Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of the
Sunrise Powerlink Transmission Line Project. Applications for this
project were submitted to CPUC on December 14, 2005 (A.05-12-014)
and August 4, 2006 (A.06-08-010). The Proponent's Environmental
Assessment was filed with the CPUC on August 4, 2006. This
project was approved by the California Independent System Operator
on August 3, 2006. This site provides access to public documents
and information relevant to the CEQA and National Environmental
Policy Act (NEPA) review processes. The CPUC voted on December 18,
2008 to approve the Final Environmentally Superior Southern Route
(see Decision D.08-12-058) and a Notice
of Determination was submitted to the State Clearinghouse. The
Bureau of Land Management (BLM) issued a Record
of Decision approving the same route on January 20, 2009.
JUMP TO:
Mitigation Monitoring, Compliance, and
Reporting Program - Final Report
Mitigation Monitoring Compliance Reports,
Permit Applications, and Other Documents
Construction and Mitigation Monitoring
Mitigation Monitoring Compliance and
Reporting Plan
Notices to Proceed
Construction Monitoring Reports
CPUC Variance Approvals
USFS Variance Approvals
Other Agency Variance Approvals
Determinations of NEPA Adequacy
Helicopter Operations and FAA Compliance
Project Modifications Report
Final EIR/EIS
Recirculated Draft EIR/EIS
Draft EIR/EIS
EIR/EIS Alternatives
Documents Available
Data Requests
Requests for Technical Information Related
to the Draft EIR/EIS
For Additional Information
Final
Mitigation Monitoring, Compliance, and Reporting Program Report
A Final Mitigation Monitoring, Compliance, and Reporting Program
Report has been prepared and can be found here.
The report provides a broad summary of the entire project including
preconstruction review, document approvals, NTPs, variances and
DNAs, construction progress, mitigation monitoring, compliance,
closeout tasks, and restoration as well as operations and maintenance
expectations.
Construction
and Mitigation Monitoring
Construction of the Sunrise Powerlink Project began in September
2010 with the establishment of some construction yards and existing
substation upgrades. Mainline construction began in November 2010.
The Sunrise Powerlink was energized in June 2012. Remaining punch
list work was conducted through June 2013. Ongoing restoration activities
continue. Prior to construction all work was approved under segmented
Notices to Proceed (NTPs) issued by the CPUC, BLM, USFS, or MCAS
Miramar depending on jurisdiction, area, and type of work.
Issuance of NTPs was contingent upon SDG&E compliance with
pre-construction requirements as specified by the approved mitigation
measures and responsible agency permitting requirements. Approved
pre-compliance reports, permits, and other documents are available
in their final form here. All NTPs issued
to SDG&E are noted in the table below.
SDG&E divided the Sunrise Powerlink Project into 25 segments
including several additional work areas, as follows:
Notices to Proceed
|
Segment
|
Description
|
Jurisdiction
|
Type
|
NTP Request Submitted
|
NTP Issued
|
Construction
Authorized*
|
Segment 1 |
Imperial Valley Substation |
BLM |
Substation Upgrades |
BLM request submitted 01/19/11 |
BLM NTP #1 issued 02/3/11
|
02/04/11
|
Segment 2 |
Imperial Valley Substation to Pyramid Mining (MP0
to MP19.2) |
CPUC
BLM |
500 kV Overhead |
CPUC request submitted 11/09/10
for non-federal lands only; 3/28/11; BLM request submitted
03/25/11
|
CPUC NTP #13 issued 01/13/11
for non-federal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 3 |
Pyramid Mining to Mountain Springs Grade (MP19.2
to MP23.2) |
CPUC
BLM |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 4 |
Mountain Springs Grade to Jade (MP23.2 to MP30.3) |
CPUC
BLM |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 5 |
Jade to I-8 (McCain Valley) (MP30.3 to MP39.7) |
CPUC
BLM |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 6 |
I-8 (McCain Valley) to USFS (MP39.7 to MP52.5) |
CPUC
BLM
USFS |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11;
USFS request submitted 07/29/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB);
USFS NTP #1 issued 08/09/11 |
01/20/11
|
Segment 7 |
USFS East (MP52.5 to MP61.3) |
CPUC
BLM
USFS |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11;
USFS request submitted 07/29/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB);
USFS NTP #1 issued 08/09/11 |
01/20/11
|
Segment 8 |
USFS East to Cameron Substation (MP61.3 to MP65.4) |
CPUC
BLM |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 9 |
