NTP #/
Permit
|
Date Requested
|
Date Issued
|
Segment
|
Description
|
WORK PACKAGE 1 - SEGMENTS 4, 5, AND 10
|
Segment 4
|
|
1/13/10
|
2/11/10
|
4
|
Yard 28
|
|
7/28/10
|
8/20/10
|
4
|
Work Package 1 Contractor Yards
|
|
8/25/10
|
9/03/10
|
4
|
Partial Segment 4 Transmission Line work associated with LADWP
outage
|
|
8/30/10
|
9/13/10
|
4
|
Segment 4 Transmission Line
|
|
11/15/12
|
11/20/12
|
4
|
Installation of a transition pole outside of Whirlwind Substation
|
|
10/29/10
|
11/12/10
|
4
|
Avenue F Contractor Yard
|
|
5/16/11
|
6/07/11
|
4
|
Modifications for the Midway-Vincent #3 Transmission Line
|
Segment 5
|
|
1/13/10
|
2/11/10
|
5
|
Yard 28
|
|
7/28/10
|
8/20/10
|
5
|
Work Package 1 Contractor Yards
|
|
8/13/10
|
9/10/10
|
5
|
Segment 5 Transmission Line
|
|
3/08/11
|
3/14/11
|
5
|
Modification of FOC alignment
|
|
6/16/11
|
6/21/11
|
5
|
Additional disturbance areas for grading limits in 5 locations
|
|
6/16/11
|
6/24/11
|
5
|
Temporary additional workspace near Tower 20
|
|
10/18/11
|
10/25/11
|
5
|
Relocate CT 68 and associated extra work space
|
|
3/23/12
|
3/30/12
|
5
|
Additional disturbance areas for drainage drain installation
|
|
3/14/12
|
4/2012
|
5
|
Sagebrush Interset Towers
|
|
3/14/12
|
4/18/12
|
5
|
Installation of two H-frame structures within the Sagebrush alignment
to allow for clearance of TRTP conductor
|
|
7/27/12
|
8/13/12
|
5
|
Installation of guard rails at Tower 19
|
|
9/17/12
|
9/17/12
|
5
|
Fencing for retaining wall at Tower 42
|
|
12/19/12
|
12/20/12
|
5
|
Stormwater Drains Towers 19 and 35
|
|
6/25/14
|
7/17/14
|
5
|
Additional MacCarthy drain installation at four locations
|
|
10/29/10
|
11/12/10
|
5
|
Avenue F Contractor Yard
|
|
5/16/11
|
6/07/11
|
5
|
Modifications to the Midway-Vincent #3 Transmission Line
|
Segment 10
|
|
1/13/10
|
2/11/10
|
10
|
Yard 28
|
|
7/28/10
|
8/20/10
|
10
|
Work Package 1 Contractor Yards
|
|
10/29/10
|
11/12/10
|
10
|
Avenue F Contractor Yard
|
|
10/08/10
|
11/30/10
|
10
|
Segment 10 Telecom
|
|
4/19/11
|
5/06/11
|
10
|
Changes to Segment 10 Telecom route.
|
|
6/17/11
|
6/24/11
|
10
|
Additional trenching and vault placement along Oak Creek Road for
Segment 10 Telecom
|
|
1/03/11
|
3/08/11
|
10
|
Segment 10 Transmission Line
|
|
10/13/11
|
10/21/11
|
10
|
Relocation of Tower 39, in line shift
|
|
11/01/11
|
11/10/11
|
10
|
Additional guard pole and turning radii locations
|
|
11/14/11
|
11/21/11
|
10
|
Modify road near CT 25
|
Segment 9 - Substations
|
|
1/28/10
|
3/10/10
|
9
|
Vincent Substation Expansion
|
|
9/18/14
|
10/07/14
|
9
|
Vincent Substation upgrades associated with 500 kV Underground.
