|
SDG&E
|
PG&E
|
SCE
|
Functional Unbundling of Generation |
- Generation revenues will be derived in SDG&E's Generation PBR
- O&M and capital-related costs will be directly assigned to business functions
- Methods of assigning A&G, general plant and common plant expenses are described
|
- Presents discussion of "Physical" versus "Contractual" generation and the interaction with PX and ISO
- Describes a "mapping" approach for aggregated costs and allocation of shared costs
- Result is $5.1 billion (includes CTC, which will be identified in 8/30 filing)
|
- These costs are contained in SCE's July 15 PBR application
- Describes the mapping process that was used for direct, joint and common costs
|
Functional Unbundling of Transmission |
- Transmission revenues will be determined by the FERC and will be subtracted from total revenue requirements
- Implications of FERC and CPUC scenarios are discussed but no preference is stated
|
- Demarcation between transmission and distribution must be resolved
- Transmission will include revenue requirements for all facilities 60 kV and greater
- Result is $272 million
|
- Expects the revenue requirement for transmission will be authorized by FERC based on ISO Phase II filings in early 1997
- Proposes a revenue-credit methodology to separate FERC jurisdictional revenue requirements
|
Functional Unbundling of Distribution |
- Once the transmission revenue requirement is identified, it will be subtracted from the total T&D amount to obtain the distribution revenue requirement
|
- Estimated using a mapping approach
- Result is $1.7 billion
|
- Proposes to calculate by subtracting the FERC-adopted transmission revenue requirement from the non-PBR revenue requirement that the CPUC will adopt.
- More fully described in PBR proposal
|
Further Unbundling of Distribution Functions |
- Emphasizes that meaningful competition cannot be achieved so long as services are bundled
- Unbundling should occur by 1/1/98
- Examples of unbundled services are provided
- Classifying and costing methodology is described in detail
|
- Believes that unbundling the five cost categories satisfy the criterion in the June 21 ACR
- Further unbundling should use the same principles as the Commission applied to the unbundling of generation: no cost-shifting, rate cap, and stranded cost recovery
|
- Further unbundling first requires determination of whether it provides customer value
- Believes that the CPUC's deadline of 1/1/98 requires deferring this determination
- Notes that parties were directed to focus "only on resolving issues that are necessary for implementation by January 1, 1998"
|