MP65.4 to MP70.9 |
CPUC
BLM |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 10 |
MP70.9 to MP74.8 |
CPUC
BLM
USFS |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11;
USFS request submitted 07/29/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB);
USFS NTP #1 issued 08/09/11 |
01/20/11
|
Segment 11 |
MP74.8 to MP77.6 |
CPUC
BLM |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 12 |
MP77.6 to MP90.0 |
CPUC
BLM
USFS |
500 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11;
USFS request submitted 07/29/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB);
USFS NTP #1 issued 08/09/11 |
01/20/11
|
Segment 13 |
Suncrest Substation (Modified Route D Substation) |
CPUC |
New 500/230 kV Substation |
10/20/10; 11/09/10
for nonfederal lands only |
CPUC NTP #11 issued 12/15/10 |
12/17/10
|
Segment 14 |
Suncrest Substation to Alpine Boulevard (MP90.0 to
MP92.8) |
CPUC
USFS |
230 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11;
USFS request submitted 07/29/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB);
USFS NTP #1 issued 08/09/11 |
01/20/11
|
Segment 15 |
Alpine Boulevard Underground (MP92.8 to MP99.0) |
CPUC |
230 kV Underground |
10/13/10; 11/09/10
for nonfederal lands only |
CPUC NTP #10 issued 11/23/10 |
11/30/10
|
Segment 16 |
Peutz Valley to El Monte Valley (MP99.0 to MP105.5) |
CPUC
BLM
USFS |
230 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11;
USFS request submitted 07/29/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB);
USFS NTP #1 issued 08/09/11 |
01/20/11
|
Segment 17 |
El Monte Valley to Highway 67 (MP105.5 to MP112.7) |
CPUC
BLM |
230 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 18 |
Highway 67 to Sycamore Canyon Substation (MP112.7
to MP118.1) |
CPUC |
230 kV Overhead |
CPUC request submitted 11/09/10
for nonfederal lands only; BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 19 |
Sycamore Canyon Substation |
CPUC |
Substation Upgrades |
CPUC request not yet submitted;¹ BLM request
submitted 03/25/11 |
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 20 |
Sycamore to Elliot 69 kV Reconductor |
CPUC |
69 kV Reconductoring |
CPUC request submitted 11/09/10;
BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 21 |
Sycamore to Scripps 69 kV Reconductor |
CPUC |
69 kV Reconductoring |
CPUC request submitted 11/09/10;
BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 22 |
Sycamore to Pomerado 69 kV Reconductor |
CPUC |
69 kV Reconductoring |
CPUC request submitted 11/09/10;
BLM request submitted 03/25/11
|
CPUC NTP #13 issued 01/13/11
for nonfederal lands only; modified 02/24/11;
BLM NTP #2 issued 04/04/11 (19.9MB) |
01/20/11
|
Segment 23 |
South Bay Substation Upgrades |
CPUC |
Substation Upgrades |
02/08/10 |
CPUC NTP #2 issued 04/29/10, updated 08/3/10 |
09/17/10
|
Segment 24 |
Encina Switchyard Upgrades |
CPUC |
Substation Upgrades |
05/26/10 |
CPUC NTP #6 issued 09/28/10 |
10/15/10
|
Segment 25 |
San Luis Rey Substation Upgrades |
CPUC |
Substation Upgrades |
02/04/10 |
CPUC NTP #1 issued 04/28/10, updated 08/3/10 |
09/17/10
|
N/A |
White Star Telecomm Site |
CPUC |
Telecomm Site |
05/28/10 |
CPUC NTP #7 issued 09/28/10 |
10/08/10
|
N/A |
Pomerado Substation Upgrade
(part of PMR submittal) |
CPUC |
Substation Upgrades |
06/09/10 |
CPUC NTP #8 issued 09/28/10 |
|
N/A |
Scripps Substation Upgrade
(part of PMR submittal) |
CPUC |
Substation Upgrades |
06/09/10 |
CPUC NTP #9 issued 09/28/10 |
|
Construction Yards and Other Workspace
|
Alpine Yard 18, Town of Alpine |
CPUC |
Construction Yard |
02/26/10 |
CPUC NTP #3 issued 05/20/10, updated 08/3/10 |
09/17/10
|
Alpine Yard 18A, Town of Alpine |
CPUC |
Construction Yard |
01/26/10 |
CPUC NTP #4 issued 05/28/10, updated 08/3/10 |
09/17/10
|
Rough Acres Phase I Yard, Boulevard
area, San Diego County |
CPUC |
Construction Yard |
02/18/10 |
CPUC NTP #5 issued 09/28/10 |
10/06/10
|
Rough Acres Phase II Yard, Boulevard area,
San Diego County
|
CPUC |
Construction Yard |
11/29/10 |
CPUC NTP #12 issued 12/28/10
|
Not yet authorized
|
*Compliance with all remaining pre-construction mitigation
measures and NTP conditions satisfied
The CPUC, in conjunction with SDG&E, BLM, USFS, and other Responsible
Agencies, drafted a Mitigation Monitoring Compliance and Reporting
Program (MMCRP) to ensure compliance with mitigation measures approved
in the Final EIR/EIS, as well as with the terms and conditions associated
with the BLM right-of-way. A current version of the MMCRP document
and attachments, including a map
of the approved route with segments, is found here.
