DAWG Team B Report

Meeting on 6/6:

Material Distributed on Load Profiling: Four Alternatives

The difficulty is with settlements and assigning responsibility

Closure scheduled for 6/19

Material Distributed on Aggregation:

Different Forms: No consensus; closure scheduled 6/19

Mobile Home Park Issues

Scheduled for closure on 6/19

Meeting on 6/19:

New Assignments:

Retail Reciprocity -- SDG&E

Codes of Conduct -- CEC (With input from Team D)

Information Access -- CEC (Team D to B to A)

Billing Issues -- SDG&E

Quotations from CPUC on Aggregation for Report -- SCE

Monopoly/Affiliate Codes of Conduct -- CEC

Revised/Updated Workplan -- Coordinating Members

Wrap-up:

Aggregation

Load Profiling

Mobile Home Park Issues

Obligation-to-Serve

Cost Responsibility

Begin:

Franchise Fees

Regulatory Issues: Jurisdiction

mmccay:6/7/96