Permit
|
Issue Date
|
Description
|
USFWS Biological Opinion
|
July 31, 2010
|
|
USFWS Biological Opinion Amendment No. 1
|
January 13, 2012
|
Change of impacts to California Gnatcatcher and Least Bell's Vireo
habitat due to ingressing/egressing of TRTP related vehicles on
well-used public roads and the increase in impact to LBVI habitat
(permanently and temporarily).
|
USFWS Biological Opinion Amendment No. 2
|
August 20, 2013
|
Change of impacts to California Gnatcatcher habitat along Segment
8 and clarification on use of developed/barren areas within designated
critical habitat.
|
USFWS Biological Opinion Amendment No. 3
|
June 20, 2014
|
Change of impacts to Least Bell's Vireo habitat along Segment 8
specifically within the Chino Hills area of the TRTP project.
|
USFWS Biological Opinion Amendment No. 4
|
October 30, 2014
|
CRLF Seasonal Restriction Modification for Wire Stringing Activities
|
USFWS Biological Opinion Amendment No. 5
|
October 29, 2015
|
Allow restoration activities to take place within CRLF restriction
areas until November 15, 2015.
|
USFWS Biological Amendment No. 6
|
February 2, 2016
|
Increase in temporary Impacts to coastal California gnatcatcher
occupied habitat by 0.14 acre, and decrease of in permanent habitat
impacts by 0.07 acre. Repair of erosion at Segment 11 Tower 18 between
February 1 and 15, during California red-legged frog exclusion
season.
|
USFWS Biological Opinion Clarification No. 1
|
February 21, 2012
|
Clarification on BMP inspection and maintenance at Montebello Hills
SRA
|
USFWS Biological Opinion Clarification No. 2
|
June 19, 2012
|
Clarification to Conservation Measure 6 (Least Bell's Vireo)
and Conservation Measure 9 (CA gnatcatcher) related to survey
and monitoring requirements.
|
USFWS Biological Opinion Clarification No. 3
|
December 13, 2012
|
Segment 6 ARTO Monitoring Crossings - ANF and SCE requesting clarification
of Conservation Measure 9, Bullet 5, (Page 14) pertaining
to arroyo toad monitoring at road crossings during the dry, non-breeding
season.
|
USFWS Biological Opinion Modification No. 1
|
November 8, 2012
|
Approval of Modification of ARTO Seasonal Restriction Time frame
for 2012
|
USFWS Biological Opinion Modification No. 2
|
March 31, 2014
|
ARTO and CRLF seasonal restriction changes in support of restoration
efforts including manual weed removal, herbicide application and
ground disturbing restoration activities.
|
USFWS Biological Opinion Clarification No. 4
|
January 23, 2015
|
Segment 11C CRLF SRA - Request to Conduct Jumper Loop Removal/Reinstallation
Activities
|
CDFW Incidental Take Permit
|
November 15, 2010
|
|
CDFW Incidental Take Permit Amendment No. 1
|
June 1, 2011
|
- Changes the allowed work schedule from "7:00 a.m. to 5 p.m."
to "daylight hours".
- Limits vegetation removal restriction described in ITP Condition
8.3.2 to within 0.5 miles of a Swainson's hawk nest, rather than
limiting all vegetation removal activities during the general
avian nesting season.
- Allows for an alternative desert tortoise exclusion fence design
with written approval from DFG.
|
CDFW Incidental Take Permit Amendment No. 2
|
September 18, 2012
|
- Change in contact person for ITP.
- Recalculates impacts to Riparian Birds and updated surveys
of Riparian birds.
- Inserts a new Condition 7.10 to require notification for any
Covered Species observed during Covered Activities.
- Changes Conditions 8.4: (1) modify survey requirements;and
(2) provide for procedural changes, when appropriate, to reduce
standard, effective buffers based on physical site characteristics
or land ownership where access prohibits conventional surveys.
- Extends the date to complete mitigation for Covered Species
to January 15, 2013 for Desert Species, and July 15,
2013 for Riparian Birds and Swainson's hawk.
|
CDFW Incidental Take Permit Amendment No. 3
|
July 22 2014
|
- Change in contact person for ITP.