CPUC Environmental Monitors (EMs) assisted the CPUC, BLM, and USFS
by monitoring construction activities to ensure that they were conducted
in accordance with approved mitigation measures and permit conditions.
Weekly reports documenting construction activities and compliance
are posted here.
As defined by the MMCRP, at various times throughout project construction,
needs for extra workspace or micrositing changes were identified.
Similarly, minor changes to the project requirements (e.g., mitigation
measures, specifications, etc.) were needed to facilitate construction
(e.g., nighttime construction in response to a planned power outage).
The CPUC Project Manager, along with the CPUC EMS, implemented the
variance procedures defined in the MMCRP to evaluate each proposed
project change for its potential for creating significant environmental
effects to determine whether supplemental CEQA and/or NEPA review
was required. CPUC Variance Requests processed are provided in the
table below.
CPUC Variance Approvals
|
Variance
Request
|
Date
Requested
|
Date
Issued
|
Segment
|
Description |
#1
|
11/04/10
|
|
N/A
|
Thomas Yard, Imperial County |
#2
|
12/22/10
|
|
N/A
|
Sycamore Estates Construction Yard. Comments submitted
to SDG&E 01/06/11. |
#3
|
01/06/11
|
|
All
|
Variance from Mitigation Measure B-8a
to allow limited tree trimming to occur between January 1
and September 15. |
#3 MOD
|
01/21/11
|
|
All
|
Allow limited vegetation clearing between January 15
and September 15 |
#4
|
01/13/11
|
|
N/A
|
Helicopter Temporary Landing Pad area at the Alpine
Regional Field Offices |
#5
|
02/01/11
|
|
Link 3, Segment 13
|
Site improvements at the Wilson Construction Yard
and along Bell Bluff Trail |
#6
|
02/01/11
|
|
Link 5, Segment 16
|
Variance from Mitigation Measure H-1a
(CC) to allow work outside of the dry season |
#7
|
02/11/11
|
|
Link 3, Segment 13
|
Expand work limits along Bell Bluff Truck Trail |
#8
|
03/02/11
|
|
Link 2
|
Alternative access route to structure EP27 |
#9
|
03/29/11
|
|
All
|
Variance from Mitigation Measure N-1a
and expanded workdays/hours |
#10
|
04/05/11
|
|
Link 4
|
Expand work space north of Viejas Creek Bridge |
#11
|
04/06/11
|
|
Link 1
|
Add additional 200-ft-by-150-ft extra workspace east
of structure EP 215 |
#12
|
04/15/11
|
|
Link 1
|
Add turnaround along the access road to Structure
EP 220-1 |
#13
|
04/25/11
|
|
Link 1
|
Request to add communication shelters near EP215
and EP54-1 |
#13 MOD
|
05/06/12
|
|
Link 1
|
Alter two previously approved telecom shelter configurations. |
#14
|
04/28/11
|
|
Projectwide
|
Variance from the approved Construction Yard Visual
Screening Plan |
#15
|
05/12/11
|
|
Link 2
|
Alternate reroutes along approved the access road
to structure EP84 |
#16
|
05/16/11
|
|
Link 4
|
Request to use four vehicle equipment parking areas
in Link 4 |
#17
|
05/18/11
|
|
Segment 24
|
Modification to the driveway at the Encina Substation |
#18
|
06/27/11
|
|
Link 1
|
Installation of gates along a number of project access
roads in the Jacumba area |
#19
