DATE |
||||||||
1 | 0 | Decision Becomes Effective | Issues | 06 MAY | CPUC | ----- | D. 97-04-040
[Page 99] | |
2 | +21 | Advice Letters to Establish Interim, 90 Day Memorandum Accounts to Track All Costs to Implement Direct Access | 376 | 27 MAY | Parties | ----- | D. 97-04-040
[O.P. 8.] | |
3 | +21 | Advice Letters to Establish IRMA Subaccounts Identified in D. 97-05-040 to which Costs from the 90-Day Interim Memo Accounts will be Reallocated | 376 | 27 May | Utilities | ----- | D. 97-04-040
[O.P. 9.) | |
4 | +30 | First Direct Access Implementation Plan Meeting Convened | Protocols & Policies | 05 JUN | Utilities | Interested
Parties incl. DAWG | D. 97-04-040 [O.P. 5.e.(2)] | |
5 | +30 | Load Profile Methodologies Workshop | Profiling | 05 JUN | Energy Division |
UDCs and Int. Parties |
D. 97-04-040 [O.P. 7.b.(1)] | |
6 | +40 | Workshop Report on Load Profile Methodologies Due | Profiling | 16 JUN | UDCs | Workshop
Participants | D. 97-04-040 [O.P. 7.b.(1)] | |
7 | +45 | Metering Technical Specifications / Communication Stds Workshop | Standards | 20 JUN | Energy Division |
UDCs and Int. Parties |
D. 97-04-040 [O.P. 7.a.(1)] | |
8 | +45 | Comments on Affiliate Transaction Guidelines Due | Transactions | 20 JUN | Utilities | ----- | D. 97-04-040
[O.P. 10.] | |
9 | +55 | Comments on Load Profile Methodologies Workshop Report Due | Profiling | 30 JUN | Parties | ----- | D. 97-04-040
[O.P. 7.b.(1)] | |
10 | --- | Prepared Direct Testimony on Load Profiling Issues Due (if required) | Profiling | Week of 30 JUN | Utilities | ----- | D. 97-04-040
[O.P. 7.b.(2)] | |
11 | --- | Direct Access Implementation Plans Due | Protocols & Policies | 01 JUL | Utilities | Stkholders | D. 97-04-040
[O.P. 5.e.(3)] | |
12 | --- | Retailer Registration Application Forms Acceptance Begins | Registration | 01 JUL | Retailers | ----- | D. 97-04-040
[O.P. 5.i.(2)] | |
13 | +60 | Reply Comments on Affiliate Transaction Guidelines Due | Transactions | 07 JUL | Parties | ----- | D. 97-04-040
[O.P. 10.] | |
14 | +60 | Comments on Code Section 394(b) Notice Format Due | Format | 07 JUL | Parties | ----- | D. 97-04-040
[Page 63] | |
15 | +60 | Retail Settlement & Information Flow Issues Workshop | 07 JUL | Energy
Division |
UDCs and Int. Parties |
D. 97-04-040 [O.P. 7.c.] | ||
16 | --- | Reply Testimony on Load Profiling Issues Due (if required) | Profiling | Week of 14 JUL | Non-Utilit. | ----- | D. 97-04-040
[O.P. 7.b.(2)] | |
17 | +70 | Workshop Report on Metering Technical Specifications / Communication Stds Due | Standards | 15 JUL | Utilities | Workshop
Participants | D. 97-04-040 [O.P. 7.a.(1)] | |
18 | --- | Comments on Direct Access Implementation Plans Due | Protocols & Policies | 18 JUL | Parties | ----- | D. 97-04-040
[O.P. 5.e.(3)] | |
19 | --- | Evidentiary Hearings on Load Profiling Issues Begin (if required) | Profiling | Week of 21 JUL/ 28 JUL | CPUC | Parties | D. 97-04-040
[O.P. 7.b.(2)] | |
20 | +75 | Reply Comments on Code Section 394(b) Notice Format Due | Format | 21 JUL | Parties | ----- | D. 97-04-040
[Page 63] | |
21 | +75 | Customer Information Data Base Workshop | 21 JUL | Energy
Division |
UDCs and Int. Parties |
D. 97-04-040 [O.P. 7.d.] | ||
22 | +80 | Workshop Report on Retail Settlement & Information Flow Issues Due | & Information Flow | 25 JUL | Utilities | Workshop
Participants | D. 97-04-040 [O.P. 7.c.] | |
23 | +85 | Comments on Metering Technical Specifications / Communication Stds Workshop Report Due | Standards | 30 JUL | Parties | ----- | D. 97-04-040
[O.P. 7.a.(1)] | |
24 | +95 | Comments on Retail Settlement & Information Flow Workshop Report Due | & Information Flow | 11 AUG | Parties | ----- | D. 97-04-040
[O.P. 7.c.] | |
25 | +100 | Workshop Report on Customer Information Data Base Due | 14 AUG | Utilities | Workshop
Participants | D. 97-04-040 [O.P. 7.d.] | ||
26 | +115 | Comments on Customer Information Data Base Workshop Report Due | & Information Flow | 29 AUG | Parties | ----- | D. 97-04-040
[O.P. 7.d] | |
27 | --- | Direct Access Request Acceptance Begins (to be effective 1/1/98) | 01 NOV | Utilities | ----- | D. 97-04-040
[O.P. 5.e.(4)] | ||
28 | --- | Monthly Progress Reports on Implementation Activities Begin | 15 NOV | Utilities | ----- | D. 97-04-040
[O.P. 5.e.(5)] |
* Date Status:
- Activity Completed
- Milestone Deadline per D. 97-05-040