Welcome to the California Public Utilities Commission (CPUC) website
for the environmental review of the Tehachapi Renewable Transmission
Project (TRTP) in Kern, Los Angeles, and San Bernardino Counties.
Southern California Edison (SCE) submitted an application for a
Certificate of Public Convenience and Necessity (CPCN) for this
project to the CPUC on June 29, 2007. SCE also submitted an
application for a Special Use authorization to the USDA Forest Service.
The project has been reviewed under both the California Environmental
Quality Act (CEQA) and National Environmental Policy Act (NEPA).
This site provides access to public documents and information relevant
to the CEQA and NEPA review processes, as well as information regarding
construction of the Project.
JUMP TO:
Project
Location Maps
Addendum
to Final EIR (7.7MB)
Draft
SEIR/SEIS
Final
SEIR/SEIS
Final
EIR
Final
EIS
Document
Repositories
Address
Lookup
Fact
Sheets
The CPUC certified the Final Environmental Impact Report (EIR)
on December 17, 2009 and subsequently issued Decision
09-12-044 approving the Project.
The USDA Forest Service published a Final EIS for the Project in
September 2010. Following release of the Final EIS, the Forest Service
issued a Record
of Decision (ROD) (13.4MB)
approving the requested Special Use authorization for the Project
on October 4, 2010.
The Approved Project includes a combination of Alternative 2 (SCE's
Proposed Project), Alternative 3 (West Lancaster Alternative), Alternative
6 (Maximum Helicopter Construction in the ANF), and Alternative
7 (66-kV Subtransmission). Additionally, on July 11, 2013 in
Decision
13-07-018, the CPUC granted the City
of Chino Hills' Petition for Modification of Decision 09-12-044
filed October 28, 2011, which includes undergrounding of the
500-kV transmission line in the existing right-of-way (ROW) along
an approximately 3.5-mile portion of the TRTP alignment through
Chino Hills in lieu of the previously approved overhead transmission
line. SCE will now be required to place the subject portion of the
TRTP transmission line underground using a single-circuit, two cable
per phase design (known as Option UG5) using cross-linked polyethylene
(XLPE) cable. This will also include the construction of a ductbank
system and structures for a third cable in the future, if necessary.
The underground portion of the transmission line will run in a southwest
to northeast direction, with the southwest end terminating in a
transition station to be located just west of the end of Eucalyptus
Avenue and the northeast end terminating in a transition station
to be located adjacent to State Route (SR) 71 (Chino Valley Freeway).
The environmental effects of undergrounding the TRTP through Chino
Hills were analyzed in an Addendum to the TRTP Final EIR (provided
below).
The CPUC and USFS also prepared a Supplemental EIR/EIS (SEIR/SEIS)
for the proposed changes requested in SCE's Petition for Modification
of Decision 09-12-044 on the TRTP. The SEIR/SEIS addressed
implementation of the Federal Aviation Administration (FAA) recommendations
including: installation of marker balls on 276 transmission line
spans; installation of aviation lights on 90 transmission structures;
and engineering refinements to reduce the height of 21 structures
within Segment 8 between Chino and Mira Loma Substations utilizing
a combination of shorter tubular steel poles and specially designed
dead-end lattice steel towers, which would result in changing the
previously approved structure type for seven structures. The CPUC
issued a Final Decision (Decision 13-10-062) for the
FAA related changes on October 31, 2013, for non-ANF lands.
A final ROD for the FAA changes on ANF lands was issued by the USFS
on October 17, 2014.
Construction Progress and Mitigation
Monitoring
Construction started in April 2010 with the establishment of some
construction yards and expansion of the existing Vincent Substation
in Acton. Notices to Proceed (NTPs) were issued by CPUC for each
of these activities. The majority of construction started in June/July
2010 as CPUC issued NTPs for each segment and substation of the
Project. As final engineering was completed and as construction
necessitated, minor permanent modifications were made to the Project.
