Southern California Edison's
Tehachapi Renewable Transmission Project

(Application A.07-06-031, filed June 29, 2007)

   
 

   
Compliance Plans
Plan Report Title

Mitigation Measure(s) and APM(s)

Required to Initiate Construction

Fugitive Dust Emission Control Plan (FDECP)

AQ-1a, APM AQ-7

Yes

Habitat Restoration and Revegetation Plan

B-1a

Yes

Riparian Conservation Areas Treatment Plan

B-2

Yes

Weed Control Plan

B-3a

Yes

Pre-construction surveys for nesting birds

B-5

Yes

Protocol surveys for rare plants

B-7

Yes

Protocol surveys for California red-legged frogs

B-8a

Yes

Biological Monitoring

B-8b

No

Protocol surveys for Arroyo Toads

B-9

Yes

Protocol surveys for Desert Tortoise

B-10

Yes

Hazardous Material Spill kit(s)

B-12

Yes

Protocol surveys for listed riparian birds

B-15

Yes

Focused surveys for coastal California Gnatcatcher

B-16

Yes

Pre-construction surveys for Swainson's Hawks

B-18a

Yes

Protocol surveys for Mohave ground squirrel

B-22a

Yes

Construction Monitoring for Mohave ground squirrel

B-22b

Yes

Focused presence/absence surveys for Southwestern pond turtles

B-24

Yes

Focused surveys for two-striped garter snakes and south coast garter

B-25

Yes

Focused surveys for Coast Range newts

B-26

Yes

CDFG protocol for burrowing owls (Implement)

B-29

Yes

Pre-and during construction nest surveys for spotted owl

B-30

Yes

Maternity colony or mibernaculum surveys for roosting bats

B-33a

Yes

Focused surveys for San Diego Desert woodrat

B-36

Yes

Focused surveys for ringtail

B-37

Yes

Focused surveys for American badgers

B-38

Yes

Programmatic Agreement - Cultural Resources

C-1a

Yes

Inventory Cultural Resources Report

C-1b

Yes

Historic Properties Treatment Plan (HPTP)

C-1e

Yes

Long-term plan for NRHP-eligible sites

C-1i

No

Phase I Environmental Site Assessments (ESAs)

E-2a

Yes

Phase II Environmental Site Investigations (ESIs)

E-2b

Yes

Health and Safety Plan and Gas Monitoring Program

E-3b

Yes

Plans of access roads required to construct Route C, Route C Modified, or Route D

E-6b

Yes

Plan to avoid or minimize interference with oil field operation

G-1

Yes

Geological surveys for landslides

G-3

Yes

Report to avoid the placement of project structures on active fault traces

G-4

Yes

Geotechnical Investigation for groundshaking

G-5a

Yes

Geotechnical Investigation for liquefaction

G-5b

Yes

Geotechnical studies for potentially detrimental soil chemicals

G-6

Yes

Geotechnical analysis of settlement potential

G-9

Yes

Erosion Control Plan

H-1a

Yes

Monitoring of all wet-weather coordination with the FS

H-1b

Yes

SCE Transmission Line Fire Plan

PSU-1a

Yes

Traffic Control Plans (TCP)

T-1a, T-1b

Yes

Construction Transportation Plan (CTP)

T-2

Yes

Wildland Traffic Control Plans

F-1a

Yes

Fire Management Plan

F-3a

Yes

Emergency Evacuation Plan

F-4a

Yes

Phase I Environmental Site Assessment (ESA)

APM HAZ-1

Yes

Soil Management Plan

APM HAZ-2

Yes

Spill Prevention, Countermeasure, and Control Plan and Hazardous Materials Business Plan

APM HAZ-5

Yes

Construction SWPPP

APM HYD-1

Yes

Operation Storm Water Management Plan (SWMP)

APM HYD-8

Yes

Fire Management Plan

PSU-1, APM HAZ-4

Yes

Traffic Management Plan

APM TRA-4

Yes

Substations - Landscape Plan

APM AES-23

Yes

Construction Monitoring and Unanticipated Cultural Resources Discovery Plan

APM CR-2b

Yes

   