Welcome to the California Public Utilities Commission (CPUC) website for the California Environmental Quality Act (CEQA) review of the Prineville to Reno Fiber Optic Project (project) proposed by Zayo Group, LLC (applicant). An application (A.20-10-008) for the project was submitted to the CPUC on October 1, 2020 and includes the Proponent's Environmental Assessment (PEA) prepared pursuant to Rule 2.4 of the CPUC's Rules of Practice and Procedure. Click here to access the Formal Proceeding website. The site provides access to public documents and information relevant to the CEQA review process.
In accordance with CEQA, the CPUC, as the Lead Agency, is required to conduct a review of the environmental impacts of the proposed project and has prepared an Environmental Impact Report (EIR). This site provides access to public documents and information relevant to the CEQA review process. Additional project information and documentation will be posted as it becomes available.
Zayo Group, LLC, a California telephone corporation, proposes the construction and operation of an underground fiber optic network from Prineville, Oregon, to Reno, Nevada, spanning 433.8 miles. The applicant intends to construct fiber optics infrastructure and associated facilities (such as conduits, fiber optics cable, handholes and manholes) in connection with the transport and transmission of communications. The three state project includes a 193.9 mile route through California. The project primary travels along U.S. Route 395 from the Oregon border through Modoc, Lassen and Sierra counties and into Nevada. Figure 1: (Project Overview Map PDF) shows the route in California.
According to the applicant, the purpose of the project is to improve the quality of rural broadband in south-central Oregon, northeastern California, and northwestern Nevada, and to make affordable broadband internet services available to currently undeserved communities in these areas.
The portion of the project that crosses California would extend 193.9 miles across portions of Modoc, Lassen, and Sierra counties. The project generally follows U.S. Route 395 but also county roads between the communities of Standish and Buntingville in Lassen County, where it follows Lassen County Road A3 for 7.35 miles and Cummings Road for 1.15 miles before returning to the right-of-way parallel to U.S. Highway 395. Conduit to house the new fiber optic cable would be buried using a combination of plowing or trenching construction techniques.
The lands underlying the Caltrans right-of-way are owned or administered by various state, federal, and private entities, including (BLM); U.S. Forest Service; U.S. Fish and Wildlife Service; California State Lands Commission; unincorporated Modoc, Lassen, and Sierra counties; the City of Alturas; and several tribal entities. The CPUC is the CEQA lead agency. BLM ?This website provides access to public documents and information relevant to the CEQA review processes and mitigation monitoring. For information on the NEPA process, please refer to the BLM’s eplanning website for the project at https://eplanning.blm.gov/eplanning-ui/project/1503554/510
Quick Links
- Proponent's Environmental Assessment (PEA) and Application
- Zayo Response Letter February 2, 2021
- Zayo Response Letter, dated February 18, 2021
- Zayo Response Letter, dated February 26, 2021
- Zayo Response Letter, dated April 28, 2021 (Please note: All files are mark-ups)
- CPUC Completeness Letter - February 3, 2021
- Notice of Preparation (NOP) - March 8, 2021
- Public Scoping Report - April 23, 2021
Data Response
Schedule
Milestone |
Date |
Applicant files Application and PEA |
October 1, 2020 |
Application deemed completed by CPUC |
February 3, 2021 |
Publish Notice of Preparation (NOP) |
March 8, 2021 |
Scoping Meeting |
March 24, 2021 |
Post Scoping Report |
April 2021 |
Publication of Draft Environmental Impact Report (Draft EIR) |
Spring 2021 |
Draft EIR Public Comment Meeting |
Spring 2021 |
Close of Draft EIR comment period (45 days) |
Spring 2021 |
Publication of Final EIR |
Summer 2022 |
CPUC Issues Decision |
Summer 2022 |
CPUC Issue notice to proceed and start construction |
Summer 2022 |
Finish construction (6 months) |
Fall 2022 |
For Additional Information
The CPUC, through its Environmental Review Team, is conducting an environmental review of the project. To request additional information or to be added to the mailing list, please contact the CPUC's Project Manager.
Connie Chen, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102
Email: connie.chen@cpuc.ca.gov
Tel: (415) 703-2124
Fax: (909) 307-0056
|