NOTE: Linked files presented on this page are in PDF format. To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your computer. For faster results in displaying the larger files, right-click the file's link, click "Save Target As" to download the file to your hard drive, then double-click the downloaded file.

 

Back to ECO Project Home Page  

Welcome to the Mitigation Monitoring Compliance and Reporting Program page for the East County (ECO) Substation Project in southeastern San Diego County, California.

Pursuant to the California Public Utilities Commission’s (CPUC) approval of the Project, San Diego Gas & Electric (SDG&E) is required to implement the Applicant Proposed Measures (APMs) and mitigation measures identified in the Final Environmental Impact Report/Environmental Impact Statement (EIR/EIS) and the Mitigation Monitoring, Reporting, and Compliance Program (MMRCP). The CPUC, as the lead agency, is responsible for ensuring that the APMs and mitigation measures, as well as plans reviewed and approved by other agencies, are implemented throughout the construction phase of the Project. Below are Project documents related to mitigation monitoring that are available for public review.

Quick Links

Mitigation Monitoring, Compliance and Reporting Program

Notices to Proceed

Environmental Monitoring Reports

Minor Project Refinement Requests

Mitigation Monitoring, Compliance and Reporting Program

The program’s goal is to ensure compliance with CPUC and Bureau of Land Management (BLM) adopted mitigation. The CPUC and BLM, in conjunction with SDG&E, drafted a Mitigation Monitoring Compliance and Reporting Program (MMCRP) to ensure compliance with mitigation measures approved in the Final EIR/EIS. A link to view a complete copy of the MMCRP is provided below.

MMCRP

Notices to Proceed (NTPs)

NTPs are issued contingent upon SDG&E’s compliance with pre-construction requirements as specified by the approved mitigation measures and responsible agency permitting requirements. A link to the approved pre-compliance reports, permit applications, and other documents is provided below.

Pre-compliance reports, permit applications, and other documents

Notice to Proceed Description NTP Request NTP Approval
001 Abatement Activities at the Boulevard Substation Rebuild Site. 11/29/12 11/30/12
002 Construction of a new substation (a 500 kV yard and a 230/138 kV yard). 12/20/12 2/1/13
003 Geotechnical Activities 1/7/13 2/1/13 - CPUC

2/5/13 - BLM

2/11/13 - CPUC (BLM lands)
004 Geotechnical Activities 2/28/13 3/4/13
005 Construction Yards 4/5/13

SDG&E Supplemental Memo (5/13/13)
5/21/13
006 138 kV Underground Transmission Line along Southern Access Road  6/27/13 7/2/13
007 138 kV Underground Transmission Line within Old Highway 80 and Carrizo Gorge Road  7/12/13 7/30/13 (CPUC)

8/16/13 (BLM)
008 Construction Activities Associated with Boulevard Substation Rebuild  8/1/13 8/2/13 (CPUC)
009 138 kV Underground Transmission Line from Boulevard Substation to 138 kV Overhead Transmission Line  8/30/13 9/25/13 (CPUC)
010 138 kV Underground Transmission Line from Carrizo Gorge Road to Steel Pole 91  9/30/13 10/17/13 (CPUC)
011 138 kV Overhead Transmission Line  10/02/13 11/5/13 (CPUC)
012 Geotechnical Activities Associated with Fault Investigations at the Southwest Powerlink (SWPL) Loop-In  11/15/13 11/19/13
013 138 kV Overhead Transmission Line Steel Pole- 105B and Steel Pole- 108A  11/25/13 12/4/13 (CPUC)
014 Construction of Southwest Powerlink (SWPL) loop-in to connect the existing 500 kV SWPL transmission line to the ECO Substation site.  3/11/14 3/18/14 (CPUC)

Environmental Monitoring Reports

A CPUC Environmental Monitor (EM) is monitoring construction activities to ensure that they are conducted in accordance with the approved mitigation measures and permit conditions. Reports documenting construction status and compliance activities are provided below.

