CPUC logo

 

STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION


Central Valley Natural Gas Storage Project


(Application No. A.09-08-008)

Construction Progress and Mitigation Monitoring

Construction of the Central Valley Gas Storage Project began in March 2011 with the establishment of construction yards, 10-acre compressor station, 5-acre remote well pad site and three observation wells. Notices to Proceed (NTPs) have been issued by the CPUC for each of these activities. The majority of construction is expected to start in June 2011 once the CPUC issues NTPs for each project component. Issuance of NTPs will be contingent upon Central Valley compliance with pre-construction requirements as specified by the approved mitigation measures and responsible agency permitting requirements. NTPs that have been issued to Central Valley are noted in the table below.

Notice to Proceed Construction Activities NTP Request Submitted NTP Issued
1

Obtain site access and complete road and site preparation for existing observation wells

Central Valley Request Submitted 02/28/11 CPUC NTP 1 issued 03/21/11
2 Southam #3, #4, and Sara Louise #1; inspection and work-over activities Pending Pending
3 Remote well pad site preparation

Compressor site preparation
Pending Pending
4 Construction of 16-inch dual gathering lines and 24-inch pipe segment between compressor station and remote well pad site Pending Pending
5 Drill up to 10 injection/withdrawal wells at remote well pad site Pending Pending
6 Remote well pad civil foundations, piping systems, temporary compressor, and equipment installation

L-172 meter and interconnection

Saltwater disposal pipeline from McAusland Road to remote well pad site

Compressor station civil foundations, piping systems, temporary compressor, and equipment installation
Pending Pending
7 Installation of emitting equipment (compressors, dehydration, generators) at the compressor site Pending Pending
8 Site preparation and drilling of Zumwalt #2 observation well Pending Pending
9 Horizontal directional drilling (HDD) for 24-inch pipeline Pending Pending
10 Preparation of 24-inch pipeline right-of-way Pending Pending
11 Construction of 24-inch pipeline between remote well pad and L-401 meter station Pending Pending
12 Complete test well and install saltwater disposal pipeline to remote well pad site Pending Pending
13 Construct L-401 meter station and pipeline connection to L-401 Pending Pending
14 Construction of 24-inch pipeline between remote well pad and L-401 meter station Pending Pending

The CPUC, in conjunction with Central Valley Gas Storage LLC, drafted a Mitigation Monitoring Compliance and Reporting Program (MMCRP) to ensure compliance with mitigation measures approved in the Final MND. Although changes may be made to the document as construction progresses, a current final version of the MMCRP document and attachments, including a map of the approved route with segments, is found here.

A CPUC Environmental Monitor (EM) is monitoring construction activities to ensure that they are conducted in accordance with the approved mitigation measures and permit conditions. Weekly reports documenting construction status and compliance activities will be posted here.

As defined by the MMCRP, at various times throughout project construction, the need for extra workspace or additional access roads may be identified. Similarly, changes to the project requirements (mitigation measures, specifications, etc.) may be needed to facilitate construction or provide more effective protection of resources (e.g., installation of additional erosion control outside of approved disturbance areas). The CPUC Project Manager, along with the CPUC EMs, will implement the variance procedures defined in the MMCRP to evaluate each proposed project change for its potential for creating significant environmental effects to determine whether supplemental California Environmental Quality Act (CEQA) and/or National Environmental Policy Act (NEPA) review is required. Variance requests processed to date are provided in the table below.

Variance
Request
Date
Requested
Date
Issued
Segment Description
None N/A  N/A  N/A  N/A 

This page contains tables and is best viewed with Netscape Energy Division web coordinator.

Project Home Page - CPUC Environmental Information - CPUC Home

CVGS Home