STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

PUC > Energy > Transmission and Environmental Review > Current Projects > San Diego Gas & Electric – South Bay Substation Relocation Project

San Diego Gas & Electric – South Bay Substation Relocation Project

 

(Application A.10-06-007)

NOTE: Linked files presented on this page are in PDF format. To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your computer.
For faster results in displaying the larger files, right-click the file's link, click "Save Target As" to download the file to your hard drive, then double-click the downloaded file.

 

 

Welcome to the Mitigation Monitoring Compliance and Reporting Program page for the San Diego Gas & Electric (SDG&E) South Bay Substation Relocation Project located in the City of Chula Vista, California, in the southwesterly portion of San Diego County, California.

Pursuant to the California Public Utilities Commission’s (CPUC) approval of the Project, San Diego Gas & Electric (SDG&E) is required to implement the Applicant Proposed Measures (APMs) and mitigation measures identified in the Final Environmental Impact Report (EIR) and the Mitigation Monitoring, Reporting, and Compliance Program (MMRCP). The CPUC, as the lead agency, is responsible for ensuring that the APMs and mitigation measures, as well as plans reviewed and approved by other agencies, are implemented throughout the construction phase of the Project. Below are project documents related to mitigation monitoring that are available for public review.

Quick Links

Mitigation Monitoring, Compliance and Reporting Program

Notice to Proceed

Environmental Monitoring Reports

Minor Project Refinements Requests

Mitigation Monitoring, Compliance and Reporting Program

The program’s goal is to ensure compliance with CPUC’s adopted mitigation. The CPUC, in conjunction with SDG&E, drafted a Mitigation Monitoring Compliance and Reporting Program (MMCRP) to ensure compliance with mitigation measures approved in the Final EIR. Click on link below to view a complete copy of the MMCRP.

MMCRP

Notice to Proceed (NTP)

A NTP is issued contingent upon SDG&E’s compliance with pre-construction requirements as specified by the approved mitigation measures and responsible agency permitting requirements. A link to the approved pre-compliance reports, permit applications, and other documents is provided below.

Pre-compliance reports, permit applications, and other documents

Notice to Proceed

Description

NTP Request

NTP Approval

001

Limited Construction Activities Associated with the Bay Boulevard Substation Component and Potholing Activities

11/07/14

11/14/14
Attachment A

002

Bay Boulevard Construction

03/09/15

03/17/15
Attachment A

003

Transmission Construction

08/14/15

09/03/15
Attachment A

004

Dismantling of the South Bay Substation

06/22/16

Data Request 1 (07/05/16)


Data Response 1 (07/12/16)

07/18/16
Attachment A

 

Environmental Monitoring Reports

A CPUC Environmental Monitor (EM) is monitoring construction activities to ensure that they are conducted in accordance with the approved mitigation measures and permit conditions. Reports documenting construction status and compliance activities are provided below.

Weekly Report #

Reporting Period

Environmental Issues / Concerns

001

January 5 to February 5, 2015

No issues/concerns reported

002

February 16 to March 1, 2015

No issues/concerns reported

003

March 2 to March 15, 2015

No issues/concerns reported

004

March 16 to March 29, 2015

No issues/concerns to report

005

March 30 to April 12, 2015

No issues/concerns to report

006

April 13 to April 26, 2015

No issues/concerns to report

007

April 27 to May 10, 2015

No issues/concerns to report

008

May 11 to May 24, 2015

No issues/concerns to report

009

May 25 to June 7, 2015

No issues/concerns to report

010

June 8 to June 21, 2015

No issues/concerns to report

011

June 22 to July 5, 2015

No issues/concerns to report

012

July 6 to July 19, 2015

No issues/concerns to report

013

July 20 to August 2, 2015

No issues/concerns to report

014

August 3 to August 31, 2015

No issues/concerns to report

015

September 1 to September 30, 2015

No issues/concerns to report

016

October 1 to October 31, 2015

No issues/concerns to report

017

November 1 to November 30, 2015

No issues/concerns to report

018

December 1 to December 31 2015

NCR 001

019

January 1 to January 31, 2016

No issues/concerns to report

020

February 1 to February 29, 2016

No issues/concerns to report

021

March 1 to March 31, 2016

No issues/concerns to report

022

April 1 to April 30, 2016

No issues/concerns to report

023

May 1 to May 31, 2016

No issues/concerns to report

024

June 1 to June 30, 2016

No issues/concerns to report

025

July 1 to August 3, 2016

No issues/concerns to report

026

August 4 to September 16, 2016

No issues/concerns to report

Minor Project Refinement Requests

The Commission decision approving the permit to construct authorizes Energy Division staff to approve requests by SDG&E for minor project refinements. The decision states that the Energy Division may approve requests by San Diego Gas & Electric Company for minor project refinements that may be necessary due to final engineering of the South Bay Substation Relocation Project so long as such minor project refinements are located within the geographic boundary of the study area of the Environmental Impact Report and do not, without mitigation, result in a new significant impact or a substantial increase in the severity of a previously identified significant impact based on the criteria used in the environmental document; conflict with any mitigation measure or applicable law or policy; or trigger an additional permit requirement. San Diego Gas & Electric Company shall seek any other project refinements by a petition to modify this decision.

SDG&E's Minor Project Refinement Requests will be made available below when submitted to the CPUC.

For Additional Information

The CPUC, through its Environmental Review Team, is conducting an environmental review of the project. To request additional information or to be added to the mailing list, please contact us by email or phone, as follows:

Project email: southbaysub@dudek.com
Project voicemail: (800) 930-8275

The CPUC's project manager is:

Jensen Uchida, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-5484
Fax (415) 703-2200

Please report any problems to the Energy Division web coordinator.