|
06/27/11
|
|
Rough Acres Yard
|
Temporary installation of a foundation and towers
at the yard site |
#20
|
07/11/11
|
|
Link 5
|
Modification of a temporary access route to pull
site between CP 48-2 and CP 49-1,
addition of a pull site along the access road between CP 49-1
and CP 50-1 and addition of a site approximately
600 feet south of CP 51-2 to stockpile soil |
#21
|
07/07/11
|
|
Link 1
|
Permits workspace and access for guarding of facilities
near GS-NF-37 and GS-BLM-4/GS-NF-41 |
#22
|
07/15/11
|
|
Link 1
|
Requests use of the Fromm construction yard |
#23
|
08/15/11
|
|
Links 1, 2, and 5
|
Use of landing platforms and tower staging access
pads |
#24
|
08/25/11
|
|
Link 3
|
Vegetation clearing at the Suncrest Substation for
fire safety |
#25
|
09/01/11
|
|
Links 1, 2, and 5
|
Prolonged use of previously approved TEWS areas |
#26
|
09/16/11
|
|
Link 2
|
Tank stand placement adjacent to Barrett Substation |
#27
|
09/20/11
|
|
Link 1
|
Two extra workspace locations near Mountain Springs
Grade |
#28
|
10/31/11
|
|
Link 3
|
Request to work during red flag warning days at the
Suncrest Substation |
#29
|
10/21/11
|
|
Links 1, 2, and 5
|
Guard structure installations |
#30
|
11/01/11
|
|
Links 1, 2, and 5
|
Temporary parking and turnaround areas |
#30 MOD #1
|
02/09/12
|
|
CP 75, Overhead
|
Parking area long-lining |
#31
|
11/08/11
|
Rescinded
|
Links 1, 2, and 5
|
Variance to NTP #13 Condition #37 regarding work
practices during precipitation events |
#32
|
11/16/11
|
|
Links 1, 2, and 5
|
Guard structure installations and pull site modifications |
#33
|
11/28/11
|
|
Links 1, 2, and 5
|
Temporary TSAP and pull site modification |
#34
|
11/29/11
|
|
Projectwide
|
Mitigation Measure B-7h, Eagle Buffers |
#35
|
12/22/11
|
|
Link 5
|
Modify Access Road to Tower CP59 |
#36
|
01/20/12
|
|
Overhead
|
Vegetation clearance |
#37
|
01/20/12
|
|
Overhead
|
Anchor block placement |
#37 Clarification
|
|
|
|
|
#38
|
02/10/12
|
|
Segment 5
|
Install a gate near CP55 |
#39
|
02/10/12
|
Rescinded
|
Segment 4A
|
Pull-site CP23 restoration |
#40
|
03/20/12
|
|
Segment 5
|
Use of an area near GS-NF-7 for staging |
#41
|
04/17/12
|
|
Segment 5
|
Driveway improvements |
#42
|
05/09/12
|
Rescinded 05/19/12
|
Links 1, 2, and 5
|
Placement of temporary concrete block anchors outside
of three approved tower work areas |
#43
|
09/05/12
|
|
Projectwide
|
Leaving in place project improvements at five construction
yards to accomodate landowner requests |
#44
|
09/06/12
|
|
Links 4 and 5
|
Permanent use of two TSAPs for telecommunications
equipment and designation of temporary TSAP as permanent |
#45
|
09/07/13
|
|
Link 1
|
Converts temporary access road to permanent |
In July 2010 the U.S. Forest Service's Supplemental
Information Report (SIR) acknowledged the Final Environmentally
Superior Southern Route as well as changes in the proposed action.
On Cleveland National Forest (CNF) lands the USFS evaluated and
provided variance review and approval. USFS Variance Requests processed
are provided in the table below.