|
|
4/09/10
|
4/19/10
|
9
|
Changes to Substation components
|
|
9/24/10
|
10/2010
|
9
|
Vincent Substation Control Building
|
|
11/22/10
|
12/14/10
|
9
|
Section of road widening and riprap extension for the Vincent Substation
expansion
|
|
6/22/10
|
1/14/11
|
9
|
Whirlwind Substation
|
|
12/10/10
|
1/2011
|
9
|
Whirlwind Substation Modifications
|
|
3/01/11
|
3/17/11
|
9
|
Bridge construction to access Whirlwind Substation
|
WORK PACKAGE 3 - SEGMENTS 7 & 8
|
Segment 7
|
|
3/09/10
|
4/01/10
|
7
|
Rancho Vista Yard
|
|
1/27/10
|
4/26/10
|
7
|
Segment 7 and 8 Cell Sites
|
|
1/27/10
|
4/30/10
|
7
|
Segment 7 Telecom
|
|
3/29/10
|
5/12/10
|
7
|
Mesa Materials Storage Yard
|
|
7/21/10
|
7/29/10
|
7
|
Segment 7 Contractor Yards
|
|
8/10/10
|
9/24/10
|
7
|
Segment 7 Transmission Line
|
|
1/13/11
|
2/25/11
|
7
|
Segment 7
|
|
7/06/11
|
7/19/11
|
7
|
Access road additions and modifications, grading limit modifications,
and OPGW splice sites
|
|
7/15/11
|
7/19/11
|
7
|
Removal of existing overhead ground wire and skywrap and replacement
with fiber optic ground wire
|
|
2/24/12
|
3/01/12
|
7
|
Extra work space at M32-T4
|
|
3/12/13
|
3/20/13
|
7
|
Recreational trail reroute at Towers M39-T4 and M39-T5
|
|
7/08/13
|
8/07/13
|
7
|
Expansion of grading area to construct access road to Tower M27-T3
in Duarte
|
|
9/10/13
|
9/25/13
|
7
|
Access roads to three locations in Segment 7
|
|
12/18/13
|
1/17/14
|
7
|
Changes to permanent grading impacts at M27-T2
|
|
6/06/14
|
6/20/14
|
7
|
Erosion repairs on access road to Tower M27-T3
|
|
1/17/15
|
1/30/15
|
7
|
U.S. Army Corps of Engineers "give back" areas
|
|
9/01/15
|
10/14/15
|
7
|
Erosion repairs associated with Structures M27-T3 and M41-T5, and
permanent grading near Structure M40-T4
|
|
10/24/17
|
10/31/17
|
7
|
Erosion repairs associated with Structure
M27-T3 |
|
10/13/10
|
10/15/10
|
7
|
Potrero Grande Contractor Yard
|
Segment 8
|
|
3/09/10
|
4/01/10
|
8
|
Rancho Vista Yard
|
|
1/27/10
|
4/26/10
|
8
|
Segment 7 and 8 Cell Sites
|
|
3/29/10
|
5/12/10
|
8
|
Mesa Materials Storage Yard
|
|
5/12/10
|
5/28/10
|
8
|
Segment 8 Telecommunications
|
|
8/20/10
|
8/20/10
|
8
|
Minor re-routes to Segment 8 Telecom
|
|
4/27/10
|
6/04/10
|
8
|
Segment 8 Contractor Yards
|
|
5/08/10
|
8/12/10
|
8
|
Segment 8 Transmission Line, Chino Hills Phase I
|
|
9/07/11
|
9/12/11
|
8
|
Increased grading limits for access road to Towers M57-T1 and M24-T1A
|
|
1/03/12
|
1/05/12
|
8
|
Relocation of a distribution pole and use of associated disturbance
