Background Decisions and Information
on QF Issues
Resolution
E-3645: November 4, 1999
SCE-Delano QF Contract Restructuring Agreement.
On July 7, 1999, SCE filed Advice Letter 1390-E, requesting Commission
approval of a QF contract restructuring with Delano Energy Company, Inc.,
pursuant to the RALF guidelines laid out in D.98-12-066. Approved.
Decision
99-10-016: October 4, 199
PG&E-San Joaquin Cogen QF Contract Termination Agreement.
PGE&E had filed Application 99-04-009 for Commission approval of the
termination of Standard Offer No.2 Power Purchase between PG&E and San
Joaquin Cogen Limited, L.P. This decision approves the Termination
Agreement between PG&E and San Joaquin Limited.
Resolution
E-3635: September 2, 1999
SCE-Beowawe QF Contract Restructuring Agreement.
On May 20, 1999, SCE filed Advice Letter 1381-E, requesting Commission
approval of a QF contract restructuring with Oxbow Power of Beowawe, Inc.,
pursuant to the RALF guidelines laid out in D.98-12-066 (see
"Background Decisions and Information" page). Approved.
Decision
99-08-008: August 5, 1999
SCE-AES Placerita QF Contract Restructuring Agreement.
On May 5, 1999, SCE filed Application 99-05-006 seeking Commission
approval of agreements restructuring the PPA between SCE and AES Placerita.
Approved.
Resolution
E-3625: August 5, 1999
PG&E Enabling Agreement for greater QF operating flexibility.
On June 12, 1999, PG&E filed Advice Letter 1870-E, requesting
Commission approval of two standard forms modifying standard offer
contracts. The forms, for which individual QFs are eligible, give QFs
greater operational latitude to participate in energy and ancillary
services markets. Approved.
Decision
99-05-049: May 27, 2000
SCE-O'Brien QF Contract Restructuring Agreement.
On December 18, 1998, SCE filed Application 98-12-021. This decision
approves SCE's proposed buyout and termination of a 1985 power purchase
agreement with O'Brien California Cogen Limited (O'Brien). Expected
customer benefits from the buyout are $13.7 million in net present value (NPV).
The decisions finds the settlement embodied in the agreement to be
reasonable.
Decision
99-03-021: March 4, 1999
This decision denies SDG&E’s request to modify transmission line
loss adjustment factors, stating that SDG&E has not adequately
demonstrated that these factors no longer reflect avoided line
losses, or that the alternative generator meter multipliers (GMMs)
proposed by SDG&E are more appropriate to use for short-run avoided
cost calculations. SDG&E’s proposal to modify its distribution
line loss adjustment factors is approved.
Decision
99-02-085: February 18, 1999
The main issues addressed are: (1) the standard of reasonableness
the Commission applies to QF contract restructuring; (2) whether QF
contract restructurings should be voluntary for both the utility and the
QF; (3) whether a utility’s decisions in QF restructuring negotiations
should be subject to reasonableness review; (4) whether to retain and how
to implement the 10% shareholder incentive to renegotiate QF contracts.
Decision
98-12-072: December 17, 1998
This decision approves as reasonable a package of settlements with certain
bidders in the Biennial Resource Plan Update (BRPU) auction proposed by
SCE in an application. The cost of the total package of ten
settlements is $92,142,163.
Decision
98-12-074: December 17, 1998
This decision approves as reasonable a package of settlements with certain
bidders in the Biennial Resource Plan Update (BRPU) auction proposed by
SDG&E in an application. The cost of the total package of three
settlements is $5,095,000. SDG&E’s request to terminate its
BRPU solicitation is deferred, and SDG&E is encouraged to continue
negotiating with non-settling bidders.
Decision
98-12-066: December 17, 1998
This decision adopts a process to address certain QF contract modification
proposals in the instances where the restructuring Advice Letter has the
support of the Office of Ratepayer Advocates. Under the expedited
process, the utility would submit a Restructuring Advice Letter Filing
(RALF) to the Commission’s Energy Division. Energy Division staff
will, after a review and public comment period, submit for Commission vote
a resolution either accepting or rejecting the proposed contract
restructuring.
Decision
98-04-046, April 23, 1998 Energy Reliability Index (ERI)
Decision
97-11-013, November 5, 1997 Opinion on As-Available Capacity Payments.
Decision
96-12-028, December 9, 1996 Interim Opinion Replacing the Index
Methodology for Calculating Avoided Energy Costs.
Decision
96-10-036, October 9, 1996 Phase 1 Opinion, ,
on approval of a compromise proposal (Joint Recommendation) which proposes
to resolve all Phase 1 issues in the consolidated applications.
For More Information on QF Issues from the Energy
Division
Contact James Loewen, Energy Division, at
415-703-1866, or by email at loe@cpuc.ca.gov.