A summary of NTPs and modifications issued for TRTP is provided
here. Issuance of NTPs was contingent upon
SCE's compliance with pre-construction requirements as specified
by the approved mitigation measures and responsible agency permitting
requirements. At times, minor temporary changes were required to
address construction constraints. A summary of these minor temporary
changes is provided here. Each of these requests
was reviewed by CPUC to ensure that no new impacts or increase in
impact severity would result from the requested change. Compliance
plans were developed as required by the mitigation measures and
submitted to the CPUC for review and approval prior to construction.
A listing of major compliance plans requiring CPUC and/or permit
agency review and approval is provided here.
Other responsible agency permits required for construction, and
their amendments, are listed here.
Status of Construction
Construction of TRTP has been completed, and complete Project energization
occurred on December 15, 2017. Post-construction activities
include restoration and Stormwater Pollution Prevention Plan (SWPPP)
compliance as described below.
CPUC Environmental Monitors (EMs) monitored construction activity
since its start to ensure that construction was conducted in accordance
with the approved mitigation measures and permit conditions. Weekly
reports documenting construction and monitoring activities are posted
here.
As construction was completed, SCE has been required to restore
temporary construction disturbance areas. The plans detailing those
restoration efforts are provided here.
CPUC EMs have been monitoring restoration activities and SWPPP compliance
at project disturbance areas. Monthly reports documenting SCE's
restoration activities and SWPPP monitoring can be found here.
For permanent loss of habitat due to TRTP structures and ancillary
facilities, SCE was required to purchase offsite mitigation lands
that would be managed in perpetuity as permanent habitat.
For questions, comments, or complaints related to the TRTP construction,
please contact us by email at the address below. Please include
your name and phone number so that we may contact you for follow-up
clarification.
Contact
Information During Construction:
|
|
Project Background and Description
The Project, as approved, includes new and upgraded transmission
infrastructure along approximately 173 miles of new and existing
ROW from the Tehachapi Wind Resource Area (TWRA) in southern Kern
County south through Los Angeles County and the ANF and east to
the existing Mira Loma Substation in Ontario, San Bernardino County,
California. The major components of Project have been separated
into eight distinct segments (Segments 4 through 11). Under
separate application to the CPUC, SCE previously requested approval
for Segments 1, 2, and 3 of the Antelope Transmission Project. The
major components of the Project are as follows:
- Two new single-circuit 220-kilovolt (kV) transmission lines
traveling in parallel approximately 4 miles over new right-of-way
(ROW) from the Cottonwind Substation (not part of this project)
to the new Whirlwind Substation (Segment 4 - 220 kV).
NOTE: Since approval of the TRTP, the Cottonwind Substation has
not been built; the two projects that were anticipated to connect
to the Cottonwind Substation now connect directly to the Whirlwind
Substation utilizing the two "Cottonwind-Whirlwind"
positions. The two single-circuit 220-kV transmission
lines approved as part of Segment 4 are no longer necessary and
have not been built.
- A new single-circuit 500-kV transmission line, initially energized
to 220 kV, traveling approximately 16.0 miles over new ROW from
the new Whirlwind Substation to the existing Antelope Substation
(Segment 4 - 500 kV).
- Replace approximately 17.4 miles of the existing Antelope-Vincent
220-kV transmission line and the existing Antelope-Mesa
220-kV transmission line with only one new transmission
line built to 500-kV standards in existing ROW between
the existing Antelope Substation and the existing Vincent Substation
(Segment 5).
- Rebuild approximately 31.9 miles of existing 220-kV transmission
line to 500-kV standards from existing Vincent Substation
to the southern boundary of the ANF. This segment includes the
rebuild of approximately 26.9 miles of the existing Antelope-Mesa
220-kV transmission line and approximately 5 miles
of the existing Rio Hondo-Vincent 220-kV No. 2
transmission line (Segment 6).
- Rebuild approximately 15.8 miles of existing 220-kV
transmission line to 500-kV standards from the southern
boundary of the ANF to the existing Mesa Substation. This segment
would replace the existing Antelope-Mesa 220-kV transmission
line (Segment 7).
