CALIFORNIA PUC > Energy > Transmission and Environmental Review > Current Projects Pacific Gas & ElectricSanta Cruz 115kV Reinforcement Project(Application No. A.12-01-012)Last Update: September 3, 2014 NOTE: Linked files presented on this page are in PDF format. To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your computer. For faster results in displaying the larger files, right-click the file's link, click "Save Target As" to download the file to your hard drive, then double-click the downloaded file. |
Welcome to the California Public Utilities Commission (CPUC) website for the California Environmental Quality Act (CEQA) review of Pacific Gas and Electric Company’s (PG&E’s) proposed Santa Cruz 115 kV Reinforcement Project (Project). PG&E submitted an application to the CPUC for a Permit to Construct (PTC) this project on January 25, 2012. This site provides access to public documents and information relevant to the CEQA environmental review process. QUICK LINKSProponent's Environmental Assessment (PEA) Additional Data Requests (Update: Additional Response to Data Request #8 added September 3, 2014) Upcoming Public MeetingsPublic MeetingNone scheduled at this time. Administrative Law Judge's Prehearing ConferenceThe Administrative Law Judge
held a prehearing conference for the Santa Cruz 115-kV Reinforcement
Project on June 11, 2013 at the Commission To find out how you can participate in the Permit to Construct Proceeding for the Santa Cruz 115-kV Reinforcement Project, please register your interest by contacting the public advisor office: http://www.cpuc.ca.gov/PUC/aboutus/Divisions/CSID/Public+Advisor/ BackgroundThe proposed Project would increase transmission system reliability in the Santa Cruz area during outages. The project will add a second 115 kV circuit between Green Valley Substation and Rob Roy Substation to prevent potential large-scale service interruptions if there are overlapping outages in the existing local electricity supply system. The proposed project includes converting the existing 7.1 miles of single-circuit 115 kV power line to a double-circuit 115 kV power line by replacing existing wood poles with tubular steel poles (TSPs); constructing a new, approximately 1.7-mile-long single-circuit 115 kV power line connecting the Green Valley-Camp Evers 115 kV Power Line to Rob Roy Substation; and modifying the existing Rob Roy Substation and existing power lines to accommodate the new circuit. The new circuit will provide two sources of power in the event of an outage on either the southern line between Green Valley Substation and Rob Roy Substation or on the existing northern line between Green Valley Substation and Camp Evers Substation. Project DescriptionThe
project is located in southern Santa Cruz County,
California near the cities of Watsonville and Aptos. The project
traverses an
area of rolling terrain, including agricultural valleys and grassland,
as well
as low ridgelines forested with mature trees. The predominant
development
pattern throughout the project area is a mix of low-density
residential, open
space, and agricultural land uses. The agricultural areas are
predominantly
apple orchards, berry orchards, livestock pastures, and row crops.
Proponent's Environmental Assessment (PEA)PG&E filed an application (A. 12-01-012) for a Permit to Construct and the Proponent's Environmental Assessment on January 25, 2012. The PEA is a starting point for the independent environmental review process conducted by the CPUC. The application and PEA can be viewed here: Application (6.6 MB) PEA (25.7 MB) The Declarations of Mailing and Posting of Supplemental Notice of an Application for a Permit to Construct can be viewed here (9 MB). Additional Data RequestsThe CPUC submitted additional data requests regarding PG&E's application. The data requests and PG&E's responses can be viewed below. Data Request #8 and Response, Supplemental Reponse, and Additional Response Data Request #9, Response, and Supplemental Response Data Request #10 and Response and Supplemental Response Environmental ReviewPG&E’s
Application and PEA were deemed
complete by
the CPUC on April 24, 2012. Draft Initial Study/Mitigated Negative DeclarationOn October 18, 2013 the CPUC released a Notice of Intent to Adopt a MND/Notice of Availability (NOI/NOA) for the Santa Cruz 115kV Reinforcement Project, showing that the proposed project, as mitigated, would not have any significant effects on the environment. The Draft IS/MND was available for a 45-day public review period. The Draft was released on October 18, 2013. The comment period was extended by an additional 4 days and comments were accepted through 5:00 p.m. on December 6, 2013. The Draft IS/MND can be viewed here. Public MeetingA public information meeting to accept comments on the Draft IS/MND was held on November 6, 2013. Documents that were presented at the meeting are available below. Public Meeting Presentation (44 MB)Project Map Book (58 MB) Project Visual Simulations Book (176 MB) Sign-in Sheet (0.5 MB) Environmental Impact ReportAfter review of comments received on the Draft IS/MND, the CPUC determined that an Environmental Impact Report (EIR) should be prepared in accordance with CEQA. Notice of Preparation and Scoping PeriodThe CPUC published a Notice of Preparation (NOP) of an Environmental Impact Report (EIR) for the proposed project on January 17, 2014. Click here to review the NOP. The CPUC accepted comments on the scope of the Draft EIR during the 30-day scoping period that ended on February 18, 2014. The comments received during the Draft IS/MND comment period are also being considered during the preparation of the EIR. Comments on the Draft IS/MND and EIR scoping comments are available below.Comments on the Draft IS/MND (24 MB) Comments on the Scope of the EIR (21 MB) Public Scoping MeetingThe CPUC held a public meeting on January 29, 2014, in order for the public and regulatory agencies to become informed about and submit comments on the scope of the EIR. Click the following links to view the public meeting presentation and meeting transcript. Scoping Meeting Presentation (2 MB)Scoping Meeting Transcript (0.5 MB) Scoping ReportA Scoping Report has been prepared to describe the CEQA scoping process and to document all comments received on the Santa Cruz 115-kV Reinforcement Project. Click the link below to access the Scoping Report.Scoping Report For Additional InformationAdditional information will be posted at this site as it becomes publically available. The CPUC, through its Environmental Review Team, is conducting an environmental review of the project. To request additional information, ask a question, or be added to the project mailing list, please contact:
|
|
||||||||||
|
|||||||||||