira Sorrento Distribution Substation Project with CPUC. The CPUC, as lead agency under California law, will prepare a mitigated negative declaration (MND) to comply with CEQA. SDG&E is proposing to construct a new 120-megavolt ampere (MVA), 69-/12-kilovolt (kV) distribution substation with the loop-in of an existing 69 kV electrical transmission line (TL665). The proposed 1.4-acre substation would be situated on a 3.7-acre parcel with a 10-foot-high screening wall that would enclose the substation area. The proposed substation at full buildout is planned to have 120 MVA capacity with four 30 MVA transformer banks; four 69 kV tie lines; sixteen 12 kV circuits; four 12 kV capacitors and four bays of standard steel rack approximately 30 feet tall of 69 kV bus and 69 kV transformer; and one 40-foot-long x 20-foot-wide masonry block control shelter. In addition, on the northeast side of the substation site, two tiered retaining walls would be constructed that would be approximately 32 and 20 feet in height. Access to the substation will be via two 30-foot-wide driveways from Mira Sorrento Place to the west of the substation. Power would be supplied to the new substation by an existing SDG&E 69 kV transmission line (TL665) that would require installation of underground transmission facilities into the substation site. Initially, six 12 kV underground distribution circuits would be installed and would be routed to Mira Sorrento Place to tie into the existing underground system serving the area. Project construction is expected to require approximately 18 to 24 months to complete. SDG&E is proposing to construct the Mira Sorrento Distribution Substation in the vicinity of Vista Sorrento Parkway and Mira Mesa Boulevard in the Sorrento Mesa area within the Mira Mesa Community Plan area of the City of San Diego, California. The proposed project site is situated approximately 9 miles north of Downtown San Diego (see Regional Map and Project Vicinity Map). Application and Proponent's Environmental Assessment (PEA)The application and PEA for the Mira Sorrento Distribution Substation Project were filed with the CPUC on October 14, 2011.
Other Documents AvailableThe CPUC sent SDG&E a completeness review letter on November 16, 2011, that requested additional information from SDG&E to satisfy CPUC’s Information and Criteria List. Click the following links to view the letter and SDG&E’s response.
The application was deemed complete on February 3, 2012.
Data RequestsThe CPUC submitted data requests to the project applicant for specific information during preparation of the environmental document. Click the following links to view the data request(s) and SDG&E’s response(s). Data Request No. 1 (February 3, 2012) and SDG&E Response (February 21, 2012) Environmental DocumentsThe project's environmental documents will be posted here when available. Commission DecisionThe commission's decision will be posted here when available. Construction Progress and Mitigation MonitoringReports issued by the CPUC, reports on construction progress, and reports issued as part of the Mitigation Monitoring, Compliance, and Reporting Program will be published here when available. For Additional InformationThe CPUC, through its environmental review team, is conducting an environmental review of the project. To request additional information or to be added to the mailing list, please contact us by email, phone, or fax as follows:
The CPUC's project manager is:Michael Rosauer, CPUC Project Manager
| |