Direct Access Implementation
WORKSHOP REPORT PREPARATION


Attachment #10: WORK BREAKDOWN STRUCTURE


Total Project


Plan & Workshop Report Tasks
Due Date
Responsibility
Status
1Project Plan
2Distribute Draft Project Plan 17 APRSDG&E
3Convene Planning Meeting 21 APRCEC
4Arrange Facilities 15 APRCEC
5Send Notice of Meeting to Participants 17 APRCEC
6Make Presentation on Project Plan 21 APRSDG&E
7Provide Comments on Project Plan 21 APRParticipants
8Distribute Final Project Plan* 08 MAYSDG&E
9Update Plan, as Necessary
----------
SDG&E
10Retain a Workshop Facilitator 20 MAYSCE
11Load Profile Methodologies
12Distribute Draft Outline 16 MAYPG&E,SCE,SDG&E
13Convene Pre-Workshop Meeting 23 MAYPG&E
14Arrange Facilities 09 MAYPG&E
15Send Notice of Meeting to Service List 16 MAYPG&E
16Prepare Agenda & Distribute 16 MAYPG&E
17Make Presentation on Outline 23 MAYStakeholders
18Reach Consensus on Final Outline 23 MAYParticipants
19Distribute Text of Proposal 02 JUNPG&E,SCE,SDG&E
20Convene CPUC-Ordered Workshop 05 JUNEnergy Division
21Arrange Facilities 16 MAYEnergy Division
22Serve Notice of Workshop to Service List 23 MAYEnergy Division
23Make Presentation on Outline Topics 05 JUNStakeholders
24Discuss/Resolve Issues 05 JUNParticipants
25List Contested Issues by Party 05 JUNFacilitator
26Send Position on Contested Issues to PG&E 10 JUNParties
27Distribute Draft of Workshop Report 09 JUNPG&E,SCE,SDG&E
28Provide Comments on Draft to PG&E 12 JUNParties
29File Final Workshop Report with CPUC 16 JUNPG&E,SCE,SDG&E
30File Comments on Workshop Report 30 JUNParties
31DA Implementation Plan (DAIP)
32Distribute Draft Outline 16 MAYSCE
33Convene Pre-Workshop Meeting 23 MAYSCE
34Arrange Facilities 09 MAYSCE
35Send Notice of Meeting to Service List 16 MAYSCE
36Prepare Agenda & Distribute 16 MAYSCE
37Make Presentation on Outline 23 MAYStakeholders
38Reach Consensus on Final Outline 23 MAYParticipants
39Distribute Text of Proposal 04 JUNPG&E,SCE,SDG&E
40Convene CPUC-Ordered Workshop 09 JUNEnergy Division
41Arrange Facilities 16 MAYEnergy Division
42Serve Notice of Workshop to Service List 30 MAYEnergy Division
43Make Presentation on Outline Topics 09 JUNEnergy Division
44Discuss/Resolve Issues 09 JUNParticipants
45List Contested Issues by Party 09 JUNFacilitator
46Send Position on Contested Issues to SCE 12 JUNParties
47Distribute Draft of DAIP 20 JUNPG&E,SCE,SDG&E
48Provide Comments on Draft to SCE 26 JUNParties
49File Final DAIP with CPUC 01 JULPG&E,SCE,SDG&E
50File Comments on DAIP 18 JULParties
51Meter/Data Communications Stds
52Distribute Draft Outline 21 MAYPG&E,SCE,SDG&E
53Convene Pre-Workshop Meeting 28 MAYSDG&E
54Arrange Facilities 14 MAYSDG&E
55Send Notice of Meeting to Service List 21 MAYSDG&E
56Prepare Agenda & Distribute 21 MAYSDG&E
57Make Presentation on Outline 28 MAYStakeholders
58Reach Consensus on Final Outline 28 MAYParticipants
59Distribute Text of Proposal 17 JUNPG&E,SCE,SDG&E
60Convene CPUC-Ordered Workshop 20 JUNEnergy Division
61Arrange Facilities 27 MAYEnergy Division
62Serve Notice of Workshop to Service List 10 JUNEnergy Division
63Make Presentation on Outline Topics 20 JUNStakeholders
64Discuss/Resolve Issues 20 JUNParticipants
65List Contested Issues by Party 20 JUNFacilitator
66Send Position on Contested Issues to SDG&E 25 JUNParties
67Distribute Draft of Workshop Report 03 JULPG&E,SCE,SDG&E
68Provide Comments on Draft to SDG&E 10 JULParties
69File Final Workshop Report with CPUC 15 JULPG&E,SCE,SDG&E
70File Comments on Workshop Report 30 JULParties
71Retail Settlement & Info. Flow
72Distribute Draft Outline 03 JUNPG&E,SCE,SDG&E
73Convene Pre-Workshop Meeting 10 JUNPG&E
74Arrange Facilities 23 MAYPG&E
75Send Notice of Meeting to Service List 30 MAYPG&E
76Prepare Agenda & Distribute 30 MAYPG&E
77Make Presentation on Outline 10 JUNStakeholders
78Reach Consensus on Final Outline 10 JUNParticipants
79Distribute Text of Proposal 02 JULPG&E,SCE,SDG&E
80Convene CPUC-Ordered Workshop 07 JULEnergy Division
81Arrange Facilities 13 JUNEnergy Division
82Serve Notice of Workshop to Service List 27 JUNEnergy Division
83Make Presentation on Outline Topics 07 JULStakeholders
84Discuss/Resolve Issues 07 JULParticipants
85List Contested Issues by Party 07 JULFacilitator
86Send Position on Contested Issues to PG&E 10 JULParties
87Distribute Draft of Workshop Report 14 JULPG&E,SCE,SDG&E
88Provide Comments on Draft to PG&E 22 JULParties
89File Final Workshop Report with CPUC 25 JULPG&E,SCE,SDG&E
90File Comments on Workshop Report 11 AUGParties
91Customer Info. Data Base
92Distribute Draft Outline 03 JUNPG&E,SCE,SDG&E
93Convene Pre-Workshop Meeting 10 JUNSCE
94Arrange Facilities 23 MAYSCE
95Send Notice of Meeting to Service List 30 MAYSCE
96Prepare Agenda & Distribute 30 MAYSCE
97Make Presentation on Outline 10 JUNStakeholders
98Reach Consensus on Final Outline 10 JUNParticipants
99Distribute Text of Proposal 16 JULStakeholders
100Convene CPUC-Ordered Workshop 21 JULEnergy Division
101Arrange Facilities 27 JUNEnergy Division
102Serve Notice of Workshop to Service List 11 JULEnergy Division
103Make Presentation on Outline Topics 21 JULStakeholders
104Discuss/Resolve Issues 21 JULParticipants
105List Contested Issues by Party 21 JULFacilitator
106Send Position on Contested Issues to SCE 24 JULParties
107Distribute Draft of Workshop Report 04 AUGPG&E,SCE,SDG&E
108Provide Comments on Draft to SCE 11 AUGParties
109File Final Workshop Report with CPUC 14 AUGUtilities
110File Comments on Workshop Report 29 AUGParties

Status Column: - Denotes Completion of Task
* Subject to Review and Approval from Commissioner Knight's Office