Weekly Report # Reporting Period Summary of Work Completed Environmental Issues/Concerns
001 February 4, to February 17, 2013 Abatement activities at the Boulevard Substation Rebuild Site No issues/concerns reported.
Mobilization of Construction Equipment to ECO Substation Site Non-Compliance Report (NCR) #001 – Equipment mobilized to the project site prior to notifying environmental monitors.
Geotechnical Investigations NCR #002 – Geotechnical activities were completed at a location not authorized under BLM NTP No. 001 or CPUC NTP No. 003.
002 March 11, to March 25, 2013 Mobilization of Construction Equipment and Installation of Best Management Practices (BMPs) No issues/concerns reported.
Site Clearing and Grubbing No issues/concerns reported.
Geotechnical Investigations No issues/concerns reported.
003 March 25, to March 29, 2013 Site Clearing and Grubbing No issues/concerns reported.
004 May 13, to May 27, 2013
Clearing, Grubbing, and Grading of the Southern Access Road No issues/concerns reported.
Mobilization of Construction Equipment and Excavation of Temporary Retention Basin No issues/concerns reported.
005 May 27, to June 9, 2013
Grading Southern Access Road No issues/concerns reported.
Excavation and Construction of Temporary Retention Basin No issues/concerns reported.
006 June 10, to June 23, 2013
Grading ECO Substation No issues/concerns reported.
Clearing, Grubbing, and Fencing at Carrizo Gorge Fly Yard No issues/concerns reported.
007 June 23, to July 7, 2013
Grading ECO Substation No issues/concerns reported.
Clearing, Grubbing, and Fencing of Jewel Valley Fly Yard Construction activities completed beyond the authorized work limits.
Installation of Best Management Practices (BMPs) at Carrizo Gorge Fly Yard No issues/concerns reported.
008 July 8, to July 21, 2013
ECO Substation Earthwork Activities No issues/concerns reported.
Clearing and Grubbing at Jewel Valley Fly Yard No issues/concerns reported.
Clearing and Grubbing at Carrizo Gorge Fly Yard No issues/concerns reported.
009 July 22, to August 4, 2013
ECO Substation Earthwork Activities No issues/concerns reported.
BMP’s at Jewel Valley Fly Yard No issues/concerns reported.
010 August 5, to August 18, 2013
ECO Substation Earthwork Activities No issues/concerns reported.
Mobilize construction equipment to Jewel Valley Fly Yard No issues/concerns reported.
Mobilize construction equipment to Carrizo Gorge Fly Yard No issues/concerns reported.
011 August 19 to September 1, 2013
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
012 September 2, to September 15, 2013
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
ECO Substation Non-Compliance Report / Temporary Stop Work Order 001 – Failure to effectively implement MM-CUL-1D.
Construction Yards No issues/concerns reported.
013 September 16, to September 29, 2013
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards NCR #003 – Vegetation clearing beyond the approved work limits.
014 September 30, to October 13, 2013
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
015 October 14, to October 27, 2013
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
016 October 28, to November 10, 2013
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line Construction activities completed outside of the permitted work hours.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
017 November 11, to November 24, 2013
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line Minor Deviation - Vegetation removal in absence of a biological monitor being present.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
018 November 25, to December 18, 2013
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation NCR #004 - Construction equipment traveled off an approved access road.
Construction Yards No issues/concerns reported.
019 December 9, to December 22, 2013
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
020 December 23, to January 5, 2014
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
021 January 6, to January 19, 2014
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
022 January 20, to February 2, 2014
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line Minor Deviation - Construction activities occuring prior to nesting bird surveys being completed.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
023 February 3, to February 16, 2014
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
024 February 17, to March 2, 2014
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line Minor Deviation - Construction activities occuring prior to nesting bird surveys.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
025 March 3, to March 16, 2014
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
026 March 17, to March 30, 2014
Boulevard Substation Rebuild No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards Minor Deviation - Unauthorized disturbance beyond project work limits.
027 March 31, to April 13, 2014
Boulevard Substation Rebuild Site No issues/concerns reported.
138 kV Underground Transmission Line Minor Deviation - Unauthorized travel along an access road that was not approved for project use.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
028 April 14, to April 27, 2014
Boulevard Substation Rebuild Site No issues/concerns reported.
138 kV Underground Transmission Line Minor Deviation - Unauthorized travel along an access road that was not approved for project use.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation

NCR #005 – Construction delivery truck utilized an access road that was not approved for project use.

Minor Deviation – Construction flatbed truck drove over boundry staking and roping.