- Modifies the scope of the ITP to address impacts to least Bell's
vireo and willow flycatcher from covered activities in 500kV UG.
- Increases impacts to occupied least Bell's vireo habitat.
- Decreases the desert tortoise and Mohave ground squirrel mitigation
obligation based on a reduction of Project impacts that were originally
authorized.
- Authorizes horizontal directional drilling subject to certain
conditions.
- Modifies the acreage requirements and acquisition costs for
habitat management lands, modifies the amount of time allotted
to the Permittee in fulfilling the compensatory mitigation obligation,
and seeks to coordinate Permittee's acquisition of certain habitat
management lands with development of the Petersen Ranch Mitigation
Bank.
- Clarifies the location of annual protocol surveys.
|
CDFW Incidental Take Permit Modification No. 1
|
November 9, 2011
|
WP1 - Impact acreage for Mohave Ground Squirrel, Desert Tortoise
and Swainson's Hawk.
|
CDFW Incidental Take Permit Modification No. 2
|
November 17, 2011
|
WP1 - Impact acreage for Southwestern Willow Flycatcher and Least
Bell's Vireo.
|
CDFW Incidental Take Permit Modification No. 3
|
February 17, 2012
|
WP1 - Implement site clean-up, rehabilitation and close out subsequent
to the removal of desert tortoise-proof exclusion fencing
|
CDFW Incidental Take Permit Modification No. 4
|
March 26, 2012
|
WP1 - Implement the addition of anchor weights on Segment 10 Construct
9 subsequent to the removal of desert tortoise-proof exclusion fencing
|
CDFW Incidental Take Permit Modification No. 5
|
September 4, 2012
|
WP2 - Segment 6 final HMMP due date extended
|
CDFW Incidental Take Permit Clarification No. 1
|
September 16, 2012
|
WP3 - Least Bell's Vireo Survey methodology and notification clarified
|
CDFW Incidental Take Permit Modification No. 6
|
December 4, 2012
|
WP1 - Provides concurrence from CDFG for extended work hours between
civil twilight time (civil dusk and dawn) for construction activities
within Segments 4, 5, and 10.
|
CDFW Incidental Take Permit Modification No. 7
|
February 1, 2013
|
WP1 - Telecom Slicing after Desert Tortoise Fencing removed
|
CDFW Incidental Take Permit Modification No. 8
|
March 15, 2013
|
WP3 - Annual and protocol surveys not conducted due to access issues,
specifies construction activities allowed to access Tonner Canyon
|
CDFW Incidental Take Permit Modification No. 9
|
April 22, 2013
|
WP3 - Annual and protocol surveys not conducted due to access issues,
BMP Removal allowed to access Tonner Canyon
|
CDFW Incidental Take Permit Modification No. 10
|
April 26, 2011
|
WP1 - Desert Tortoise proposed Exclusionary Fencing Alternative
Materials Fencing
|
CDFW Incidental Take Permit Modification No. 11
|
May 12, 2011
|
WP4 - Proposed Nighttime Concrete Pour for the Whirlwind Substation
|
CDFW Incidental Take Permit Modification No. 12
|
May 16, 2011
|
WP4 - Proposed Nighttime Transformer Delivery for the Whirlwind
Substation
|
CDFW Incidental Take Permit Modification No. 13
|
March 8, 2012
|
WP1 - Request for additional activity proposed for site close out
within suitable desert tortoise habitat areas subsequent to the
removal of desert tortoise exclusionary fencing
|
CDFW Section 1602 Segments 2 and 3 - Windhub Substation
|
April 15, 2009
|
|
CDFW Section 1602 Segments 2 and 3 - Segment 3B
|
August 27, 2012
|
|
CDFW Section 1602 Segments 7 and 8
|
February 16, 2011
|
|
CDFW Section 1602 Segments 7 and 8 Amendment 1
|
July19, 2011
|
Add one additional stream crossing resulting in an additional 346
linear feet of jurisdictional streams and two oak trees under the
department's jurisdiction
|
CDFW Section 1602 Segments 7 and 8 Amendment 2
|
April 13, 2012
|
Add changes at 23 locations of TRTP affecting 12 jurisdictional
streams
|
CDFW Section 1602 Segments 7 and 8 Amendment 3
|
July 5, 2013
|
Add changes at one location (M27-T3) resulting in
additional impacts of 0.02 acre of permanent and 0.04 acre of temporary
impacts
|
CDFW Section 1602 Segments 7 and 8 Amendment 4
|
June 23, 2014
|
Add impacts to eight jurisdictional drainages due to the Chino
Hills Undergrounding decision by the CPUC
|
CDFW Section 1602 Segments 7 and 8 Amendment 5
|
August 5, 2014
|
Allowed engineered erosion repairs at M27-T3 resulting
in new minor impacts to feature 7-3-S-9
|
CDFW Section 1602 Segment 11C
|
October 22, 2013
|
|
CDFW Section 1602 Segment 11C Amendment 1
|
December 17, 2014
|
Minor amendment to allow construction of a new McCarthy drain in
a non-riparian ephemeral drainage (11-5-S-2) located within the
Angeles National Forest below the access road to Structure M31-T3
on TRTP Segment 11C.
