7.1 Implementation Objectives
First and foremost, there is general agreement as to the importance
of developing procedures for registering electricity service providers
and developing a program to educate consumers, prior to the commencement
of direct access on January 1, 1998. Failure to achieve these
objectives risks customer confusion, poor market information,
inadequate choices for some consumer groups, and political backlash
resulting from an undeveloped and poorly performing competitive
market.
In addition, AB 1890 has identified some additional tasks that must be incorporated into an implementation plan for consumer protection and education. To be specific, these new tasks are:
[1] design and implementation of the formal notification that providers must furnish to prospective customers (see Sec. 394(b));
[2] design of a mechanism for cancellation of a contract by customers (see Sec. 395);
[3] creation of standards for safety and reliability of distribution systems, including restoration of service after outages (see Sec. 364);
[4] determination of the process for exempting renewable-energy customers from phase-in of direct access (see Sec. 366(b));
[5] creation of operating rules for the entity or entities to perform third-party verification of customer changes of service provider (see Sec. 366 (d,e)); and
[6] education of existing and potential cogeneration consumers
about opportunities to benefit from CTC relief (see Sec. 372).
These new tasks affect the implementation of consumer protection
and education in a twofold manner. First, they increase the scope
of activities that must be conducted during 1997, and second,
they affect the content of the consumer education effort by adding
new elements about which consumers must be educated.
This chapter proposes implementation timelines and recommends
actions that some of the DAWG members believe the CPUC should
take now in order to implement an effective program of consumer
protection and education. We propose two "critical path"
chains of events, one leading to CPUC registration of electricity
service providers, the other leading to adoption and implementation
of a Consumer Education Plan. Time is clearly of the essence,
as a review of our proposed timelines will show. Already, time
constraints are acting to limit our opportunity to pursue more
deliberative efforts. For instance, Section 11.2 of the August
30, 1996 DAWG Report identified a number of different entities
in whom responsibility for Consumer Education Plan development
could be vested. Whatever the merits of these different options,
AB 1890 made it clear that the state's "electric corporations"
ó most notably the existing utilities ó will take
the lead to develop and implement, subject to Commission approval,
Consumer Education Plans in the time available.
Obviously, the implementation schedules adopted for consumer protection
and education issues need to dovetail with the Commissionís
other restructuring and direct access implementation efforts.
Many of the DAWG members agree with the importance of developing
a Consumer Education Trust, which would serve as a source of funding
for community-based and other targeted educational outreach programs.
In Chapter 5, various structural and funding approaches are described.
In light of more pressing needs, we have not developed specific
implementation proposals, and do not plan to make a further submission
to the CPUC on this subject on December 6, 1996. Finding a reasonable
source of funding for the trust is a problem, due to the rate
freeze enacted in recent legislation, and a general concern with
high electricity rates. We request the Commissionís guidance
with regard to funding sources.
In addition to registration and education efforts, the Direct
Access Working Group envisions the CPUC taking an affirmative
role in developing redress, oversight and monitoring procedures
(Chapter 4 of this report) and becoming a reliable, neutral source
for information about electricity service providers (Chapter 5).
Because these are internal CPUC functions, we have not provided
specific implementation recommendations. Nevertheless, we are
concerned that the CPUC move expeditiously in these areas. Our
members welcome any opportunity to comment or assist in these
CPUC efforts.
7.2 Legislative Issues and AB 1890
This report has been drafted to reflect the beliefs of the DAWG
members about the necessary elements of effective programs to
insure adequate consumer protection and education. In developing
our recommendations, we made no attempt to limit ourselves based
on what is permissible under existing law, or what is achievable
through legislative changes.
Recently enacted legislation, AB 1890, explicitly imposes on the
CPUC a requirement to register electricity service providers and
specifies information to be compiled from such providers. The
DAWG members are not prepared to express opinions as to whether
this legislation restricts the CPUC's ability to impose requirements
on electricity service providers, such as bonding, or allows the
CPUC to reject or suspend a registrant. In general, most of us
believe the CPUC should have such authority. As soon as possible,
the CPUC should conduct a review of its statutory responsibilities
and authorities in light of AB 1890's registration requirements,
and determine whether it will require additional consumer protection
legislation to carry out its responsibilities. Such clarity is
essential to move forward with the registration timeline presented
in the following section.
