STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

San Diego Gas & Electric East County Substation Project

(Application A.09-08-003)
 

     
Related Links

Sempra Transmission Project

SDG&E ECO
Project

Welcome to the California Public Utilities Commission (CPUC) website for the environmental review for the proposed construction of the San Diego Gas & Electric (SDG&E) East County (ECO) Substation Project located in southeastern San Diego County, California.  SDG&E submitted an application to the CPUC on August 10, 2009 (Application A.09-08-003). The Proposed Project is subject to review under both the California Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA). This site provides access to public documents and information relevant to the CEQA and NEPA review processes.

Background

SDG&E filed an application for a Permit to Construct the ECO Substation Project with the CPUC and an application for a Right-of-Way (ROW) Grant from the Bureau of Land Management (BLM).  The Proposed Project will cross approximately 1.5 miles of land managed by BLM.  The CPUC will evaluate the environmental impacts of the Proposed Project in accordance with CEQA and the BLM will evaluate the Proposed Project in accordance with NEPA.

The ECO Substation Project, as proposed by SDG&E, includes the following major components:

  • Construction of a 500/230/138 kilovolt (kV) substation in Eastern San Diego County

  • Construction of the Southwest Power link (SWPL) loop-in, a short loop-in of the existing SWPL transmission line to the proposed ECO Substation

  • Construction of a138 kV transmission line, approximately 13.3 miles in length, running between the proposed ECO Substation and the rebuilt Boulevard Substation

  • Rebuild of the existing Boulevard Substation

  • Rebuild of the White Star Communication Facility.

    The Proposed Project would provide an interconnection hub for renewable generation along SDG&E’s existing SWPL 500 kV transmission line. In addition to accommodating the region’s planned renewable generation, the project would also provide a second source for the southeastern 138 kV transmission system that avoids the vulnerability of common structure outages, which would increase the reliability of electrical service for Boulevard, Jacumba, and surrounding communities. The Proposed Project would provide interconnection capability at three voltage levels, which would provide renewable generators the option to connect at a voltage level that is appropriately sized for their project.

    The primary component of the Proposed Project, the ECO Substation, is situated approximately 0.5 mile north of the United States (U.S.)­Mexico border and 0.5 mile west of the Imperial County border.  The Project Location Map depicts the location of the project components.

    Application and Proponent's Environmental Assessment (PEA)

    The PEA was submitted August 10, 2009 and is available here.

    Other Documents Available

    The First PEA deficiency letter was sent by the CPUC on September 9, 2009 and can be viewed here.

    Application deemed complete on October 2, 2009. Letter can be viewed here.

    The CPUC is currently seeking further information from area developers (based on developer information provided by SDG&E) to assess whether such information should be treated as privileged.

     

    Environmental Impact Report (EIR)/Environmental Impact Statement (EIS)

    Draft EIR/EIS

    The Draft EIR/EIS will be published here, when available.

     

    Final EIR/EIS

    The Final EIR/EIS will be published here, when available.

    Commission Decision

    The Commission’s decision will be posted here when available.

    Construction Progress and Mitigation Monitoring

    Reports issued by the CPUC, reports on construction progress, and reports issued as part of the Mitigation Monitoring Program will be published here, when available.

    For Additional Information

    The CPUC, through its Environmental Review Team, is conducting an environmental review of this project. To request additional information or to be added to the mailing list, please contact us by email, fax, or phone as follows:

    Project email: ecosub@dudek.com
    Project fax and voicemail: (800) 371-8854

    The CPUC's Project Manager is:

    Iain Fisher, CPUC Project Manager
    California Public Utilities Commission
    505 Van Ness Avenue
    San Francisco CA 94102

    Tel. (415) 355-5580

    Fax (415) 703-2200


    The BLM Project Manager is:

    Lynnette Elser, BLM Project Manager
    Planning & Environmental Coordinator
    California Desert District Office
    (951) 697-5233

     

     

     

     

     
     
     


    This page contains tables and is best viewed with Netscape or Internet Explorer. Please report any problems to the Energy Division web coordinator.

                             Project Home Page - CPUC Environmental Information - CPUC Home