|
CDFW Section 1602 Segment 6
|
October 31, 2011
|
|
CDFW Section 1602 Segment 6 Amendment 1
|
January 3, 2013
|
Amend the agreement to address 34 changes in existing conditions
along the project alignment due to USFS winter road maintenance,
new features and changes project design
|
CDFW Section 1602 Segments 4, 5, and 10
|
December 27, 2010
|
|
CDFW Section 1602 Segment 9
|
January 24, 2011
|
|
USACE Section 404 Segment 11
|
October 15, 2013
|
|
USACE Section 404 Segment 11 Deviation Request
|
December 3, 2014
|
SCE utilized contingency acreage for the NWP Authorization (SPL-2013-00314-SLP);
therefore, no permit amendment was warranted
|
USACE Section 404 Segment 6
|
August 31, 2011
|
|
USACE Section 404 Segment 6 Permit Verification
|
March 15, 2013
|
Additional temporary and permanent impacts to waters of the U.S.
|
USACE Section 404 Segments 4, 5, and 10
|
January 19, 2011
|
|
USACE Section 404 Segments 7 and 8
|
August 5, 2011
|
|
USACE Section 404 Segments 7 and 8 Verification 1
|
April 4, 2012
|
Additional temporary and permanent impacts to waters of the U.S.
due to final engineering
|
USACE Section 404 Segments 7 and 8 Verification 2
|
July 31, 2013
|
Temporary and permanent impacts to one jurisdictional drainage
near M27-T3
|
USACE Section 404 Segments 7 and 8 Verification 3
|
June 25, 2014
|
Temporary and permanent impacts to waters of the U.S. resulting
from the Chino Hills 500kV Underground activities
|
SWRCB Section 401 Segment 6
|
August 23, 2011
|
|
SWRCB Section 401 Segment 6 Permit Reissuance
|
March 7, 2013
|
Additional temporary and permanent impacts to waters of the U.S.
|
SWRCB Section 401 Segment 11
|
October 7, 2013
|
|
SWRCB Section 401 Segment 11 Permit Deviation Approval
|
March 27, 2015
|
Mac Drain installation at Construct 6
|
SWRCB Section 401 Segments 4, 5, and 10
|
January 24, 2011
|
|
SWRCB Section 401 Segments 4, 5, and 10 Administrative Amendment
|
January 4, 2012
|
Modification of mitigation strategy
|
SWRCB Section 401 Segments 7 and 8
|
December 24, 2010
|
|
SWRCB Section 401 Segments 7 and 8 Amendment 1
|
July 13, 2011
|
Covers the additional permanent impacts to an ephemeral drainage
near M57-T1
|
SWRCB Section 401 Segments 7 and 8 Permit Reissuance
|
April 4, 2012
|
Covers additional permanent and temporary impacts to U.S. and waters
of the State for construction at M24-T1 and M57-T1 and access roads
|
SWRCB Section 401 Segments 7 and 8 Permit Variance
|
July 25, 2013
|
Installation of a wet crossing in drainage near M27-T3
|
SWRCB Section 401 Segments 7 and 8 Amendment 2
|
May 23, 2014
|
Additional impacts related to construction and operation of the
Chino Hills 500 kV Underground alignment
|
SWRCB Section 401 Segment 9
|
March 23, 2011
|
|