Welcome to the California
Public Utilities Commission (CPUC) website for the California
Environmental Quality Act (CEQA) review of proposed construction of
Southern California Edison (SCE) Triton Substation Project. An
application for this project was submitted to the CPUC on November 21,
2008 (Application
A.08-11-019). This site provides access to public documents
and information relevant to the CEQA review process.
Background
Southern California Edison (SCE) has filed an application with the CPUC
to construct the Triton Substation project for a new 56 megavolt ampere
(MVA) 115/12 kilovolt (kV) unattended substation (Triton Substation)
that would serve the cities of Temecula, Murrieta, and unincorporated
southwestern Riverside County. The Triton Substation is proposed to be
built on an approximately 10-acre parcel at the southeast corner of
Nicolas Road and Calle Medusa in Temecula, California. Click
here for a map showing the location of the proposed site.
The proposed project would also include construction of a 115 kV
loop-in from the existing Valley-Auld-Pauba 115 kV subtransmission line
into the new substation, two new underground 12 kV distribution duct
banks, and a telecommunications system to connect the proposed Triton
Substation to the existing Auld and Moraga substations. SCE’s existing
Canine 33/12 kV Substation in Temecula would also be retired when the
Triton Substation is operational. SCE has designed the Triton
Substation to eventually expand to 112 MVA at some future date,
depending on need.
SCE currently forecasts that the demand in the service area may exceed
the designed operating limits of the existing distribution facilities
as early as the summer of 2010. SCE has designed the project to meet
the long-term forecasted electrical demands of the cities of Temecula,
Murrieta, and adjacent areas of unincorporated southwestern Riverside
County while maintaining system reliability and enhancing operational
flexibility. SCE initially proposed to construct the project from
approximately October 2009 to May 2010. If the CPUC approves the
project, the earliest construction would begin would be spring 2010. If
approved, construction is estimated to take 8 months. The estimated
cost of the proposed Triton Substation is approximately $29.9 million
in 2008 constant dollars.
Application and Proponent’s Environmental
Assessment (PEA)
The application
and PEA
for the Triton Substation Project are available to view.
The CPUC sent SCE a deficiency letter on December 22, 2008. The CPUC
found the application and the additional information that SCE submitted
in response to satisfy the Commission’s Information and Criteria List
and determined it to be complete on April 30, 2009.
Environmental Review Process
As the lead CEQA agency, the CPUC circulated a Draft Mitigated Negative
Declaration (Draft MND) and supporting Initial Study (IS) on November
18, 2009. The Draft MND/IS describes the project, evaluates potential
environmental impacts, identifies impacts that could be significant,
and presents mitigation measures that would avoid or reduce potential
impacts to less than significant levels.
Click on the links below to download each chapter of the
Draft Mitigated Negative Declaration / Initial
Study:
Cover
Draft
Mitigated Negative Declaration
Table
of Contents
1.0
Background Information
2.0
Environmental Determination
3.0
Evaluation of Environmental Impacts
4.0
List of Preparers, Agencies, and Persons Contacted
5.0
Mitigation Monitoring, Reporting, and Compliance Plan
Appendix
A Review of Alternative Substation Locations
Appendix
B Air Quality and Greenhouse Gas Emissions
Appendix
C Biological Survey Maps
Public Comment Period
The circulation of the Draft MND/IS opens a public comment period that
will extend from November 18, 2009, through December 17, 2009. The CPUC
will host a public meeting on the Triton Substation project:
|
Date:
Time:
Location:
|
Monday December 7, 2009
7:00 p.m.
Calvary Baptist Church of Temecula
31089 Nicolas Road
Temecula, California 92591
|
Interested parties may present comments about the project and Draft
MND/IS. Written comments must be postmarked or received by fax or email
no later than December 17, 2009. Please be sure to include your name,
address, and telephone number in correspondence. Send written comments
to:
Triton
Substation Project
c/o Ecology and Environment, Inc.
Attn: Karen Ladd, Project Manager
130 Battery Street, 4th Floor
San Francisco, CA 94111
Fax: (415) 981-0801
Email: triton@ene.com
Following the public comment period, the CPUC will prepare a Final
MND/IS that will address comments received on the Draft MND/IS. There
is no comment period following issuance of the Final MND. The CPUC will
then determine the adequacy of the Final MND. If adequate, the CPUC
will adopt the document as being compliant with CEQA and issue a
Proposed Decision on the Application, which will be announced and
published concurrent with a scheduled CPUC commission meeting. After
the Commission makes the decision on the Application, a Notice of
Determination will be mailed to the State Clearinghouse within 5 days
of the Decision. After the Notice of Determination is filed, the 30-day
statute of limitations for court challenges begins to run.
Availability of Draft MND/IS
Copies of the Draft MND/IS will also be available for review at the
Temecula Public Library and on the project website.
Temecula
Public Library
30600 Pauba Road
Temecula, CA 92592-6206
(951) 693-8900
Other Documents Available
Deficiency
Letter (December 22, 2008)
SCE
fact sheet (April 2008)
SCE
project update (October 2008)
For Additional Information
The CPUC, through its Environmental Review Team, is conducting an
environmental review of the project. To request additional information
or to be added to the mailing list, please contact us by email, fax, or
phone, as follows:
Project
email: triton@ene.com
Project fax: (415) 981-0801
Project voicemail (toll-free): (877) 651-3666
The CPUC’s Project Manager is:
Iain Fisher,
CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102
tel. (415) 355-5580
fax (415) 703-2200
email: AEI@cpuc.ca.gov
|