USFS Variance Approvals
|
Date
Issued
|
Segment
|
Description |
|
USFS lands
|
Conduct work until 1:00pm on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
08/25/11
|
Link 2
|
Request for work sites along La Posta Road |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
10/28/11
|
USFS lands
|
Request for work sites, addition of a subcontractor,
and insecticide use |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
Dec 2011
|
Eagle Buffer areas
|
Work in eagle breeding season |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
01/19/12
|
USFS Lands
|
Work on PAL fire danger days |
|
USFS lands
|
Work on PAL fire danger days |
02/02/12
|
USFS lands
|
Work on PAL fire danger days |
02/08/12
|
USFS lands
|
Extension of vegetation clearing, TSAP
and access road revision, temporary work areas, helicopter landing
area, and temporary weather station installation. |
02/09/12
|
USFS lands
|
Work on PAL fire danger days |
02/16/12
|
USFS lands
|
Work on PAL fire danger days |
02/23/12
|
USFS lands
|
Work on PAL fire danger days |
03/01/12
|
USFS lands
|
Work on PAL fire danger days |
03/08/12
|
USFS lands
|
Work on PAL fire danger days |
03/08/12
|
USFS lands
|
Sunday work |
03/19/12
|
USFS lands
|
Sunday work |
03/22/12
|
USFS lands
|
Work on PAL fire danger days |
03/29/12
|
USFS lands
|
Work on PAL fire danger days |
|
USFS lands
|
Concurrence that Bell Bluff and Thing
Valley golden eagle nests are inactive - permission to enter
buffer areas |
04/12/12
|
USFS lands
|
Work on PAL fire danger days |
04/26/12
|
USFS lands
|
Work on PAL fire danger days |
05/10/12
|
USFS lands
|
Work on PAL fire danger days |
05/20/12
|
USFS lands
|
Work on PAL fire danger days |
05/31/12
|
USFS lands
|
Work on PAL fire danger days |
06/04/12
|
USFS lands
|
Sunday and holiday work |
06/07/12
|
USFS lands
|
Work on PAL fire danger days |
06/14/12
|
USFS lands
|
Work on PAL fire danger days |
From time to time, local jurisdictions issued variances from a
local ordinance or regulation that it administers. Variance requests
processed to date are provided in the table below.
Other Agency Variance Approvals
|
Agency |
Variance
|
Date
Requested
|
Date
Issued
|
Segment
|
Description |
County of Imperial |
#1
|
10/06/10
|
|
Link 1
|
Extended work hours |
County of San Diego |
#2
|
03/28/11
|
|
Link 4
|
Traffic control permit, Alpine Boulevard |
County of San Diego |
#3
|
09/30/11
|
|
Various
|
Alternative construction work hours and days of work,
Sundays 10/16/11 through 11/27/11 plus Friday 11/25/11 |
County of San Diego |
#3
amended
|
|
|
Various
|
Amendment to variance 3973-11-8-008
(NV) restricting Sunday work at some locations |
City of San Diego |
#4
|
|
|
Link 5
|
Sunday construction at Stonebridge Parkway |
County of San Diego |
#5
|
02/01/12
|
|
East County locations
|
Work on 8 Sundays between 03/25/12 and 05/20/12 |
SDG&E submitted a number of micrositing changes to the approved
Project on BLM lands. In response, Determination of NEPA Adequacy
(DNA) analyses were conducted. Please see the table below.
Determinations of NEPA Adequacy
|
DNA
Request
|
Date
Requested
|
Date
Issued
|
Segment
|
Description |
PMR DNA
|
|
|
Projectwide
|
PMR modifications (see PMR section
below) |
BLM NTP #2 DNA
|
|
|
Links 1, 2, and 5
|
Changes submitted and approved under BLM
NTP #2 (19.9MB) |
#1
|
06/22/11
|
|
Links 1, 2, and 5
|
Micrositing changes to the approved project on BLM
lands |
#2
|
10/21/11
|
|
Overhead
|
Micrositing |
#3
|
02/08/12
|
|
Overhead
|
Anchor block micrositing |
#4
|
11/09/12
|
|
CP60/EP146 |
Permanent use of TSAPs and placement of radio communications
facilities |
The following table provides the FAA authorizations granted to
SDG&E for use of the sky crane from the project construction
yards for tower construction activities. In addition, the CPUC incident
response letter to two sky crane related incidents is also provided.
On September 27, 2011, the CPUC issued a Stop
Work Order affecting project helicopters, pending resolution
of issues. On October 4, 2011, the CPUC determined that the
issues had been resolved and notified SDG&E
that it could resume helicopter operations.
Project
Modifications Report
Determination: The CPUC and BLM have published the CEQA
and NEPA Determination on SDG&E's proposed Project Modifications;
the supporting documents are available here.
After careful review of the proposed modifications, as documented
in the Determination Memorandum and BLM Determination of NEPA Adequacy
and in accordance with the CEQA and NEPA requirements, the CPUC
and BLM have determined that the changes to the Sunrise Powerlink
Project are within the scope of the Certificate of Public Convenience
and Necessity and Record of Decision issued by the CPUC and BLM
respectively.