areas
|
|
12/19/11
|
1/17/12
|
8
|
Structure additions or modifications, and associated work areas/access
|
|
5/28/13
|
6/18/13
|
8
|
Modification of access road from Everest Drive to M59-T2
|
|
10/21/14
|
10/28/14
|
8
|
Permanent grading changes to access road to Tower M59-T3
|
|
7/19/10
|
8/24/10
|
8
|
Segment 8 Transmission Line, Phase 2 and 3
|
|
8/30/11
|
9/2011
|
8
|
Replacement of TSPs with LSTs on Segment 8, Phase 3
|
|
6/22/12
|
7/23/12
|
8
|
Addition of Towers M0-T9A and M66-J8, Segment 8 Phase 3
|
|
1/31/13
|
4/30/13
|
8
|
Access road and structure shifts
|
|
2/20/15
|
4/10/15
|
8
|
66 kV, Distribution, Telecommunications Line Relocation and
Lowering in the City of Ontario
|
|
9/23/16
|
10/04/16
|
8
|
Schaefer Avenue 68 kV and distribution lines
relocation |
|
11/10/10
|
1/13/11
|
8
|
Segment 8 West, Phase 4 Transmission Line
|
|
6/15/11
|
6/20/11
|
8
|
Access road to M3-T3A and M48-T1
|
|
11/14/11
|
11/17/11
|
8
|
Lower 66 kV line at I-605 shoofly
|
|
11/30/11
|
12/15/11
|
8
|
Shift in M52-T2 structure location and associated extra work space
and access roads
|
|
3/20/12
|
4/16/12 (5.5MB)
|
8
|
Access road and structure additions and modifications
|
|
4/03/12
|
4/24/12
|
8
|
Access roads on Rose Hills and Sanitation District roads
|
|
5/22/12
|
6/05/12
|
8
|
Curve widening along access roads between M49-T2 and M51-T5
|
|
11/28/12
|
12/06/12
|
8
|
Permanent access road leading to M49-T2
|
|
3/05/13
|
5/07/13
|
8
|
M43-T3/M8-T1A access road
|
|
2/11/13
|
6/05/13
|
8
|
Turn-out expansions on Phase 4
|
|
5/16/13
|
6/11/13
|
8
|
Access road at M44-T3/M7-T2B
|
|
4/15/14
|
5/14/14
|
8
|
Changes to grading and contractor work limits at M43-T3
|
|
9/01/15
|
10/07/15
|
8
|
Erosion repair and permanent grading
|
|
10/02/15
|
10/28/15
|
8
|
USACE give back areas
|
|
12/24/15
|
1/22/16
|
8
|
Erosion repair at M43-T3
|
|
7/21/17
|
8/11/17
|
8
|
Erosion repair at M49-T1 |
|
11/19/10
|
1/13/11
|
8
|
Fullerton Contractor Yard
|
|
7/25/12
|
7/30/12
|
8
|
Geotechnical investigations in Chino Hills for Chino Hills Underground
|
|
07/29/13
|
08/22/13
8/23/13
(revised)
|
8
|
Removal of towers and foundations from Chino Hills Underground
alignment.
|
|
4/15/14
|
5/30/14
|
8
|
Chino Hills Underground - Vegetation clearing and temporary fence
installation
|
|
6/02/14
|
9/19/14 (Revision 2) (5.0MB)
|
8
|
Chino Hills Underground - Conduit installation. (Additional maps
provided 10/25/14 for vault engineering changes.)
