Southern California Edison
Triton Substation Project

(Application No. A.08-11-019)

PDF
Files linked on this page are in Portable Document Format (PDF). To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your PC. Note: For best results in displaying the largest files (see sizes shown in parentheses below for files larger than 3.0 MB), right-click the file's link, click "Save Target As" to download the file to a folder on your hard drive, then browse to that folder and double-click the downloaded file to open it in Acrobat
Welcome to the California Public Utilities Commission (CPUC) website for the California Environmental Quality Act (CEQA) review of proposed construction of Southern California Edison (SCE) Triton Substation Project. An application for this project was submitted to the CPUC on November 21, 2008 (Application A.08-11-019). This site provides access to public documents and information relevant to the CEQA review process.

Background

Southern California Edison (SCE) has filed an application with the CPUC to construct the Triton Substation project for a new 56 megavolt ampere (MVA) 115/12 kilovolt (kV) unattended substation (Triton Substation) that would serve the cities of Temecula, Murrieta, and unincorporated southwestern Riverside County. The Triton Substation is proposed to be built on an approximately 10-acre parcel at the southeast corner of Nicolas Road and Calle Medusa in Temecula, California. Click here for a map showing the location of the proposed site.

The proposed project would also include construction of a 115 kV loop-in from the existing Valley-Auld-Pauba 115 kV subtransmission line into the new substation, two new underground 12 kV distribution duct banks, and a telecommunications system to connect the proposed Triton Substation to the existing Auld and Moraga substations. SCE’s existing Canine 33/12 kV Substation in Temecula would also be retired when the Triton Substation is operational. SCE has designed the Triton Substation to eventually expand to 112 MVA at some future date, depending on need.

SCE currently forecasts that the demand in the service area may exceed the designed operating limits of the existing distribution facilities as early as the summer of 2010. SCE has designed the project to meet the long-term forecasted electrical demands of the cities of Temecula, Murrieta, and adjacent areas of unincorporated southwestern Riverside County while maintaining system reliability and enhancing operational flexibility. SCE initially proposed to construct the project from approximately October 2009 to May 2010. If the CPUC approves the project, the earliest construction would begin would be spring 2010. If approved, construction is estimated to take 8 months. The estimated cost of the proposed Triton Substation is approximately $29.9 million in 2008 constant dollars.

Application and Proponent’s Environmental Assessment (PEA)

The application (3.3 MB) and PEA (11.5 MB) for the Triton Substation Project are available to view.

The CPUC sent SCE a deficiency letter on December 22, 2008. The CPUC found the application and the additional information that SCE submitted in response to satisfy the Commission’s Information and Criteria List and determined it to be complete on April 30, 2009.

Preparation of Draft MND/IS

As the lead CEQA agency, the CPUC circulated a Draft Mitigated Negative Declaration (Draft MND) and supporting Initial Study (IS) on November 18, 2009. The Draft MND/IS describes the project, evaluates potential environmental impacts, identifies impacts that could be significant, and presents mitigation measures that would avoid or reduce potential impacts to less than significant levels.

Click on the links below to download each chapter of the Draft Mitigated Negative Declaration / Initial Study:

Cover
Draft Mitigated Negative Declaration
Table of Contents
1.0 Background Information
2.0 Environmental Determination
3.0 Evaluation of Environmental Impacts (4.9 MB)
4.0 List of Preparers, Agencies, and Persons Contacted
5.0 Mitigation Monitoring, Reporting, and Compliance Plan
Appendix A Review of Alternative Substation Locations
Appendix B Air Quality and Greenhouse Gas Emissions
Appendix C Biological Survey Maps (10 MB)

Public Comment Period and Preparation of the Final MND/IS

The circulation of the Draft MND/IS opened a public comment period on the Triton Substation project from November 18, 2009, through December 17, 2009. During the public comment period, the CPUC hosted a public meeting on Monday, December 7, 2009, at 7:00 p.m. at the Calvary Baptist Church of Temecula, where the CPUC invited interested parties to present comments about the project and Draft MND/IS.

During the comment period, in addition to the oral comments made at the public meeting, the CPUC received comments via mail, email, and voicemail. Following the public comment period, the CPUC prepared a Final MND/IS that addresses comments received on the Draft MND/IS. The CPUC circulated the Final MND/IS on March 10, 2010. There is no comment period for the Final MND.

Availability of Final MND/IS

Click on the links below to download each chapter of the Final Mitigated Negative Declaration / Initial Study:

Cover
Cover Letter
Mitigated Negative Declaration
Table of Contents
1.0 Background Information
2.0 Environmental Determination
3.0 Evaluation of Environmental Impacts (5.2 MB)
4.0 List of Preparers, Agencies, and Persons Contacted
5.0 Mitigation Monitoring, Reporting, and Compliance Plan
6.0 Responses to Comments (8.8 MB)
Appendix A Review of Alternative Substation Locations
Appendix B Air Quality and Greenhouse Gas Emissions
Appendix C Biological Survey Maps (6.8 MB)

Copies of the Final MND/IS will also be available for review at the Temecula Public Library and on the project website.

Temecula Public Library
30600 Pauba Road
Temecula, CA 92592-6206
(951) 693-8900

CPUC Actions After Final MND/IS Circulation and Public Involvement in CPUC General Proceeding

The assigned Administrative Law Judge (ALJ) may seek further briefings or testimony on issues associated with the project, including information on the legal validity of the MND/IS or any other topic pertaining to the issuance of the Permit to Construct.

If the ALJ intends to take further evidence relating to the project then she will convene a pre-hearing conference to allow parties to set out their issues and to establish a timetable for briefing on these issues. Upon completion of briefs the ALJ will then write the proposed decision which may include the recommendation that the Commission adopt and certify the MND/IS.

The Commissioners will evaluate the proposed decision, and may propose alternative decisions. The Commissioners will then vote on whether to issue a Permit to Construct for the Triton Substation.

The decision will be announced and published concurrent with a scheduled CPUC Meeting. Within 30 days after the Decision is issued by the CPUC, parties can apply for rehearing.

If the CPUC approves the proposed project, the CPUC will implement a Mitigation, Monitoring, Reporting, and Compliance Plan. This plan will ensure that the approved project is constructed as defined, and that all adopted mitigation measures and project design features the applicant committed to are implemented to ensure that effects on the environment do not exceed those described in the MND/IS.

Other Documents Available

Deficiency Letter (December 22, 2008)
SCE fact sheet (April 2008)
SCE project update (October 2008)

For Additional Information

To request additional information or to be added to the mailing list, please contact us by email, fax, or phone, as follows:

Project email: triton@ene.com
Project fax: (415) 981-0801
Project voicemail (toll-free): (877) 651-3666


The CPUC’s Project Manager is:

Iain Fisher, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102
tel. (415) 355-5580
fax (415) 703-2200
email: AEI@cpuc.ca.gov
   
Web Info

This page is best viewed with Mozilla Firefox or Internet Explorer. Please report any problems to the Energy Division web coordinator.

   
 
Project Home Page - CPUC Environmental Information - CPUC Home