| 1 | Project Plan | |||
| 2 | Distribute Draft Project Plan | 17 APR | SDG&E | |
| 3 | Convene Planning Meeting | 21 APR | CEC | |
| 4 | Arrange Facilities | 15 APR | CEC | |
| 5 | Send Notice of Meeting to Participants | 17 APR | CEC | |
| 6 | Make Presentation on Project Plan | 21 APR | SDG&E | |
| 7 | Provide Comments on Project Plan | 21 APR | Participants | |
| 8 | Distribute Final Project Plan* | 08 MAY | SDG&E | |
| 9 | Update Plan, as Necessary | SDG&E | ||
| 10 | Retain a Workshop Facilitator | 20 MAY | SCE | |
| 11 | Load Profile Methodologies | |||
| 12 | Distribute Draft Outline | 16 MAY | PG&E,SCE,SDG&E | |
| 13 | Convene Pre-Workshop Meeting | 23 MAY | PG&E | |
| 14 | Arrange Facilities | 09 MAY | PG&E | |
| 15 | Send Notice of Meeting to Service List | 16 MAY | PG&E | |
| 16 | Prepare Agenda & Distribute | 16 MAY | PG&E | |
| 17 | Make Presentation on Outline | 23 MAY | Stakeholders | |
| 18 | Reach Consensus on Final Outline | 23 MAY | Participants | |
| 19 | Distribute Text of Proposal | 02 JUN | PG&E,SCE,SDG&E | |
| 20 | Convene CPUC-Ordered Workshop | 05 JUN | Energy Division | |
| 21 | Arrange Facilities | 16 MAY | Energy Division | |
| 22 | Serve Notice of Workshop to Service List | 23 MAY | Energy Division | |
| 23 | Make Presentation on Outline Topics | 05 JUN | Stakeholders | |
| 24 | Discuss/Resolve Issues | 05 JUN | Participants | |
| 25 | List Contested Issues by Party | 05 JUN | Facilitator | |
| 26 | Send Position on Contested Issues to PG&E | 10 JUN | Parties | |
| 27 | Distribute Draft of Workshop Report | 09 JUN | PG&E,SCE,SDG&E | |
| 28 | Provide Comments on Draft to PG&E | 12 JUN | Parties | |
| 29 | File Final Workshop Report with CPUC | 16 JUN | PG&E,SCE,SDG&E | |
| 30 | File Comments on Workshop Report | 30 JUN | Parties | |
| 31 | DA Implementation Plan (DAIP) | |||
| 32 | Distribute Draft Outline | 16 MAY | SCE | |
| 33 | Convene Pre-Workshop Meeting | 23 MAY | SCE | |
| 34 | Arrange Facilities | 09 MAY | SCE | |
| 35 | Send Notice of Meeting to Service List | 16 MAY | SCE | |
| 36 | Prepare Agenda & Distribute | 16 MAY | SCE | |
| 37 | Make Presentation on Outline | 23 MAY | Stakeholders | |
| 38 | Reach Consensus on Final Outline | 23 MAY | Participants | |
| 39 | Distribute Text of Proposal | 04 JUN | PG&E,SCE,SDG&E | |
| 40 | Convene CPUC-Ordered Workshop | 09 JUN | Energy Division | |
| 41 | Arrange Facilities | 16 MAY | Energy Division | |
| 42 | Serve Notice of Workshop to Service List | 30 MAY | Energy Division | |
| 43 | Make Presentation on Outline Topics | 09 JUN | Energy Division | |
| 44 | Discuss/Resolve Issues | 09 JUN | Participants | |
| 45 | List Contested Issues by Party | 09 JUN | Facilitator | |
| 46 | Send Position on Contested Issues to SCE | 12 JUN | Parties | |
| 47 | Distribute Draft of DAIP | 20 JUN | PG&E,SCE,SDG&E | |
| 48 | Provide Comments on Draft to SCE | 26 JUN | Parties | |
| 49 | File Final DAIP with CPUC | 01 JUL | PG&E,SCE,SDG&E | |
| 50 | File Comments on DAIP | 18 JUL | Parties | |
| 51 | Meter/Data Communications Stds | |||
| 52 | Distribute Draft Outline | 21 MAY | PG&E,SCE,SDG&E | |
| 53 | Convene Pre-Workshop Meeting | 28 MAY | SDG&E | |
| 54 | Arrange Facilities | 14 MAY | SDG&E | |
| 55 | Send Notice of Meeting to Service List | 21 MAY | SDG&E | |
| 56 | Prepare Agenda & Distribute | 21 MAY | SDG&E | |
| 57 | Make Presentation on Outline | 28 MAY | Stakeholders | |
| 58 | Reach Consensus on Final Outline | 28 MAY | Participants | |