Minor Deviation - Unauthorized travel along an access road that was not approved for project use (SWPL Loop-In).
Construction Yards No issues/concerns reported.
029 April 28, to May 11, 2014
Boulevard Substation Rebuild Site No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.
030 May 12, to May 25, 2014
Boulevard Substation Rebuild Site No issues/concerns reported.
138 kV Underground Transmission Line No issues/concerns reported.
138 kV Overhead Transmission Line No issues/concerns reported.
ECO Substation No issues/concerns reported.
Construction Yards No issues/concerns reported.

CPUC - Minor Project Refinement Requests

The Commission decision approving the permit to construct authorizes Energy Division staff to approve requests by SDG&E for minor project refinements. The decision states that minor project refinements may be approved so long as such minor project refinements are located within the geographic boundary of the study area of the Environmental Impact Report/Environmental Impact Statement and do not, without mitigation, result in a new significant impact or a substantial increase in the severity of a previously identified significant impact based on the criteria used in the environmental document; conflict with any mitigation measure or applicable law or policy; or trigger an additional permit requirement. Below are SDG&E's Minor Project Refinement Requests that have been approved by the CPUC to date.

Minor Project Refinement Request Description MPR Request MPR Approval
001 Temporary Retention Basin 1/25/13 2/7/13 (CPUC)
002 Adjustments to the Domingo Lake and Jewel Valley Construction Yards 3/22/13 5/20/13 (CPUC)

5/13/13 (BLM)
003 Adjustments to the Carrizo Gorge Construction Yard 3/22/13 5/20/13 (CPUC)

5/13/13 (BLM)
004 Adjustments to the Southern Access Road & 138 kV Overhead & Underground Transmission Line 5/17/13 6/26/13 (CPUC)

7/2/13 (BLM)
005 Adjustments to the Boulevard Substation Rebuild Site 6/27/13 7/26/13 CPUC

7/16/13 (BLM)
006 Adjustments to the 138 kV Overhead Transmission Line 07/05/13 09/23/13 CPUC

8/21/13 (BLM)
007 Relocation of Temporary Retention Basin 8/16/13 8/22/13 CPUC

8/22/13 (BLM)
008 Construction Water Use 9/20/13 10/1/13 CPUC
009 Additional Temporary Work Space for Fence Replacement 11/22/13

11/26/13 (CPUC)

12/5/13 (BLM)

010 Access Road and Work Space Refinements at Steel Pole 63 & 64 12/19/13

1/14/14 (CPUC)

1/8/14 (BLM)

011 Temporary Meeting Location for Material & Equipment 1/16/14

1/22/14 (CPUC)

012 Work Space Refinements to the Sothwest Powerlink 2/27/14

3/11/14 (CPUC)

3/5/14 (BLM)

013 Additional Temporary Work Space at 138kV Overhead Transmission Line 4/3/14

4/17/14 (CPUC)

6/16/14 (BLM)

014 Amended Construction Water Supply Plan 6/11/14

6/12/14 (CPUC)

BLM - Variance Requests

As defined by the MMCRP, at various times throughout project construction, the need for workspace modifications or changes to the project requirements may be needed to facilitate construction or provide more effective protection of resources. The BLM will implement the variance procedures defined in the MMCRP to evaluate each proposed project variance for its potential for creating adverse environmental effects to determine whether supplemental NEPA review is required.

Variance Request Description Variance Request Submitted Variance Issued
001 Reroute a portion of the 138 kV underground transmission route and associated transition poles from BLM-managed land to private land. 7/5/13 7/12/13

For Additional Information

To request additional information or to be added to the mailing list, please contact us by email, fax, or phone as follows:

Project email: ecosub@dudek.com
Project fax and voicemail: (800) 371-8854

To leave a voice-mail message, please press “1.”
To send a fax, please press “2.”

The CPUC's project manager is:

Eric Chiang, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-1956
Fax (415) 703-2200

The BLM's project manager is:

Brian Paul, BLM Project Manager
Bureau of Land Management, El Centro Field Office
1661 S. 4th Street
El Centro, CA 92243
Tel. (760) 337-4400

 

This page contains tables and is best viewed with Internet Explorer. Please report any problems to the Energy Division web coordinator.

ECO Project Home Page - CPUC Environmental Information - CPUC Home

 

Contact Information During Construction

Project email: ecosub@dudek.com

Project voicemail: (800) 371-8854

To leave a voice-mail message, please press “1.”
To send a fax, please press “2.”