|
|
9/18/14
|
10/07/14
|
8
|
Vincent Substation equipment upgrades for Chino Hills 500 kV Underground
|
|
5/08/15
|
5/20/15
|
8
|
Mira Loma Substation equipment upgrades for Chino Hills 500 kV
Underground
|
|
5/20/15
|
6/02/15
|
8
|
New underground telecom duct bank for Chino Hills 500 kV Underground
|
|
5/26/17
|
8/30/16
|
8
|
Vault cluster fencing |
|
4/07/17
|
4/18/17
|
8
|
ROW Fencing |
|
11/17/14
|
2/10/15 (Revision 1)
|
8
|
Eastern and Western Transition Station construction in Chino Hills
|
|
3/05/15
|
3/25/15
|
8
|
Telecom and distribution connections to Transition
Stations |
|
4/14/16
|
7/28/16
|
8
|
Barrier Screen at ETS |
|
10/31/18
|
11/20/18
|
8
|
Installation of final componenet of the Mira Loma-Vincent 500 kV
fault locating system at the East and West Transition Stations and
extension of the north barrier screen at the East Transition Station
|
Segments 7 & 8 66 kV
|
|
4/08/10
|
8/03/10
|
7/8 66 kV
|
Segments 7/8 66 kV re-route and relocation
|
|
12/21/10
|
January 2011
|
7/8 66 kV
|
Distribution line realignment and addition
of four distribution poles |
|
1/28/11
|
2/04/11
|
7/8 66 kV
|
Replace 14 existing wooden H-frames poles with steel H-frame poles
in order to support the double 66 kV circuit
|
|
3/15/11
|
3/22/11
|
7/8 66 kV
|
Removal and replacement of 21 wood poles with lightweight steel
poles within Rio Hondo Substation
|
|
4/22/11
|
4/29/11
|
7/8 66 kV
|
Underground telecom
|
|
4/22/11
|
5/03/11
|
7/8 66 kV
|
Chino pole removals
|
|
5/23/11
|
6/02/11
|
7/8 66 kV
|
Realignment of approximately 500 feet of 66 kV underground
transmission line
|
|
7/20/11
|
7/25/11
|
7/8 66 kV
|
Dusty underground connection
|
|
8/26/11
|
9/01/11
|
7/8 66 kV
|
New Fiber Optic Underground trench
|
|
8/29/11
|
9/08/11
|
7/8 66 kV
|
Insulator replacement in Montebello Hills
|
|
09/28/11
|
10/21/11
|
7/8 66 kV
|
Additional work areas and poles
|
|
10/31/11
|
11/04/11
|
7/8 66 kV
|
Additional underground trenching near Edison Avenue
|
|
11/02/11
|
11/09/11
|
7/8 66 kV
|
Pole removal along Siphon Road
|
|
12/13/11
|
12/22/11
|
7/8 66 kV
|
San Gabriel Dip extra work space and vault shift
|
|
1/31/12
|
3/01/12
|
7/8 66 kV
|
Removal and installation activities at Pole No. 1431134E
|
|
8/06/12
|
8/13/12
|
7/8 66 kV
|
Structure installation, various reframing, installation of ground
and guy wire, and shift activities.
|
|
12/09/13
|
12/18/13
|
7/8 66 kV
|
Additional duct bank installation and work areas for telecom relocation
in Chino.
|
|
11/18/14
|
12/04/14
|
7/8 66 kV
|
New underground duct bank and rerouting of telecom line in Chino.
|
WORK PACKAGE 2 - SEGMENTS 6 & 11
|
Segment 6
|
|
11/18/10
|
12/09/10
|
6
|
Vincent North Material Yard
|
|
6/10/11
|
6/24/11
|
6 (& 11)
|
Telephone and IT installation at Vincent North Material Yard
|
|
4/06/15
|
7/07/15
|
6 (& 11)
|
Retain improvements within Yard.
|
|
11/18/10
|
12/09/10
|
6
|
Vincent South Material Yard
|
|
12/22/10
|
01/11/11
|
6
|
Material Yard 75
|
|
4/22/11
|
5/06/11
|
6
|
Construction Yard 58
|
|
5/06/11
|
5/13/11
|
6
|
San Gabriel Yard
|
|
9/12/11
|
11/09/11
|
6A
|
Construction of Towers 1-35 on private (non-ANF) lands
|
|
1/18/12
|
2/08/12
|
6A
|
Additional work areas outside of ANF lands
|
|
8/28/12
|
9/11/12
|
6A
|
Rev 4 engineering changes, non-ANF lands
|
|
2/21/13
|
3/29/13
|
6A
|
Gate replacement/installation
|
|
5/05/14
|
5/14/14
|
6A
|
