STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

PUC > Energy > California Environmental Quality Act > Current Projects

Pacific Gas & Electric

Fulton-Fitch Mountain Reconductoring Project

(Application No. A.15-12-005)

Last Update: August 22, 2016

NOTE: Linked files presented on this page are in PDF format. To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your computer. For faster results in displaying the larger files, right-click the file's link, click "Save Target As" to download the file to your hard drive, then double-click the downloaded file.

 

Welcome to the California Public Utilities Commission (CPUC) website for the California Environmental Quality Act (CEQA) review of Pacific Gas and Electric Company’s (PG&E’s) proposed Fulton-Fitch Mountain Reconductoring Project (project). PG&E submitted an application to the CPUC for a Permit to Construct (PTC) for the project on December 3, 2015. This site provides access to public documents and information relevant to the CEQA environmental review process.


QUICK LINKS

Background

Project Overview

Proponent's Environmental Assessment

Environmental Document

Public Meetings, Questions, and Comments


Background

PG&E proposes to reinforce the electric transmission system in central Sonoma County by replacing the conductor on a 9.9-mile-long section of the Fulton-Hopland 60 kV Power Line (Fulton-Hopland line) between the Fulton Substation and Fitch Mountain Substation. The project would include replacing poles along 8.1 miles of the Fulton-Hopland line, replacing conductor on 1.3 miles of the Geysers #12-Fulton 230 kV Transmission Line (Geysers #12-Fulton line), and making modifications to Fitch Mountain Substation.

The proposed project is subject to CEQA review because the CPUC has been presented with a discretionary action to approve or deny PG&E’s PTC application. Before making a decision about PG&E’s application, the CPUC is required to analyze potential environmental impacts associated with the project and present the findings in an environmental document for public review and comment. This website provides access to public documents and information relevant to the CEQA review process.

Project Overview

The 9.9-mile-long project alignment is comprised of the Southern Segment (1.8 miles), Northern Segment (8.1 miles), and Fitch Mountain Substation. Proposed project components at each location are summarized as follows:
  • Southern Segment/Fulton-Shiloh Segment. Replace 1.8 miles of 60 kV conductor and 1.3 miles of 230 kV conductor collocated on existing tubular steel poles (TSPs). Insulators on the TSPs would be replaced, but the poles would remain in place. 
  • Northern Segment/Shiloh-Fitch Segment. Replace 8.1 miles of 60 kV conductor located on primarily wood poles. Approximately 70 existing poles would be replaced at a roughly 1-to-1 ratio with approximately 59 light duty steel poles (LDSPs) and 7 TSPs. New poles would be between 3 to 30 feet taller than existing poles, depending on the pole location.
  • Fitch Mountain Substation Modifications. Modify the existing substation by replacing motor switches, control building, conductor, and conductor support structures to accommodate the higher rated conductor that would be installed for the Fulton-Hopland line.  

Application and Proponent's Environmental Assessment

PG&E filed an Application (A.15-12-005) for a PTC which included a Proponent's Environmental Assessment (PEA) for the project on December 3, 2015. The PEA is a starting point for the independent environmental review process conducted by the CPUC.

Deficiency Reports and Data Needs

The CPUC submitted Deficiency Reports to PG&E requesting specific information that was not included with the Application or PEA. PG&E addressed comments and provide material identified in the Deficiency Reports, and CPUC deemed the Application was complete on April 29, 2016. The Application and PEA can be viewed here. The Application completeness letter can be viewed here. Deficiency Reports for the project and PG&E’s responses are summarized in the following table.

The CPUC will submit Data Needs requests to PG&E as necessary during the environmental review process to support the preparation of an environmental document. Data Needs for the project and PG&E’s responses are summarized in the following table.