AB 1890 imposes the implementation of consumer education program
on electric companies, subject to approval by the CPUC. The discussion
of a utility-initiated Consumer Education Plan contained in Chapter
5 comports with this legislative requirement.
Finally, AB 1890 recognizes that restructuring imposes certain
implementation costs on utilities, which at the same time imposing
a rate freeze (Section 368(a)). Section 376 provides a procedure
for utilities to defer recovery of implementation costs until
after 2001. The DAWG members recognize the practical necessity
of allowing utilities to recover their costs associated with the
Consumer Education Plan described in Chapter 5. Thus, the CPUC
should allow utilities to make a funding request, and should act
expeditiously on this request.
7.3 Implementation Timelines
7.3.1 General Framework
A recent Commissioners' Ruling adopted a schedule for comments
on this report. Comments are due on November 26, 1996, and replies
are due on December 11, 1996. As a result we do not anticipate
further action by the CPUC on Consumer Protection and Education
issues until the end of 1996, once comments and replies have been
received, so the timelines presented below effectively start at
the beginning of 1997.
Technical requirements imposed on metering and communication systems
by the ISO settlements process, and Commission decisions regarding
the nature and timing in which any phase-in of direct access will
take place, will affect when in 1997 customers must begin to make
their direct access elections. One outcome could be that the ISO
will require a daily flow of metered usage information be communicated
"upstream" so that accounts can be settled each day
and so that schedule coordinators are aware of the discrepancies
between their forecast and actual loads as soon as possible. If
this is the case, most existing customer metering, even for the
largest customers, would need to be replaced or augmented with
communication devices prior to the commencement of direct access.
At least 60 days should be allowed to procure, install and test
the necessary metering and communication devices. A longer time
period for metering and communication device installation may
be needed if load profiling is not utilized for residential customers.
If the Commission adopts a phase-in schedule that limits direct
access availability during 1998, so that there are more customers
seeking direct access eligibility than can be accommodated, there
may be a need for some form of open season where customers can
choose whether to participate in the initial phase of direct access.
The schedule should allow adequate time for this open season,
if it occurs. If 30 days are allowed for the open season, and
60 days for metering and communication implementation, then registration
and initial consumer education efforts should be completed no
later than September 30, 1997. We cannot be certain that this
target date is sufficient, or that a later date would be infeasible.
However, this date provides a basis for beginning to plan for
and schedule needed registration and education implementation
activities.
Based on the above, the schedules set forth below show that there
are about nine months to complete the registration and education
processes, from the end of the comment period on this report until
the beginning of an open season on October 1, 1997. The next two
subsections present specific timelines for registration and education
consistent with this assumption. The final subsection discusses
alternatives that take into consideration delays in the schedule.
7.3.2 Registration
At the outset, the Commission must determine whether or not a
proceeding is needed to develop registration requirements. Some
parties have asserted that AB 1890 is dispositive of many issues
regarding registration of electric service providers (ESPs), so
that little additional effort by the Commission is required. In
this case, the registration process becomes a simple matter of
collecting the information required by the statute.
Other parties assert that the Commission should establish a more
comprehensive registration program than what is provided by AB
1890. If the Commission chooses to do so, it will need to determine
whether AB 1890 constrains its authority in this area, and if
so, it will need to seek new legislation that provides for greater
Commission authority. In this case, there are a variety of alternative
approaches to initiate the process of developing registration
requirements and implementing electricity service provider registration.
Some options and approaches for electricity service provider registration
are described in Chapter 4. This section describes the advantages
and disadvantages of three approaches: (1) developing registration
requirements in an Order Instituting Rulemaking (OIR) or an Order
Instituting Investigation (OII), (2) initiating a proceeding on
registration requirements by requiring Southern California Edison,
Pacific Gas and Electric, and San Diego Gas and Electric to file
proposals, and (3) directing further working group efforts to
seek consensus proposals, after the Commission provides further
guidance on certain issues.
