STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

Sacramento Natural Gas Storage Project

(Application A.07-04-013)
 

     

Welcome to the California Public Utilities Commission (CPUC) website for the California Environmental Quality Act (CEQA) review of the proposed construction of the Sacramento Natural Gas Storage Project. An application for this project was submitted to the CPUC on April 9, 2007 (Application A.07-04-013). This site provides access to public documents and information relevant to the CEQA review.

Background

Sacramento Natural Gas Storage, LLC (SNGS) has filed an application with the CPUC to construct the Sacramento Natural Gas Storage Project within the City of Sacramento. The CPUC is the CEQA lead agency. A Proponent’s Environmental Assessment was filed with the CPUC on April 9, 2007.

The SNGS project, as proposed by the applicant, consists of the operation of a natural gas storage facility, which would require the construction of three project components, as follows:

  • Wellhead site (including injection and withdrawal wells)
  • Compressor station
  • Approximately 2 miles of pipeline connections between the wells and compressor station and between the compressor station and existing Sacramento Municipal Utilities District (SMUD) and Pacific Gas & Electric (PG&E) natural gas pipelines.

    The project would provide natural gas storage by injecting natural gas into the Florin Gas Field, a depleted natural gas reservoir located approximately 3,800 feet underground. Natural gas would then be withdrawn according to the needs of its customers. SNGS proposes to initially inject up to 8 billion cubic feet (Bcf) of natural gas into the Florin Gas Field.

    The proposed project would be located in the southeast portion of the City of Sacramento.
    (see Project Location Map)

    CPUC Application Review

    The CPUC is responsible for the review and approval of any natural gas storage facility in California. In proposals such as this, the CPUC has a two-part review process to evaluate economic and environmental impacts. The CPUC conducts a legal proceeding before an administrative law judge to examine the economic and public utility issues, including impacts to utility ratepayers. At the same time, the CPUC conducts a legal proceeding before an administrative law judge, which may examine the economic and public utility issues, including impacts to utility ratepayers. The ultimate result of the two reviews is a decision by the Commission whether to grant a Certificate of Public Convenience and Necessity for the project.

    Application, Review of Completeness, Proponent's Environmental Assessment (PEA), and Amendments

    SNGS’s Application and Proponent’s Environmental Assessment (April 9, 2007)

    SNGS’s Supplement to Proponent’s Environmental Assessment (July 16, 2007)

    SNGS Amendment to Application (September 12, 2008)

    Other Documents Available

    SNGS Application Notice of Completion (April 3, 2008)

    First Deficiency Letter Response (August 10, 2007)

    Second Deficiency Letter Response (Purpose and Need and Selection Criteria [Alternatives])

    Notice of Preparation (November 16, 2007)

    Scoping Report (January 8, 2008)

    Notice of Availability

    On April 28, 2009 the CPUC conducted a public meeting regarding the SNGS Draft EIR.  The meeting was held at Depot Park Conference Center in Sacramento, California.  The meeting Agenda, PowerPoint Presentation presented, and Comment Form are available here.

    A letter was mailed to the State Clearinghouse on May 4, 2009 that requests they distribute the Draft EIR to additional agencies.  Letter can be viewed here

    Environmental Impact Report

    Draft EIR (April 2009)

    The CPUC released the Draft Environmental Impact Report (Draft EIR)  for the Proposed Project on April 8, 2009.  The public comment period for this document will end June 22, 2009.

    The original end of the DEIR review period has been extended from May 25, 2009, to June 22, 2009.   The notice of extension can be viewed here.

    For Additional Information

    The CPUC, through its Environmental Review Team, is conducting an environmental review of this project. To request additional information or to be added to the mailing list, please contact us by email, fax, or phone as follows:

    Project email: sngs@dudek.com
    Project fax and voicemail: (800) 371-8797

    The CPUC's Project Manager is:

    Michael Rosauer, CPUC Project Manager
    California Public Utilities Commission
    505 Van Ness Avenue
    San Francisco CA 94102
    Tel. (415) 703-2579

    Fax (415) 703-2200
    Email:rosauer@cpuc.ca.gov



    This page contains tables and is best viewed with Netscape or Internet Explorer. Please report any problems to the Energy Division web coordinator.

                             Project Home Page - CPUC Environmental Information - CPUC Home