- Rebuild approximately 33 miles of existing 220-kV transmission
line to 500-kV standards from a point approximately
2 miles east of the existing Mesa Substation (the "San Gabriel
Junction") to the existing Mira Loma Substation (Segment 8A).
This segment would also include the rebuild of approximately 7
miles of the existing Chino-Mira Loma No. 1 line from single-circuit
to double-circuit 220-kV structures (Segment 8B).A
new circuit between Chino Substation and approximately 0.8 mile
west of the Mira Loma Substation (6.4 miles) would also be installed
on the new double-circuit 500-kV structures built
as part of Segment 8A (Segment 8C).
- Removal of twelve former 220 kV tower locations, five 500 kV
Lattice Steel Towers (LSTs) and foundations, and eleven 500 kV
Tubular Steel Poles (TSPs) and foundations within the city of
Chino Hills and Chino to support construction of 500 kV Underground
in place of overhead transmission construction.
- Construct 3.7 miles underground 500 kV transmission, which will
include the installation of 14 cable splice vault clusters, 6
restraint vault sites, and 16 communication vaults. Installation
of approximately 17,000 feet of duct bank, approximately 14,500
feet of bundled High Density Polyethylene (HDPE) conduit via horizontal
directional drilling (HDD), and approximately 20,000 circuit feet
of cable. Replacement of 16 gas pipeline crossings and relocation
of distribution and telecom. Development and construction of an
Eastern and Western Transition Stations, with the installation
of two DC 500 kV LST structures.
- Construct the Whirlwind Substation, a new 500/220-kV
substation located near the intersection of 170th Street and Holiday
Avenue in Kern County near the TWRA (Segment 9).
- Upgrade of the existing Antelope, Vincent, Mesa, Gould, and
Mira Loma Substations to accommodate new transmission line construction
and system compensation elements (Segment 9).
- Build a new 500-kV transmission line traveling approximately
16.8 miles over new ROW between the approved Windhub Substation
(not part of this project) and the new Whirlwind Substation (Segment 10).
- Rebuild approximately 18.7 miles of existing 220-kV
transmission line to 500-kV standards between the
existing Vincent and Gould Substations. This segment would also
include the addition of a new 220-kV circuit on the
vacant side of the existing double-circuit structures of the Eagle
Rock-Mesa 220-kV transmission line, between the existing
Gould Substation and the existing Mesa Substation (Segment 11).
- Install associated telecommunications infrastructure.
Project Location
Maps of the proposed transmission routes can be viewed here.
To find the location of your property in relation to the proposed
transmission routes, click here
and enter your property address.
Additional Project Documents
Addendum
to Final EIR (7.7MB). The
CPUC prepared an Addendum to the October 2009 Final EIR for the
TRTP pursuant to the CEQA (Pub. Res. Code §21000 et seq.) and
the State CEQA Guidelines (14 Cal. Code Regs §15000 et
seq.). In November 2011, the CPUC issued an Assigned Commissioner's
Ruling directing SCE to prepare testimony on new options for the
portion of the TRTP known as Segment 8A that traverses the City
of Chino Hills. In response, testimony was submitted by SCE in January
2012 on options to the approved TRTP in Chino Hills. These options
included alternative routes, different types of overhead structures,
and undergrounding options. In response to the Scoping Memo and
Ruling of Assigned Commissioner issued on July 2, 2012, as
amended, SCE submitted preliminary testimony in December 2012 describing
five underground transmission options for Chino Hills. On February 28,
2013, SCE submitted refined testimony on the underground options.
An Addendum was prepared to address proposed changes to the TRTP
along a portion of Segment 8A in the City of Chino Hills. Specifically,
options have been considered for placing either a 500-kV
single-circuit or 500-kV double-circuit transmission
line underground in an approximately 3.5-mile segment of existing
right-of-way (ROW) through Chino Hills. The CPUC originally approved
the construction of a 500-kV double-circuit overhead
transmission line through this portion of Chino Hills as part of
the TRTP.
