STATE OF CALIFORNIA
|
These files are in Portable Document Format (PDF). To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your PC. Note: For best results in displaying the largest files (see sizes shown in parentheses below for files larger than 5 MB), right-click the file's link, click "Save Target As" to download the file to a folder on your hard drive, then browse to that folder and double-click the downloaded file to open it in Acrobat. |
Welcome to the California Public Utilities Commission (CPUC) website
for the environmental review of Southern California Edison's (SCE's) Ivanpah-Control
Project ( The Proposed Project will be reviewed under the California Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA). The CPUC is the CEQA lead agency and the Bureau of Land Management (BLM) will be preparing a separate environmental document as the NEPA lead agency. This website provides access to public documents and information relevant to the CEQA environmental review processes. An overview of the proposed Project is provided below. For additional information on the CPUC proceeding, contact the Public Advisor's Office. PROJECT SCOPING: Closed after September 30, 2020 The public scoping period has closed. The Scoping Report summarizes all comments received, and has the following appendices: Appendix A: EIR Notices Project Information The following information was made available during the Scoping Meetings (September 3 and 10, 2020):
DESCRIPTION OF THE PROPOSED PROJECT According to SCE, the Project is needed in order to meet the transmission line safety and reliability requirements defined by the CPUC and the North American Electric Reliability Corporation. The Project would involve the demolition and replacement of some or all of SCE's existing 115 kV transmission lines between the Ivanpah and Control Substations. SCE anticipates that the In its April 2020 Amended Application and PEA, SCE describes that its preferred scope for the IC Project would involve fully rebuilding three subtransmission line segments (i.e., Segments 1, 2 and 3S) while "derating" (i.e., reducing the amount of current that wires are allowed to carry) conductors in other segments (i.e., Segment 3N and Segment 4). Nevertheless, SCE continued to analyze alternative methods for remediating discrepancies on these circuits, even after the Original Application was filed. As a result of that effort, SCE determined that certain methods would accomplish the necessary remediation with less environmental impact than the scope of work described in the Original Application. Therefore, SCE has revised its preferred and proposed scope of work for the IC Project to consist of the following components: SCE proposes to remediate discrepancies along 262 miles of existing 115 kV subtransmission circuits in five segments. Detail of SCE's proposal is provided in Amended PEA Chapters 1 through 3 (15 MB). The proposal includes:
Along distribution circuits, SCE would remove existing distribution conductor and appurtenances and install new distribution conductor and appurtenances on replacement structures. SCE would install new optical groundwire or fiber optic cable to allow telecommunications and system protection, on existing and replacement structures and within and outside of existing substations. At substations, SCE would disconnect the existing conductor and connect the new conductor, connect the telecommunications, and install new cables between existing breakers, relay and protection racks. ENVIRONMENTAL REVIEW Proponent's Environmental Assessment (PEA) and Application SCE filed an application and PEA
for the The CPUC completed a completeness/deficiency review of the April 2020 amended application and PEA in May 2020. This review resulted in the definition of PEA deficiency items that were detailed in a May 4, 2020 letter to SCE. Preparation of the Draft EIR The environmental review process for the COMMENTS & QUESTIONS If you have comments, complaints, or questions regarding the project,
please contact us using the CPUC's Project e-mail: Ivanpah-Control@aspeneg.com
Project voicemail: 800-535-2572 The CPUC's Project Manager is:
John Forsythe, CPUC Project Manager California Public Utilities Commission c/o Aspen Environmental Group 235 Montgomery Street, Suite 640 San Francisco, CA 94104-2920 |
|
This page contains tables and is best viewed with Firefox or Internet Explorer. Please report any problems to the Energy Division web coordinator. |
|
Project Home Page - CPUC
Environmental Information - CPUC Home
|