7.3.2.1 ALTERNATIVE: An OIR/OII to determine registration
requirements
Alternative 7.3.2.1 PRO: This is a familiar way to resolve
policy issues.
Alternative 7.3.2.1 CON: This process is complicated, expensive
and takes a long time.
7.3.2.2 ALTERNATIVE: CPUC requires IOUs to file proposals
Alternative 7.3.2.2 PRO: Shifts responsibility for initial
effort to the electric utilities.
Alternative 7.3.2.2 CON
1. Allows little or no stakeholder participation.
2. Expertise of IOUs in this area is not sufficient to outweigh benefits of broad representation of viewpoints.
3. There is no necessary reason why the utilities should be the
applicants.
7.3.2.3 ALTERNATIVE: A stakeholder working group to develop
proposals
This alternative requires that the CPUC promptly resolve certain
key issues identified in the August 30 DAWG Report, the two sets
of comments on that report and the October 10 Hearing. Once the
working group process begins, the CPUC may need to respond quickly
to make any further decisions required to resolve barriers to
consensus.
Alternative 7.3.2.3 PRO
1. Can result in solution in which all interested parties are
meaningfully represented, leading to greater fairness, fewer incentive
or enforcement problems and greater societal efficiency.
2. The DAWG process should not be seen as lacking because it identified,
described and offered a range of alternative solutions for many
large problems but did not achieve consensus on any of them. The
DAWG process achieved its mission, which did not include trying
to achieve consensus on any issues. Moreover, DAWG did achieve
consensus quite easily on selection of coordinating committee,
subgroup leaders and editing team.
3. What is needed now is a stakeholder working group given a well
defined task, a mission to achieve a workable consensus within
a set period of time, and a process that enables meaningful representation
by all affected parties.
4. DAWG parties could select members of such a group, having done
this before as noted in PRO Point 1 above, and find ways to reduce
the resource burdens on these "representatives."
Alternative 7.3.2.3 CON
1. Some stakeholders are stretched for resources after DAWG and
other working groups, and they may find it difficult to participate
in such an effort.
2. There is no assurance that a stakeholder process will be successful.
Given the substantially divergent interests of likely participants,
the changes for success are small.
Table 7-1 below sets out an illustrative schedule for developing
registration requirements and for registering ESPs prior to the
commencement of direct access, consistent with the alternatives
above. This schedule assumes that developing registration requirements
will be a controversial process requiring a final CPUC decision.
If this is not the case, or if the Commission's receipt of registration
applications becomes a ministerial action, then this schedule
is largely moot and the registration process can be considerably
shortened. The schedule envisions a process in which ESP applicants
will be registered en masse if they meet certain application
deadlines, but late applications will be processed individually
and may not receive approval by 9/30/97.
| Activity | ||
| 1997: 1/31 | OIR/OII Issued or Utility Proposals Filed or Workshops Commence | |
| 3/7 | Prehearing Conference or Workshop Report | |
| 3/14 | Initial Comments on OIR/OII or Workshop Report or CPUC Staff
and Intervenor Testimony | |
| 3/21 | Reply Comments on OIR/OII or Workshop Report or Concurrent
Rebuttal Testimony | |
| 3/31 | Hearings (If Required) | |
| 5/30 | CPUC Decision | |
| 8/1 | Registration Applications Due | |
| 9/1 | Protests to Registration Applications Due | |
| 9/30 | CPUC Decision Approving Registrants Applications | |
| 10/1 | Open Season Commences |
The above timeline does not provide for any gap between approval
of registration applications and the start of the open season.
This could be a burden on some applicants. However, it is likely
that virtually all applicants will be approved (although some
may be required to cure defects in their original applications),
so that the applicants are likely to begin advertising and other
business activities while their applications are pending. In any
case, applicants will know whether any party has protested their
applications 30 days before the start of the open season.
