Data Requests to SDG&E
The EIR team has submitted data requests to SDG&E for specific information related to the South Bay Substation Relocation Project during preparation of the EIR. Those requests and the applicants’ responses are listed below. Additional information and technical studies are included in SDG&E’s Proponent’s Environmental Assessment.
Data Request No. 1 (September 8, 2010) and Response (October 1, 2010)
Data Request No. 2 (November 3, 2010) and Response (November 12, 2010)
Data Request No. 3 (October 22, 2010) and Response (October 29, 2010)
Data Request No. 4 (February 1, 2011) and Response (February 8, 2011)
Data Request No. 5 (May 3, 2011) and Response (May 24, 2011)
Data Request No. 6 (June 8, 2011) and Response (June 22, 2011)
Data Request No. 7 (July 5, 2011) and Response (July 21, 2011)
Data Request No. 8 (September 2, 2011) and Response (September 14, 2011)
Data Request No. 9 (September 19, 2011) and Response (September 27, 2011)
Data Request No. 10 (October 6, 2011) and Response (October 18, 2011)
Data Request No. 11 (November 4, 2011) and Response (November 15, 2011)
Data Request No. 12 (November 16, 2011) Data Request Response 12 provided by SDG&E is confidential pursuant to Public Utilities Code Section 583 and General Order 66-C and therefore not provided herein.
Data Request No. 13 (March 16, 2012) and Response
(April 12, 2012)
This page contains tables and is
best viewed with Netscape or Internet Explorer. Please report any problems to
the Energy Division web
coordinator.
Project Home Page -
CPUC Environmental Information - CPUC Home