Background: After the Final Environmentally Superior Southern
Route was approved by CPUC in December 2008 and BLM in January of
2009, SDG&E began the process of completing final project design
and engineering. As is common, some project components were modified
as engineering was completed. Modifications result from compliance
with adopted mitigation measures requiring resource avoidance to
minimize or avoid environmental impacts and final engineering design
requirements. In addition, some project components have been relocated
to accommodate landowner location preferences where possible in
compliance with mitigation requirements. As a part of this process,
SDG&E has been working with landowners regarding project components
and transmission line routes within their properties.
On January 22, 2010, SDG&E submitted to CPUC and BLM an internal
administrative draft of its Project Modification Report (PMR) that
defined changes made to the project along the entire route after
publication of the Final EIR/EIS. The document explained the reason
for each change, and presented the comparative environmental impacts
of the project components analyzed in the Final EIR/EIS and those
presented in the PMR. All changes included in the report were reviewed
by the lead agencies, CPUC and BLM, along with the cooperating,
responsible and resource agencies. The CPUC compiled and submitted
comments to SDG&E from the EIR/EIS Team and other agencies to
ensure that the PMR document included sufficient information to
make a determination for each reroute. SDG&E has since incorporated
comments, conclusions, and made required changes.
On May 14, 2010, SDG&E submitted to CPUC and BLM a final Project
Modifications Report that defines changes made to the project
along the entire route after publication of the Final EIR/EIS. Similar
to the administrative draft PMR, the final PMR document explains
the reason for each change, and presents the comparative environmental
impacts of the project components analyzed in the Final EIR/EIS
and those presented in the PMR. The final PMR document is found
here.
The CPUC accepted public comments on the Final PMR from May 14
to June 7, 2010, and reviewed all comments while evaluating
the proposed modifications.
Final EIR/EIS
The Final EIR/EIS was released to the public on October 13,
2008. The Final EIR/EIS is available here
and is also available at numerous area libraries
and government offices. Copies of the Executive Summary of the
Final EIR/EIS along with a DVD of the complete document may be requested.
CPUC and BLM also have a limited number of copies of the complete
four-volume Final EIR/EIS document available to the public. Requests
for documents should be made to the CPUC. Contact information appears
at the end of this page.
The Notice of Availability provides
further information on the approval processes for CPUC and BLM.
Pursuant to NEPA requirements, the Final EIR/EIS and Proposed Land
Use Plan Amendment will be available for review for 30 calendar
days from the date the Environmental Protection Agency (EPA) publishes
the Notice of Availability (NOA) in the Federal Register, which
is expected to occur on October 17, 2008. The review period
would end on November 15, 2008.
Copies of the Executive Summary of the Final EIR/EIS along with
a DVD of the complete document may be requested. CPUC and BLM also
have a limited number of copies of the complete four-volume Final
EIR/EIS document available to the public. Requests for documents
should be made to the CPUC. Contact information appears at the end
of this page.
Draft
EIR/EIS
CPUC and BLM published the Draft EIR/EIS in January 2008. Please
note that the Final EIR/EIS (described above) includes the entire
text of the Draft EIR/EIS, modified where necessary in response
to comments on the Draft EIR/EIS. The original text of the Draft
EIR/EIS document is available here.
EIR/EIS
Alternatives
Throughout 2007, CPUC and BLM gathered information on alternatives
to the proposed Sunrise Powerlink Project through an extensive public
involvement process. Information and documents from that process
are available here.
Documents
Available
In addition to the EIR/EIS, other documents that were published
during the CEQA and NEPA processes are available here.
Documents and letters that were compiled following publication of
the Final EIR/EIS, such as SDG&E Biological Assessment, USFWS
Biological Opinion, BLM Section 106 Programmatic Agreement, and
appeals to the BLM Interior Board of Land Appeals, are also included.
In response to concerns from the Lakeside community, a fact sheet
that summarizes past public notification and consideration of alternative
routes in the community of Lakeside is available here
(posted February 24, 2009). A similar fact sheet on public
notification was prepared for the Town of Alpine in January 2010
and is available here.
Data
Requests
The EIR/EIS Team submits Data Requests to SDG&E and other entities
when it needs specific information to support EIR/EIS preparation.
These requests are available here at
the time they are issued.
Requests for
Technical Information Related to the Draft EIR/EIS
During the 90-day public comment period on the Draft EIR/EIS, various
parties submitted requests for technical information related to
that document. The information provided is available here.
For
Additional Information
The CPUC's Project Manager is:
Billie Blanchard, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-2068
Fax (415) 703-2200
Email: bcb@cpuc.ca.gov
|