April 21, 1998

Administrative Law Judge Janet Econome

California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102

Re:

Extension of Time to File Reply Comments Regarding Qualifying Facilities Restructurings or Modifications

Dear Judge Econome:

This letter confirms that on April 21, 1998, pursuant to Rule 48 (a) of the Rules of Practice and Procedure of the California Public Utilities Commission, you granted Southern California Edison Company, Pacific Gas and Electric Company, San Diego Gas and Electric Company, and all other interested parties an extension of time to file replies to comments on the issues raised in the Commissioner Neeper/ALJ Econome Joint Ruling dated February 6, 1998.

Thus, Reply Comments (including requests for closing argument) are due on April 29, 1998. Further, under the revised schedule, a Proposed Decision will be due no later than July 29, 1998.

Thank you for your consideration of this matter.

Very truly yours,

Russell C. Swartz

RCS:jbw:LW981110.062

cc: All Parties of Record in R.94-04-031/I.94-04-032

Electric RestructuringQualifying Facility Issues Transition CostsElectric Restructuring DecisionsDirect Access & Retail Competition Rates & Tariffs Electric Service Providers Reliability


Current Issues By Industry
Current Issues in the Electric IndustryCurrent Issues in the Environmental IndustryCurrent Issues in the Gas IndustryCurrent Issues in the Telecommunication Industry