Gate replacement/installation
|
|
2/09/18
|
2/15/18
|
6A
|
Erosion repairs associated with Tower M29-T3 |
|
7/25/18
|
Verbal Approval 7/25/18
|
6A
|
Erosion repairs associated with Tower M29-T3 |
|
12/02/11
|
1/13/12
|
6B
|
Construction of Towers 35-72 on private (non-ANF) lands
|
|
1/26/12
|
5/16/12
|
6C
|
Construction of Towers 72-113 on private (non-ANF) lands
|
|
7/15/13
|
8/05/13
|
6C
|
Modifications to grading area near Tower 113 (non-ANF lands)
|
|
4/08/14
|
4/11/14
|
6C
|
McCarthy drain near Const 113
|
|
7/30/14
|
8/12/14
|
6C
|
Additional McCarthy drain installation near Const 113
|
Segment 11
|
|
11/18/10
|
12/09/10
|
11
|
Vincent North Material Yard
|
|
6/10/11
|
6/24/11
|
11
|
Telephone and IT installation at Vincent North Material Yard
|
|
4/06/15
|
7/07/15
|
11
|
Retain improvements within Yard
|
|
11/18/10
|
12/09/10
|
11
|
Vincent South Material Yard
|
|
12/22/10
|
1/11/11
|
11
|
Material Yard 75
|
|
4/22/11
|
5/06/11
|
11
|
Construction Yard 58
|
|
5/06/11
|
5/13/11
|
11
|
San Gabriel Yard
|
|
6/24/11
|
6/30/11
|
11A
|
Segment 11A Transmission Line Goodrich to Mesa (off ANF)
|
|
1/24/12
|
2/13/12
|
11D
|
Gould and Goodrich Substations
|
|
7/20/12
revised
1/09/13
|
4/25/13
|
11B
|
Construction of Segment 11B, Gould to Goodrich (off ANF). Pending
FAA concurrence.
|
|
8/14/13
|
10/10/13
|
11C
|
Construction of Segment 11C between Vincent and Gould Substations.
|
|
1/07/14
|
3/21/14
|
11C
|
Engineering Changes at M0-T1, CT 2 and 5.
|
WORK PACKAGE 4 - SEGMENT 9 SUBSTATIONS
|
|
6/22/10
|
1/14/11
|
9
|
Whirlwind Substation
|
|
-----
|
6/01/13 (7.7MB)
|
8
|
Chino Hills 500 kV Underground Transmission Line
|
MISCELLANEOUS
|
|
07/17/15
|
12/15/15
|
All
|
Retain improvements at ten TRTP material
and contractor yards (Rodeo North, Racetrack, Avenue F, Yard 28,
Yard 75 South, San Gabriel, Huntington Drive, Potrero Grande,
Strawberry Field, and Mesa). The request does not include yards being
used for 500 kV underground work. |
|
7&8
|
7/25/16
|
6/21/18
|
Exclusion of sites from restoration and off-site
compensation |
ANF PERMITTING - SEGMENTS 1, 6, AND 11
|
|
11/29/07
|
12/14/07
|
1
|
Radio Repeater - installation of a temporary radio repeater site
on Sierra Pelona Ridge to provide communication during construction
activities tied to the project. Improvement installation began Jan.
11
|
|
09/27/07
|
12/14/07
|
1
|
Geotechnical testing - 23 geotechnical borings are authorized on
National Forest lands to provide additional information that will
be used in the design of the transmission towers. Notice to proceed
was signed Jan 31 to begin work the week of Feb. 3
|
|
|
07/14/08
|
1
|
Removal of the 66 kV conductor within the ANF, from Tower
7-3 (near southern Forest boundary) to 16-3 (near Bouquet Reservoir)
Phase I
|
|
|
09/23/08
|
1
|
Removal of the 66 kV conductor within the ANF, Phase II
|
|
|
10/23/08
|
1
|
Construction of the 500 kV transmission line and wreck-out of the
66 kV towers in the ANF, Section 2
|
SUP
|
|
09/21/11
|
6 and 11
|
Electric Transmission Line Permit, Segments 6 and 11
|
NTP
|
|
11/07/11
|
6A
|
Authorization to start construction of Towers CT1-CT35
|
NTP
|
|
01/11/12
|
6B
|
Authorization to start construction of Towers CT35-CT72
|
NTP
|
|
05/14/12
|
6C
|
Authorization to start construction of Towers CT73-CT113.
|
NTP
|
|
04/23/13
|
11B
|
Authorization to start construction of Segment 11B.
|