| 59 | Distribute Text of Proposal | 17 JUN | PG&E,SCE,SDG&E | |
| 60 | Convene CPUC-Ordered Workshop | 20 JUN | Energy Division | |
| 61 | Arrange Facilities | 27 MAY | Energy Division | |
| 62 | Serve Notice of Workshop to Service List | 10 JUN | Energy Division | |
| 63 | Make Presentation on Outline Topics | 20 JUN | Stakeholders | |
| 64 | Discuss/Resolve Issues | 20 JUN | Participants | |
| 65 | List Contested Issues by Party | 20 JUN | Facilitator | |
| 66 | Send Position on Contested Issues to SDG&E | 25 JUN | Parties | |
| 67 | Distribute Draft of Workshop Report | 03 JUL | PG&E,SCE,SDG&E | |
| 68 | Provide Comments on Draft to SDG&E | 10 JUL | Parties | |
| 69 | File Final Workshop Report with CPUC | 15 JUL | PG&E,SCE,SDG&E | |
| 70 | File Comments on Workshop Report | 30 JUL | Parties | |
| 71 | Retail Settlement & Info. Flow | |||
| 72 | Distribute Draft Outline | 03 JUN | PG&E,SCE,SDG&E | |
| 73 | Convene Pre-Workshop Meeting | 10 JUN | PG&E | |
| 74 | Arrange Facilities | 23 MAY | PG&E | |
| 75 | Send Notice of Meeting to Service List | 30 MAY | PG&E | |
| 76 | Prepare Agenda & Distribute | 30 MAY | PG&E | |
| 77 | Make Presentation on Outline | 10 JUN | Stakeholders | |
| 78 | Reach Consensus on Final Outline | 10 JUN | Participants | |
| 79 | Distribute Text of Proposal | 02 JUL | PG&E,SCE,SDG&E | |
| 80 | Convene CPUC-Ordered Workshop | 07 JUL | Energy Division | |
| 81 | Arrange Facilities | 13 JUN | Energy Division | |
| 82 | Serve Notice of Workshop to Service List | 27 JUN | Energy Division | |
| 83 | Make Presentation on Outline Topics | 07 JUL | Stakeholders | |
| 84 | Discuss/Resolve Issues | 07 JUL | Participants | |
| 85 | List Contested Issues by Party | 07 JUL | Facilitator | |
| 86 | Send Position on Contested Issues to PG&E | 10 JUL | Parties | |
| 87 | Distribute Draft of Workshop Report | 14 JUL | PG&E,SCE,SDG&E | |
| 88 | Provide Comments on Draft to PG&E | 22 JUL | Parties | |
| 89 | File Final Workshop Report with CPUC | 25 JUL | PG&E,SCE,SDG&E | |
| 90 | File Comments on Workshop Report | 11 AUG | Parties | |
| 91 | Customer Info. Data Base | |||
| 92 | Distribute Draft Outline | 03 JUN | PG&E,SCE,SDG&E | |
| 93 | Convene Pre-Workshop Meeting | 10 JUN | SCE | |
| 94 | Arrange Facilities | 23 MAY | SCE | |
| 95 | Send Notice of Meeting to Service List | 30 MAY | SCE | |
| 96 | Prepare Agenda & Distribute | 30 MAY | SCE | |
| 97 | Make Presentation on Outline | 10 JUN | Stakeholders | |
| 98 | Reach Consensus on Final Outline | 10 JUN | Participants | |
| 99 | Distribute Text of Proposal | 16 JUL | Stakeholders | |
| 100 | Convene CPUC-Ordered Workshop | 21 JUL | Energy Division | |
| 101 | Arrange Facilities | 27 JUN | Energy Division | |
| 102 | Serve Notice of Workshop to Service List | 11 JUL | Energy Division | |
| 103 | Make Presentation on Outline Topics | 21 JUL | Stakeholders | |
| 104 | Discuss/Resolve Issues | 21 JUL | Participants | |
| 105 | List Contested Issues by Party | 21 JUL | Facilitator | |
| 106 | Send Position on Contested Issues to SCE | 24 JUL | Parties | |
| 107 | Distribute Draft of Workshop Report | 04 AUG | PG&E,SCE,SDG&E | |
| 108 | Provide Comments on Draft to SCE | 11 AUG | Parties | |
| 109 | File Final Workshop Report with CPUC | 14 AUG | Utilities | |
| 110 | File Comments on Workshop Report | 29 AUG | Parties |
Status Column: - Denotes Completion of Task
* Subject to Review and Approval from Commissioner