CPUC Deficiency Report
PG&E Response and Status
Deficiency Report #1
(December 23, 2015)

Response #1 (January 22, 2016)
*
Table of Responses #1
Attachment PD-08: Revised Typical Structure Drawings
Attachment AQ/GHG-01: Air Quality and Greenhouse Gas Calculations
Attachment HHM-01: EDR Report
Attachment LUP-01: New Affected Properties Spreadsheet

Response #1A (January 25, 2016)*

Letter #1A
Attachment PD-06: Detailed Workspaces and Facility Locations (Confidential)
Attachment PD-07: Structure Locations, Details, and Unique IDs (Confidential)
Attachment PD-09: Substation Modifications (Confidential)
Attachment PD-11: Staging Areas (Confidential)
Attachment PD-12: Access Roads and Footpaths (Confidential)
Attachment PD-14: Vegetation Clearance (Confidential)
Attachment BR-01: Wetland Delineation Report (Confidential)
Attachment BR-02: Biological Survey Reports (Confidential)
Attachment C/PR-01: Cultural Resources Report (Confidential)
Attachment C/PR-02: Paleontological Report (Confidential)

Response #1B (January 29, 2016)

Letter #1B
Attachment: Detailed Map Book (Confidential)
Attachment: Existing General Arrangement Plans (Confidential)

Response #1C (February 5, 2016)

Email #1C
Attachment: Project Map

Response #1D (February 26, 2016)
Attachment: Detailed Project Map

Response #1E (July 8, 2016)
Letter #1E
Attachment: Cultural Survey Memo (Confidential)
Attachment: Biology Addendum (Confidential)


Deficiency Report #2
(February 19, 2016)


Response #1 (March 18, 2016)
Table of Responses #1

Response #2 (April 1, 2016)
Attachment: Preliminary Helicopter Use Plan

Response #3 (April 22, 2016)
Attachment: DRAFT Delineation of Waters of the United States (Confidential)


Deficiency Report #3
(April 7, 2016)

Response #1 (April 26, 2016)
Letter #1
*Attachment numbers correspond to the Deficiency Request ID number.

CPUC Data Needs
PG&E Response and Status
Data Needs #1
(June 9, 2016)
Response #1 (July 8, 2016)
Table of Responses #1
Summary of Project Emissions: Air Quality, Greenhouse Gas
Helicopter Emissions Calculations: Air Quality, Greenhouse Gas
SF6-Insulated Breaker Emissions: Greenhouse Gas
Construction Equipment List
Response Pending

Environmental Document

The CPUC will prepare an environmental document in compliance with CEQA. The Draft and Final environmental documents will be published here when they are available.

Public Meetings, Questions, and Comments

Public Meetings

Date/Time
Location Description
Meeting Materials
Wednesday, August 24, 2016
6:30 PM  -  8:00 PM
Windsor Community Center
9291 Old Redwood Highway, Building 200
Windsor, CA 95492
The CPUC, as lead agency under the California Environmental Quality Act (CEQA), will hold an informational meeting for the public, to describe PG&E’s proposed project and the CEQA process.
Meeting Notice
Fact Sheet


Questions and Comments

Questions about the scope of the project or the environmental review process may be submitted to the CPUC’s environmental team through the email address or fax number provided below. A formal comment period will commence once the CPUC releases the Draft environmental document. Comments submitted during the formal comment period, will be addressed in the Final environmental document, as required by CEQA.

To receive updates on the progress of the project, please send a request to be added to the project mailing list using the email address or fax number provided below.

Comments submitted during the formal comment period should include a name, address, and telephone number of a contact person for any future correspondence. Individual respondents may request that their names and contact information be withheld from public review by prominently stating such at the beginning of each written comment. Such requests will be honored to the extent allowed by law. All submissions from organizations and businesses, and from individuals identifying themselves as representatives or officials of organizations or businesses, will be made available for public review in their entirety. Anonymous comments will not be considered. Comments may be submitted by email, fax, or U.S. mail.

Email

fulton2fitch@panoramaenv.com

Fax

(650) 373 - 1211

CPUC Project Manager
Mailing Address

Lisa Orsaba
California Public Utilities Commission
505 Van Ness Ave, 4th Floor
San Francisco CA , 94102

Formal Comment
Mailing Address

California Public Utilities Commission
Attn: Fulton-Fitch Mountain
c/o Panorama Environmental, Inc.
1 Embarcadero Center, Suite 740
San Francisco, CA, 94111


Related Links:
CPUC Proceeding
A.15-12-005 - Proceeding


This page contains tables and is best viewed with Netscape or Internet Explorer. Please report any problems to the Energy Division web coordinator.