Final
EIS. The Final EIS for the TRTP was released by the Forest
Service on September 14, 2010. The Final EIS includes responses
to all comments received on the Draft EIR/EIS, as well as responses
to comments received on the Supplemental Draft EIS. The Final EIS
contains much of the same content as the Final EIR; however, information
and analysis that has not changed substantively from the Final EIR
has not been reproduced in the Final EIS, particularly information
about conditions and impacts on non-federal lands.
Supplemental
Draft EIS. The Forest Service published a Notice
of Intent to prepare a Supplemental Draft EIS in the Federal
Register on February 8, 2010. The Forest Service released the
Supplemental Draft EIS on April 30, 2010. The Supplemental
Draft EIS assessed the changed conditions in the Angeles National
Forest created by the 2009 Station Fire.
General Conformity. The Forest Service prepared a Draft
Conformity Determination for the TRTP. The Draft Conformity Determination
was released for a 30-day public review period, as required under
40 CFR §93.156, on March 22, 2010. Responses to comments
received on the Draft Conformity Determination were incorporated
into the Final
Conformity Determination. The Forest Service approved the Final
Conformity Determination for the TRTP on June 2, 2010.
Final
EIR. The Final EIR was released on October 30, 2009
(Notice
of Availability of the Final EIR). The Final EIR includes responses
to all comments received on the Draft EIR/EIS during the public
review period (February 13 through April 6, 2009).
Draft EIR/EIS. The CPUC and the USDA Forest Service released
the Draft EIR/EIS on February 13, 2009. Revisions to the Draft
EIR/EIS are reflected in the Final EIR (see link above).The Final
EIR contains the entire content of the Draft EIR/EIS along with
responses to comments received on the Draft EIR/EIS during the public
review period.
Notices
Notice of Preparation for the Draft SEIR/SEIS. To initiate
the EIR process, a Notice of Preparation (NOP) was distributed by
the CPUC on September 24, 2012.
The NOP was advertised in local newspapers throughout the Project
area. The Notice of Preparation (English) can be viewed here.
Translated versions of the NOP can be viewed in Chinese,
Spanish,
and Korean.
To initiate the SEIS process, the Forest Service published its
Notice
of Intent to prepare a SEIR/SEIS in the Federal Register on
September 24, 2012.
Notice of Availability of the Draft EIR/EIS. When the CPUC
and the Forest Service published the Draft EIR/EIS, a Notice of
Availability (NOA) was distributed to the public on February 13,
2009. The NOA (English) can be viewed here.
Translated versions of the NOA can be viewed in Chinese,
Spanish,
and Korean.
Notice of Preparation for the Draft EIR/EIS. To initiate
the EIR process, a Notice of Preparation (NOP) was distributed by
the CPUC on August 31, 2007. The NOP (English) can be viewed here.
Translated versions of the NOP can be viewed in Chinese,
Spanish,
and Korean.
Notice of Intent. To initiate the EIS process, the USDA
Forest Service published its Notice
of Intent to prepare an Environmental Impact Statement in the
Federal Register (Volume 72, No. 173, page 51404) on September 7,
2007.
Other Project Documents
Comment Summary Report. The Comment Summary Report and its
appendices, which document and summarize the public meeting that
was held on January 17, 2008, in Brea, CA, are available here.
Scoping Report. The Scoping Report and its appendices, which
document and summarize the public scoping process, including comments
received on the proposed Project, are available here.
Policy Consistency and Plan Amendments Report. The Policy
Consistency and Plan Amendments Report, which provides a review
of relevant federal, State, regional, and local agency plans and
planning documents, is available here
(4.3MB).
Fact Sheets. Several Fact Sheets are available that provide
information on aspects of electrical transmission that frequently
interest the public. These Fact Sheets were provided at all of the
public scoping meetings and are also available here.
Proponent's Environmental Assessment (PEA). As part of its
application to the CPUC, SCE prepared and submitted a Proponent's
Environmental Assessment (PEA), which describes the proposed project,
existing environmental conditions in the project area, and potential
environmental impacts. The PEA may be viewed here.
Contact Information
For questions
on the TRTP, contact:
|
|
|
|