7.3.3 Consumer Education
The two tables below set out alternative schedules for developing
and implementing a Consumer Education Plan (CEP) as described
in Chapter 5. Both schedules assume that the CEP can be developed
by the CEP Group in a largely consensus-based process without
a requirement for formal evidentiary hearings. The DAWG members
expect that the CPUC would be able to issue a decision on the
CEP Group's consumer education application after reviewing issues
addressed in protests to the application, should any parties choose
to file a protest.
The first schedule, shown in Table 7-2, envisions that the CEP
Group would jointly file an application for development of a CEP.
The application should describe the process of consultant selection,
should include a preliminary scope of consultant services, should
describe the procedures to insure stakeholder involvement, and
should request a specific funding mechanism consistent with P.U.
Code 376. A subgroup of utility communication experts has already
begun preliminary meetings, at the request of the DAWG members,
as reported in Chapter 5. The CPUC should encourage municipal
utilities to participate in this joint application and in the
development of the CEP. Without such coordination, mass media
advertising (print ads, radio, and, if necessary, television)
may create confusion, since they will necessarily reach customers
of investor-owned utilities and municipal utilities alike.
| Activity | ||
| 1997: 2/7 | The CEP Group Jointly Files Consumer Education Application and Funding Request | |
| 3/10 | Protests Due | |
| 3/31 | CPUC Decision | |
| 5/30 | Vendor Selected | |
| 8/1 | Consumer Education Plan Completed | |
| 8/1 | Education Efforts Begin | |
| 10/1 | Open Season Commences |
The second schedule, shown in Table 7-3, assumes that the utilities
constituting the CEP Group would be prepared and willing to proceed
with significant aspects of the CEP without further direction
from the Commission. The key element of this proposal that differs
from the first, is that utility work begins in 1996 with a vendor
selected by the end of 1996. Thus, the CEP Group would file an
application almost immediately after reply comments are filed
in response to this DAWG report. Also, the actual vendor-constructed
CEP must be presented to the Commission for approval and revisions,
as per stakeholder input. The time for these two processes requires
utilities to submit the application prior to a Commission ruling
on the DAWG Consumer Protection and Education report.
| Activity | ||
| 1996: 12/15 | CEP Group Files Consumer Education Application, Vendor Recommendation and Funding Request, in anticipation of CPUC decision on DAWG report. | |
| 1997: 1/15 | Protests Due | |
| 3/1 | CPUC Decision | |
| 3/15 | Vendor Retained and Education Plan Process Begins | |
| 5/1 | Education Plan submitted to CPUC | |
| 6/1 | Comments on Plan by Stakeholders due | |
| 7/15 | Commission Ruling on the Plan and Education Efforts Begin | |
| 10/1 | Open Season Commences |
7.3.4 Accommodating Delay
The timelines shown above are very compressed, and do not permit
any slippage should delays be encountered. Some parties believe,
however, that modifications to the schedule of direct access could
occur and still allow direct access to commence on January 1,
1998, in case there is a delay in the schedule for registration
and education activities. Of course, if the ISO does not require
daily reporting of metered usage information, existing metering
would be sufficient to accommodate large customers, and it may
be possible to shorten the 60 day period for meter and communication
infrastructure installation now reflected in the schedules.
Gradually Phase-In Direct Access During the First Quarter of
1998. If the open season is conducted in December 1997, metering
infrastructure would be installed during the first 60 days of
1998. Thus, while some customers would have direct access on day
one, others would be backlogged for a period of time while infrastructure
is installed. As a result, it would be possible to accommodate
a several months delay in both the registration and education
timelines.
Different Phase-In Schedule For Residential Customers.
In comments on the August 30, 1996 DAWG Report, Southern California
Edison, Pacific Gas and Electric and San Diego Gas and Electric
companies all supported use of load profiles for residential customers.
