STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

Pacific Gas and Electric Company
Santa Cruz 115kV Reinforcement Project

Pacific Gas and Electric Company
Application No. 12-01-012

Filed January 25, 2012



Welcome to the California Public Utilities Commission (CPUC) website for the California Environmental Quality Act (CEQA) review of Pacific Gas and Electric Company’s (PG&E’s) proposed Santa Cruz 115 kV Reinforcement Project (Project). PG&E submitted an application to the CPUC for a Permit to Construct (PTC) this project on January 25, 2012. This site provides access to public documents and information relevant to the CEQA environmental review process.

Background

The proposed Project would increase transmission system reliability in the Santa Cruz area during outages. The project will add a second 115 kV circuit between Green Valley Substation and Rob Roy Substation to prevent potential large-scale service interruptions if there are overlapping outages in the existing local electricity supply system. The proposed project includes converting the existing 7.1 miles of single-circuit 115 kV power line to a double-circuit 115 kV power line by replacing existing wood poles with tubular steel poles (TSPs); constructing a new, approximately 1.7-mile-long single-circuit 115 kV power line connecting the Green Valley-Camp Evers 115 kV Power Line to Rob Roy Substation; and modifying the existing Rob Roy Substation and existing power lines to accommodate the new circuit.

The new circuit will provide two sources of power in the event of an outage on either the southern line between Green Valley Substation and Rob Roy Substation or on the existing northern line between Green Valley Substation and Camp Evers Substation.  


Project Description

The project is located in southern Santa Cruz County, California near the cities of Watsonville and Aptos. The project traverses an area of rolling terrain, including agricultural valleys and grassland, as well as low ridgelines forested with mature trees. The predominant development pattern throughout the project area is a mix of low-density residential, open space, and agricultural land uses. The agricultural areas are predominantly apple orchards, berry orchards, livestock pastures, and row crops.

The primary project components are summarized below:
    1. Northern Alignment – approximately 7.1 miles of an existing single-circuit 115 kV power line will be converted to a double-circuit 115 kV power line by replacing existing wood poles with TSPs.

    2. Cox-Freedom Segment - a new, approximately 1.7-mile-long single-circuit 115 kV power line connecting the Green Valley-Camp Evers 115 kV Power Line to Rob Roy Substation will be constructed in an existing distribution line alignment by installing new poles and collocating some existing distribution facilities.

    3. Rob Roy Substation Modifications - the existing substation will be modified to accommodate the new circuit.

    4. Rob Roy Substation Connections – one new TSP will be installed and two existing power poles will be replaced with TSPs to accommodate the interconnection of existing power lines following modification of Rob Roy Substation.


Proponent's Environmental Assessment (PEA)

PG&E filed an application (A. 12-01-012) for a Permit to Construct and the Proponent's Environemtal Assessment on January 25, 2012. The PEA is a starting point for the independent environmental review process conducted by the CPUC.

The application and PEA can be viewed here:  Application (6.6 MB)   PEA (25.7 MB)  

The Declarations of Mailing and Posting of Supplemental Notice of an Application for a Permit to Construct  can be viewed here (9 MB).

Additional Data Requests

The CPUC submitted additional data requests regarding PG&E's application. The data requests and PG&E's responses can be viewed below. 

Data Request #1 and Response

Data Request #2 and Response

Data Request #3 and Response

Data Request #4 and Response

Data Request #5 and Response

Data Request #6 and Response

Environmental Review

PG&E’s Application and PEA were deemed complete by the CPUC on April 24, 2012. 

Draft Initial Study/Mitigated Negative Declaration

The CPUC has determined that an Initial Study/Mitigated Negative Declaration (IS/MND) appears to be the appropriate CEQA document to prepare for this Project.  The Draft IS/MND is currently under preparation.

For Additional Information

Additional information will be posted at this site as it becomes publically available. 

The CPUC, through its Environmental Review Team, is conducting an environmental review of the project. To request additional information, ask a question, or be added to the project mailing list, please contact: 

Voicemail or Fax

(650) 373 - 1200

U.S. Mail or Courier

Lisa Orsaba
California Public Utilities Commission
505 Van Ness Ave, 4th Floor
San Francisco CA , 94102

c/o Panorama
1 Embarcadero Center, Suite 740
San Francisco, CA, 94111

Email

santacruz115kvproject@panoramaenv.com

This page contains tables and is best viewed with Netscape or Internet Explorer. Please report any problems to the Energy Division web coordinator.