Reorganization Agreement
¨Guarantees that the CPUC will deem prudent and recoverable all financing costs associated with the OCC/CPUC Plan
¨Creates a $1.75 billion regulatory asset to be amortized over 10 years
¨Requires CPUC to establish rates sufficient to
—pay interest and principal on securities issued under the OCC/CPUC plan
—pay prudently incurred operating and capital costs
—amortize Regulatory Asset
—achieve and maintain investment-grade credit ratings
¨Expressly waives CPUC’s sovereign immunity, allowing the Bankruptcy Court to enforce the Reorganization Agreement
—Reorganization Agreement will bind future commissions
Included in the OCC/CPUC Plan is a Reorganization Agreement that affirms the CPUC’s commitment to PG&E’s credit quality