At some risk of consumer confusion, it may be possible to have
an October 1997 open season for business customers and a December
1997 open season for residential customers. (Some believe there
will be limited residential interest in direct access. If this
is the case, over subscription of the residential portion of the
first year phase-in limits may not occur, and there may not need
to be any allocation procedures.) This would allow the education
program timeline to be delayed several months. If the Commission
is willing to allow electricity service providers to offer services
to business customers provisionally, i.e., while their application
is pending, this would also allow the registration program timeline
to be delayed several months.
7.3.5 A Sense of Urgency
Some DAWG participants are concerned with the potential for schedules
slipping, causing a delay in direct access implementation. These
parties recommend that the Commission consider a "minimum
effort" education and registration plan that would be implemented
by default, should the CEP implementation not proceed on schedule
for any reason. The minimum effort plan could be implemented as
either a substitute or a supplement for the CEP. It is therefore
recommended by some parties that the Commission request, in the
initial CEP Group filings, a "minimum effort plan" along
with utility-suggested implementation procedures.
Many DAWG participants expressed concerns over introducing in
this report a proposed 1997 funding amount for consumer education.
Some asserted that until the CEP is developed, the appropriate
funding level will not be known. Others believed that the schedules
proposed in Tables 7-2 and 7-3 adequately allow the Commission
to make timely implementation funding decisions. There are some
important details to note in these schedules, however.
First, the schedule of Table 7-2 addresses only a single funding
application on February 7, 1997, to establish funding to develop
the CEP. There is no application for funding to implement the
CEP. Quite the contrary, as soon as the CEP is prepared it begins
to be implemented. Omitted from the schedule is a process for
the Commission to (1) authorize CEP implementation funding as
a restructuring transition cost, for collection per Section 376
of the PU Code, and (2) require that the CEP be implemented by
each utility under the CEP-proposed schedule. Unless those two
items are addressed, the implementation of the CEP may not be
coordinated at a state-wide level across all three IOU service
territories. Without timely implementation of state-wide education,
the Commissionís targeted January 1, 1998 date for implementing
direct access could be in jeopardy.
Table 7-3 addresses the implementation funding application issue,
but does not schedule a CPUC decision on that application until
July 15, 1997. Although Table 7-3 indicates that education would
start immediately upon CPUC approval, some parties assert that
it would be another 30 days before education could start, which
would endanger the 1/1/98 target. For this reason, another alternative
is proposed that allows education of consumers to begin sooner,
using "start-up" educational funding approved early
in the process by the Commission as a restructuring transition
cost.
The new alternative proposes the schedule in Table 7-4. Under
that schedule the CEP group is to file, within its first application,
a proposal for start-up funding including details on how that
funding would be used. Any additional consumer education funding
that is needed would then be addressed in the second application.
Under this alternative, the initial education efforts would not
have to wait until approval of that second application.
| Activity | ||
| 1997: 1/15 | CEP Group files a Consumer Education Application, including vendor recommendation and a "start-up" funding request, in anticipation of CPUC decisions on both the August 30th and October 30th DAWG reports. | |
| 2/15 | Protests Due | |
| 3/31 | CPUC Decision | |
| 4/15 | Vendor selected and CEP process begins | |
| 6/1 | CEP completed and submitted to CPUC for approval | |
| 7/1 | Comments on the CEP by stakeholders due | |
| 7/1 | Education begins with "start-up" activities | |
| 8/15 | Commission approval of the CEP and authorization of funding | |
| 9/15 | Balance of CEP education begins |
A modest variation to this alternative would have the Commission,
in response to this report, preapprove the amount of $10 million
as start-up funding for education efforts to begin by July 1,
1997. In this case, the first filing of the CEP Group would take
this amount as given and offer a proposal for its use.
The Commission needs to decide among these alternative schedules
and processes for determining implementation funding, or suggest
another alternative that reasonably accommodates its interest
in educating consumers in adequate time to allow for direct access
by January 1, 1998. Because the first proposed date of December
15, 1996 (see Table 7-3) for a joint utility application is fast
approaching, the Commission may want to address these scheduling
issues prior to rendering a decision on the other issues of this
report.